The Cabinet noted the comments of the Business Support Overview and Scrutiny Committee as set out in the report. 156/2013 The Cabinet recommended that Full Council approve the addition of a £5.5m housing development programme to the Council’s Capital Programme funded by utilising the £5.5m borrowing Headroom available to the Housing Revenue Account. Reasons: This proposed development programme would both improve and add to the HRA’s existing housing stock, which will benefit existing tenants and Medway residents that qualify for affordable housing.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks the Cabinet’s views on a proposal to seek approval for the Housing Revenue Account (HRA) development programme to be included within the Council’s Capital Programme and to use the HRA Headroom to fund the programme.
Reports on individual HRA projects or groups of projects will subsequently be submitted to Cabinet for approval to proceed.
1. Budget and Policy Framework
1.1In accordance with the constitution, Council approval is required to set the budget and access additional funding, in this case as an addition to the Capital Programme. The Council is required under the Local Government and Housing Act 1989 to ensure that the Housing Revenue Account does not fall into a deficit position.
1.2The “HRA Headroom” must be used to create or improve an asset within the HRA Portfolio. Grant funding of non-HRA projects for development by a housing association would not be permitted.
1.3Individual schemes under this programme will be submitted to Cabinet for approval to proceed. 2. Background
2.1The new “self-financing “ regime for the HRA came into place on 1st April 2012. As part of the self-financing settlement the Council was given a maximum debt cap and the difference between this and our actual debt is known as “headroom”.
2.2The HRA headroom available as at April 2013 is £5.5m and this is estimated to increase by approximately £800,000 pa to £9.397m in year five of the programme (2017-18) once the annual provision for debt repayment has been taken into account and assuming no new borrowing is undertaken.
2.3It is proposed to increase Medway’s existing housing stock by using the available Headroom to finance a house building programme and to consider substantial remodelling or refurbishment of some existing properties where appropriate.
2.4There is also the potential to use the yearly-generated HRA revenue surplus to help fund a house-building programme, currently approximately £1.2million per year. This surplus currently part funds the additional spending requirement on the HRA planned maintenance programme.
2.5Should this proposal be approved the HRA development programme will be incorporated within the interim HRA business plan and a revised business plan will be brought forward in February 2014 as part of the Council’s budget setting exercise for the financial year 2014-15.
Options
3.1This report suggests a draft programme for future activity. The programme includes both the regeneration of currently owned assets such as existing garages and sheltered schemes as well as new development on land acquired either directly, or in partnership with local contractor/developers
3.2Do nothing This is not considered appropriate in light of Medway’s housing waiting list and strong demand for affordable housing.
3.3Develop additional housing on HRA owned garage sites This would add to Medway Council’s housing stock enabling more affordable housing to be made available to those on Medway’s housing list.
3.4Develop housing on surplus General Fund Land This would also add to Medway’s Council housing stock, however the land would need to be appropriated and the cost of the land would need to be factored into the viability of the development.
3.5The acquisition of development sites and or land and build package arrangements with contractors/developers This could represent poorer value for money because the land would need to be acquired. However it is likely that these opportunities could be brought forward within a short time frame. 3.6 Remodel homes for independent living Some of Medway’s independent living schemes are outdated and in need of either being remodelled or demolished and a new building created in its place. This would benefit residents and improve the service to customers.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.