154/2014 The Cabinet agreed: (a) permission to proceed with the procurement of: (i) Low value construction/minor works framework (ii) Construction professional services consultancy framework. (b) that Gateway One and Three reports be replaced with annual summary reports to Procurement Board detailing the number of projects, total value of spend and the framework Key Performance Information (KPI) monitoring. Reasons: The decisions will reduce the reactive procurements undertaken at present whilst providing efficiencies to the Council and ensuring quality improvements over the course of the 4 year framework. Negating Gateway One and Three papers will also speed up the procurement process, enabling officers to dedicate time to more projects thereby increasing efficiency and productivity. The production of an annual summary of contracts via the framework will enable Members to monitor contract performance and have an overview of productivity.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks permission to commence the procurement of a Minor Works / Low Value Construction Framework and a Construction & Engineering Consultancy Framework. This will cover projects up to the value of £1 million. Project works values will be met within the framework value bands set at the Framework tender stage. This Gateway 1 report has been approved for submission to Cabinet after review and discussion at virtual Corporate Management Team and the Procurement Board.
The Procurement Board has recommended that this project be approved as a Category High risk procurement.
The aim of the framework is to support the local economy through the use of local SME’s where they meet the required standards. The Property and Capital Projects service sensitivities are to ensure speedy service selection. Once the framework is in place then call off from the framework will be in line with the procedures as set out in the framework.
1. Budget and Policy Framework
1.1This procurement is within the Council’s budget and policy framework.
1.2The frameworks will be financed through the various project budgets as allocated to Property and Capital Projects (P&CP). The current need is being met via an ad hoc approach and a new system has been requested by the P&CP service and agreed as best practice for delivery and service costs between P&CP and Category Management; the implementation of the frameworks will work towards giving greater transparency of projects, more responsive services to meet needs, ensuring Key Performance Indicators are used to ensure quality via direct allocation and/or mini competitions. Once in place P&CP shall select from the frameworks in accordance with framework call off procedures and inform Category Management of services being delivered by the suppliers to assist with their monitoring of KPI’s for the services. As there is no commitment to use frameworks, the Council will estimate the amount of business to be delivered through the framework via the OJEU notice.
Background
2.1PC&P and Category Management having investigated local and national framework alternatives, have agreed that a local framework best suits Medway Council’s priorities.
2.2P&CP identified through a recent alternative service model provision exercise that Medway Council are currently spending in excess of £10m per annum of low value construction projects and a further £2m per annum on project support. These needs are currently met by running repetitive tenders which are time consuming to the Council. By implementing a framework for both areas Medway Council will free up their resources and P&CP’s involvement including the assistance of Category Management in these tenders and reduce the burden of running tenders and repetitive gateway reports on each occasion and in turn provide cost savings and quality improvements. There is currently no consistency with spend and these frameworks will ensure that the best price is used across the board for the entirety of the framework agreement.
2.3The disciplines covered by these frameworks are in frequent demand and by putting in place a framework Medway Council will be able to better monitor spend and receive better supplier performance due to the supplier relationships being built in the correct manner.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
10Gateway 1 Procurement Commencement: Minor Works / Low Value Construction Framework & Construction Professional Services Consultancy FrameworkThis decision
Gateway 1 Procurement Commencement: Minor Works / Low Value Construction Framework & Construction Professional Services Consultancy FrameworkThis decision
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.