157/2013 The Cabinet: (a) noted the comments of the Business Support Overview and Scrutiny Committee as set out in the report; (b) approved the Risk Management Strategy, as set out in Appendix A to the report; (c) approved the amendments to the Council’s Risk Register as detailed in section 3 of the report. Reasons: The establishment of a corporate framework for risk management was recommended by CIPFA and SOLACE and would complement and support the work already being carried out within each directorate to manage risks.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
In accordance with paragraph 4.1 of the Council’s Risk Management Strategy, this report is to discuss both the annual review of the Risk Management Strategy and the 6 monthly review of the Council’s Corporate Business Risk Register.
1. Budget and Policy Framework
1.1The Risk Management Strategy underpins all aspects of Council work and is fundamental to the Performance Plan in terms of "giving value for money”.
Background
2.1Risk Management Strategy - Cabinet undertook the annual review of the strategy on 30 October 2012 and agreed the strategy and officers’ recommendations that no significant changes needed to be made at that time.
2.2The Corporate Risk Register - was last reviewed by Management Team 20 February 2013 and Cabinet on 16 April 2013. The following changes were made to the register at that time:
2.2.1 Amend the name of SR26 ‘Maximising Outcomes for Looked after Children in the context of increasing demand’ to Children’s Social Care and increase the risk rating from B2 to A2 to reflect the fact that we are working to address the areas for improvement outlined in the recent OFSTED report and need to be alert until the programme has been fully embedded and delivered.
2.2.2 Amend the name of SR25 ‘Adult Social Care Demographics’ to Adult Social Care Transformation and increase the risk rating from C2 to B2 to reflect the fact that we are at a point of significant change and need to be alert until the programme has been fully embedded and delivered.
2.2.3 To achieve a single focused risk on Public Health issues, SR28 Changes to the Health System be merged with SR31 Public Health Transition.
2.2.4 The inclusion of a new risk SR32 that focuses on potential outsourcing issues.
2.3However, Cabinet also agreed to include the Business Support Overview and Scrutiny recommendations that:
References to the welfare reforms detailed in risks SR03b Finances - Longer Term and SR 19 Downturn in the Economy are made more explicit or create a separate risk.
Amend the title of risk SR21 Procurement to Procurement and Tendering.
SR17 Delivering Regeneration be amended or a new risk be created to reflect the impact on the Council’s regeneration programme should it be significantly affected by the current economic down-turn or market failure.
The risk rating for the new risk SR32 Outsourcing be increased from C2 to B2 and report back to BSO&S should this recommendation not be agreed.
2.3.1 Officers have amended the risks to addresses Members’ concerns.
2.4The Risk Management Audit 2010/2011 - confirmed that risk management arrangements are satisfactory. However it identified that training and arrangements regarding the creation of directorate risk registers require further development.
The Strategic Risk Management Group, in consultation with the Research and Review team (who manage Covalent), agreed a phased approach, to take this forward.
3. Advice and analysis
3.1Risk Management Strategy - The 2012-2013 audit review of risk management arrangements assessed compliance with the Council’s risk management strategy and compared the strategy against recognised good practice. The audit opinion found this to be ‘satisfactory’.
3.1.1 The Strategic Risk Management Group reviewed the risk strategy (Appendix A) in August 2013 and, in the light of the audit opinion, recommended that no significant changes need to be made at this time.
3.2The Corporate Risk Register - Risks owners have reviewed their risks and updated them as detailed in Appendix C and the following recommendations have been proposed:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.