55/2024 The Cabinet approved the procurement of the Refuse Collection Vehicle (RCV) fleet as per the preferred option identified in paragraph 7.2.1.3 of the report (option 3). Reasons: Approval of Option 3 (identified at paragraph 7.2.1.3 of the report) will deliver: · Best possible buyers’ terms and conditions to mitigate procurement bottlenecks as a result of increased RCV demand following October 2023 UK Government Simpler Recycling announcement. · Reduced time to market ensuring quickest transition to a new fleet with associated operational, cost and climate benefits. · Mitigation against any future inflationary pressures by locking in prices at time of order.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
12 March 2024 Gateway 1 Procurement Commencement: Replacement of the Medway Council Refuse Collection Vehicle (RCV) Fleet Portfolio Holder: Councillor Simon Curry, Portfolio Holder for Climate Change and Strategic Regeneration
Report from: Ruth Du-Lieu, Deputy Director of Place
Author: James Stubbs, Environmental Project Manager
Procurement Overview Total Contract Value (estimated): £17m. Regulated Procurement: Yes Proposed Contract Term: 30 weeks (lead time from purchase to delivery)
Summary This report seeks permission to commence the procurement of the Replacement of the Medway Council Refuse Collection Vehicle (RCV) Fleet Contract.
1. Recommendations 1.1. The Cabinet is asked to approve the procurement of the Refuse Collection Vehicle (RCV) fleet as per the preferred option identified in paragraph 7.2.1.3 of the report (option 3).
2. Suggested Reasons for decisions 2.1. Approval of Option 3 (identified at paragraph 7.2.1.3 of the report) will deliver:
• Best possible buyers’ terms and conditions to mitigate procurement bottlenecks as a result of increased RCV demand following October 2023 UK Government Simpler Recycling announcement. • Reduced time to market ensuring quickest transition to a new fleet with associated operational, cost and climate benefits. • Mitigation against any future inflationary pressures by locking in prices at time of order. • Fleet homogeny by direct award to an appropriate manufacturer ensured full flexibility to deliver the statutory waste collection service.
3. Budget and policy framework 3.1. An addition of £17m to the Capital programme was approved by Cabinet on 11 July 2023 (Decision number 106/2023) to fund the replacement of the RCV fleet.
3.2In line with this decision officers were requested to assess the appropriateness of alternative leasing solutions.
3.3Since funding approved within the Capital Programme cannot be used for such arrangements, this report assesses the appropriateness of outright purchase and phased procurement only.
3.4On 9 January 2024 Medway Council was advised of £306,900 allocated in New Burdens Capital funding for flats food waste collection vehicles and spares for the future provision under the Environment Act for new statutory food waste collections from flats.
3.5Soft market testing in August 2023 suggests that the fleet can be replaced within the £17m budget with the final figure being ascertained at Gateway 3 after procurement evaluation subject to market conditions at the time of ordering.
3.6This procurement is timebound to the end of life of existing fleet (12-24 months) and therefore extended phasing is not appropriate at this time. However, a new fleet will enable Medway to control future procurement phasing.
3.7It is necessary to treat this procurement with urgency due to the operational risk of the current fleet at the end of its operational life to discharge statutory duties.
3.8The current fleet was purchased in 2013 and has surpassed average 7- 9 year working life of RCVs and reduces the viability of a fully phased replacement at this time.
3.9Independent assessments by Medway Norse’s maintenance contractors estimated that the operational life of the majority of the fleet is now 12-24 months subject to current operational use providing the maximum period over which the procurement can be phased.
3.10Appendix 3 details an 11-month phased delivery of new vehicles enabling the capital cost to be spread over two financial years to mitigate the following risks within this time scale after an assumed 6 month lead time.
3.11There are 7 additional vehicles on spot hire in order to deliver the service fulfilling around 30,000 collections per week mainly on the refuse and organic services, as such raising the replacement priority of vehicles on these services to reduce service risk.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.