Resolved
The Cabinet noted the outcome of the contract as set out in paragraph 4.1 of the report . The Cabinet noted the headteacher feedback in section 8.5 of the report.
Cabinet noted this item on Tuesday 1 October 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
The Cabinet noted the outcome of the contract as set out in paragraph 4.1 of the report . The Cabinet noted the headteacher feedback in section 8.5 of the report.
This report reviews the progress of the Thames View Infant & Junior Schools contract delivered through the supplier as highlighted within 2.1.2 of this report.
This is based upon the high risk classified procurement process which was undertaken during January 2011 to March 2011 and which led to an award of contract in April 2011.
The commencement and delivery of this procurement requirement was approved by the Cabinet on 18 January 2011 and subsequent approval for contract award was provided by Cabinet on 29 March 2011.
This Procurement Gateway 4 report has been approved for submission to Cabinet after review and discussion at Children and Adults Directorate Management Team meeting on 17 September 2013 and Procurement Board on 17 September 2013.
1. Budget and Policy Framework
1.1Post Project Appraisal / Contract Management
This procurement post project appraisal and its subsequent review is within the Council’s policy and budget framework and ties in with all the identified Core Values, Strategic Priorities, Strategic Council Obligations and Departmental/Directorate service plans as highlighted within the Procurement Gateway 1 Report. 1.2 Statutory Requirements
The procurement was a key project in Medway’s Primary Strategy for Change Programme, which attracted £11million of Government funding to support the Council’s strategic objective. The project was consistent with the Council’s School Organisation Plan.
Within the primary phase Medway’s School Organisation Plan principles are: • to review the future of schools with low standards; • all Infant and Junior schools should be amalgamated over time; • to review the future of schools that are at risk of becoming unviable; • to enable popular and successful schools to expand.
2.1Contract Details
2.1.1 This contract is a Works contract.
2.1.2 Supplier Details
This Gateway 4 Report relates to the Thames View Infant & Junior Schools contract awarded Coleman and James.
2.1.3 Contract Description
The School and Council’s objectives and service delivery were met. The works were to extend the nursery accommodation, improve the dropping off/ waiting area outside the nursery entrance with use of a canopy and for the Junior school building to have a new main entrance, offering a more obvious focal point for the visitors to the school and allowing sufficient space for a central hub for administrative staff for the amalgamated school.
2.2Permissions Required
This report provides Cabinet with a post project appraisal and conclude this contract on the basis that this contract was for a one-off procurement requirement and because the contract has fulfilled requirements in accordance with the service specification and associated contract terms and conditions.
In arriving at the preferred option as identified within Section 4.1 ‘Preferred Option’, the following options have been considered with their respective advantages and disadvantages.
3.1Conclude Current Contract and Provide Action Plan
The option of concluding the current contract at the end of the contract term on the basis that it is a one-off procurement requirement and providing an action plan for future projects has been considered and below are the advantages and disadvantages of this option:
Advantages: Works were completed on time Works were completed in budget
Disadvantages: There are no associated disadvantages with this option.
3.2Continue With Current Contract and Negate Any Further Gateway 4 or Gateway 5 Reporting Requirements
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Gateway 4 Procurement Post Project Completion Review: Thames View Infant and Junior SchoolsReport | 38 KB | DownloadRead as text |
Follow Cabinet at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... | Approved | Open |
| 22 Sep 2026 | Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... | Approved | Open |
| 22 Sep 2026 | Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... | Noted | Open |
| 22 Sep 2026 | Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... | Noted | Open |
| 22 Sep 2026 | Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.