The Cabinet noted the performance of the Housing Revenue Account (HRA) Development Garage Sites and achievement of the outputs described in sections 2 and 4 of the report . Reasons: The contract, which started in July 2014, has successfully delivered the programme of works.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report sets out a review the progress of the contract currently delivered through the supplier(s) as highlighted within 1.1 of this Report.
At the Procurement Board meeting on 13 September 2013 approval was given by the Monitoring Officer, in consultation with the Procurement Board, to commence the procurement of the first two work streams within the HRA Development Programme, to create a number of affordable homes in Gillingham, Twydall and Rainham. These works will be part of the wider scheme to increase Medway’s housing stock by using HRA Headroom available to finance the house-building programme.
This paper outlines the performance of the contract awarded for the delivery of the first work stream for the construction of 23 affordable homes on a total of 10 locations in Medway, 9 of which were disused garage sites previously owned by the HRA.
The project was given the risk category of high as this is high profile procurement. It is the first development of affordable housing undertaken by Medway Council and it represents significant investment in Medway by using HR Headroom borrowing.
This Gateway 4 Report has been approved for submission to the Cabinet after review and discussion at Regeneration Community and Culture Directorate Management Team meeting on 10 December 2015 and Procurement Board on 20 January 2016. 1. BACKGROUND INFORMATION
1.1Budget & Policy Framework
1.1.1 This procurement is affordable from the use of the retained Right to Buy (RTB) 1-4-1 capital receipts and borrowing within Housing Revenue Account (HRA) Headroom.
1.1.2 At the meeting of Full Council on 17 October 2013 approval was given to include the HRA development programme within Medway’s Capital Programme and to use Headroom borrowing available to the HRA to fund the programme. The HRA Headroom fund available as at April 2013 was £5.5m which increases by approximately £0.8m through minimum repayment on the loan each year. The total budget for both phases of the new build programme is £8.6m. This also includes 32 bungalows in Beatty Avenue and one detached house at Christmas Street.
Contract Background Information
1.1.3 The project proposed to deliver 23 units in 10 locations in Medway:
Begonia Avenue Romany Road Buttermere Drive Tangmere Close Westerham Close – 2 separate sites Charing road Hazlemere Drive Eastcourt Lane Beechings Way
1.1.4 An additional 2 bedroom detached property in Christmas Street, Gillingham was given Director approval in June, added to contract, and will be handed over by May 2016.
1.1.5 All the units are designed to ensure full compliance with Lifetime Homes, Housing Quality Indicators (HQI) to measure the quality and design standards of affordable housing, Building for Life the national standard for well-designed homes and neighbourhoods, and the Homes and Communities Agency’s Design and Quality Standards to a minimum Level 3 of the Code for Sustainable Homes, thereby reducing running costs.
2. BUSINESS CASE
2.1Procurement Project Outputs / Outcomes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
18Gateway 4 Procurement Post Project Completion Review: Housing Revenue Account (HRA) Development of Garage Sites for Additional Housing StockThis decision
Gateway 4 Procurement Post Project Completion Review: Housing Revenue Account (HRA) Development of Garage Sites for Additional Housing StockThis decision
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.