The Cabinet noted the outcome of the contract as set out in paragraph 4.1 of the report . The Cabinet noted the Headteacher feedback as set out in paragraph 8.5 of the report . Reasons: The contract was a one off procurement, which has now finished . In addition, the project was completed to specification and within budget.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This Gateway 4 Report relates to the All Faiths Community School contract awarded to King and Johnson.
2.1.3 Contract Description
The School and Councils objectives and service delivery were met. The works were:
To deliver much needed additional teaching space of three new classrooms To provide a new hall which will not be disrupted by the main circulation of the school To demolish the existing Children’s Centre and provide a new Children’s Centre with improved storage and external learning space To allow for a new combined reception area, allowing for a stronger link between the school and Children’s Centre To provide an extra parking area and a new, safer internal road
All of these objectives were met on time.
2.2Permissions Required
This report provides Cabinet with a post project appraisal and conclude all further reporting on the basis that this contract was for a one-off requirement and the contract has fulfilled requirements in accordance with the service specification and associated contract terms and conditions. 3. Options
In arriving at the preferred option as identified within Section 4.1 ‘Preferred Option’, the following options have been considered with their respective advantages and disadvantages.
3.1Conclude Current Contract
The option of concluding the current contract at the end of the contract term on the basis that it is a one-off procurement requirement and providing an action plan for future projects has been considered and below are the advantages and disadvantages of this option:
Advantages: Works were completed on time and to budget
Disadvantages: There are no associated disadvantages with this option.
3.2Continue With Current Contract and Negate Any Further Gateway 4 or Gateway 5 Reporting Requirements
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.