129/2018 The Cabinet approved the commencement of the OJEU Framework procurement process as per the options appraisal in section 4.2 of the report. Reasons: A decision is required to allow for adequate time to have the new system in place for the school year 2019/2020. A Dynamic Purchasing System (DPS) would not allow direct awards which have been utilised heavily on the current provision. In-house provision could result in long term financial issues due to eradicating capacity. Medway Norse (option 5) would result in long term financial issues due to also eradicating capacity.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
CABINET 23 OCTOBER 2018 GATEWAY 1 PROCUREMENT COMMENCEMENT: SPECIAL EDUCATIONAL NEEDS (SEN) TRANSPORT FRAMEWORK Portfolio Holder: Councillor Andrew Mackness, Children’s Services (Lead Member)
Report from: Ian Sutherland, Director of People – Children and Adults Services
Author: Rachael Horner, Programme Lead Jo Murdoch-Goodwin, Partnership Commissioner
SUMMARY This report seeks approval to commence the procurement of Medway Council’s Home to School travel assistance. This Gateway 1 report has been approved for submission to the Cabinet after review and discussion at Children and Adults (C&A) Directorate Management Team Meeting on 14 August 2018 and the Procurement Board on 3 October 2018.
The C&A Directorate Management Team and Procurement Board have recommended that this project be approved as a high risk procurement.
1. BACKGROUND INFORMATION 1.1 Budget & Policy Framework 1.1.1 All local authorities have a statutory duty to put in place arrangements for the provision of home to school travel assistance and transport for children and young people with Special Educational Needs and Disabilities (SEND) who meet the published eligibility criteria. Section 508B and 508C of the Education act 1996 (as amended) set out the local authority’s duties and powers respectively, to make such suitable travel arrangements as the local authority considers necessary, to facilitate a child’s attendance at school. 1.1.2 Medway Council’s Education Travel Assistance policy was reviewed, updated and approved by Cabinet in April 2018. The changes made do not impact on the Council’s statutory duties or national guidance to determine eligibility for travel assistance. The policy changes were around how services are commissioned and provided locally to meet Council obligations and ensure the viability and sustainability of services. The number of eligible children requiring travel assistance, the complexity of their needs and the high cost of providing travel assistance is placing an increasing pressure on the ability of Council resources to meet their statutory requirements.
1.1.3 Medway Council has had an operational SEN Transport Framework in place since 1 September 2015. There is a proposal that a more comprehensive approach is taken to re-procuring a needs led service that is of high quality. The key drivers are to reduce costs, improve service delivery and increase the number of competitive contractors for the duration of the provision as described in this document.
1.1.4 SEN transport is currently funded from existing revenue budgets. The prediction of forecast against the current budget over the next five years is likely to continue to increase if the known demographic increases.
1.1.6 In 2017/18 the SEN transport budget was £4.402m and overspent by £0.826m. As part of the 2018/19 budget setting process, the division requested a budget increase of £1.0m to rebase and match the budget to the anticipated 2018-19 outturn forecast; the request was approved and the budget increased to £5.602m. However, after the budget was rebased, the budget was reduced to £5.250 owing to predicted savings of £0.440 which was considered achievable through the revised SEN Transport Policy and additional staffing resources to achieve the savings target. 1.2 Service Background Information
1.2.1 The Council put in place a SEN Transport Framework in 2015 which was successful and saw the managing teams nominated for national recognition due to the result. This Framework is coterminous with the academic year and due to expire at the end of the 18/19 academic year. As such a new procurement needs to be undertaken to meet the need starting September 2019. A key lesson learned from the current contract is to tailor the tolerance levels as opposed to imposing a one size fits all model.
1.3Potential procurement mechanisms
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.