78/2014 The Cabinet agreed to the commencement of the procurement process for bailiff services . Reasons: This decision is on the basis that the contract term for the current bailiff contract is due to end on 1 January 2015, and the successful collection of all monies due to the Council is necessary to ensure cash flow over coming years.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks permission to commence the procurement of Bailiff Services – Revenues and Benefits. This Gateway 1 report has been approved for submission to the Cabinet after review and discussion at Business Support Directorate Management Team Meeting on 27 February 2014 and the Procurement Board on 19 March 2014.
Further to this, current contract performance is monitored within the Exempt Appendix.
The Business Support Directorate Management Team has recommended that this project be approved as a Category B, High risk procurement.
The political and/or service sensitivities are potentially significant due to the sensitive nature of the services that will be provided on behalf of the Council.
1. Background Information
1.1Budget & Policy Framework
1.1.1 This procurement is within the Council’s budget and policy framework. The statutory duty to enforce monies owed to the Council by debtors is outlined within section 2.2 (Statutory / Legal obligations). 1.2 Service Background Information
1.2.1 Medway Council currently collects Council Tax from just over 112,000 households and National Non Domestic Rate (NNDR) from just over 6,000 business properties. The annual amount anticipated to be collected after the deduction of benefits, discounts and exemptions is £210m. In addition, approximately £500,000 of recoverable benefit overpayments are passed to debt agencies each financial year.
1.2.2 Whilst the majority of people liable for these charges pay in a timely fashion, there are a significant number who fail to do so. The Council currently employs two firms of bailiffs to encourage payment from those who continue to fail to meet their obligations.
1.2.3 The recommended option suggested by this paper will seek tenders on the basis of existing practice but will also seek tenders on any value added services that may have become available since the contract was last let.
1.3Urgency of Report
1.3.1 N/A
1.4Funding/Engagement From External Sources
1.4.1 There is no direct funding from external sources, with the cost of this service to the Council being minimal due to all costs being passed on to those people whom debts are being collected from.
1.4.2 Bailiff firms collect any outstanding balances in addition to their fees and subsequently pass on the entirety of the balance on a monthly basis to Medway Council. It is a requirement of this contract that a dedicated Medway Council bank account be maintained for the secure keeping of all monies due to the Council.
1.4.3 Following consultation at central government level and further to the Taking Control of Goods Regulations 2013 all fees as of April 2014 will be prescribed and standardised. In light of this, there is little need for an emphasis to be placed on price, allowing the Council to focus on the quality aspect in evaluating all returned tender submissions.
1.5Parent Company Guarantee/Performance Bond Required
1.5.1 The Council may require the parent company, if applicable, of any subsidiary company whose tender is accepted to guarantee the performance of the Agreement by the subsidiary company.
1.5.2 The Council retains the option to require the Contractor, at their own expense, to arrange and make known a Bond against failure for the Contract to the satisfaction of the Council for the Contract Period. The Bond will be for a sum equal to 10% of the annual value of the tender price, exclusive of the Bond. The Bond will be in the form of, or similar to, the draft.
2. Procurement Dependencies and Obligations
2.1Project Dependency
2.1.1 N/A
2.2Statutory/Legal Obligations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.