Financial Monitoring Report 2017-18 - November 2017

Noted Executive 1 paper

Cabinet noted this item on Monday 15 January 2018. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

That the financial reporting data relating to revenue budgetary control, showing a forecast net overspend at year end of £1.1million, 0.3% of the gross budget be noted. 2. That the adjustments to the Capital Programme contained in Appendix 5b to the Cabinet report be noted and the following adjustments to the Capital Programme be approved: Scheme 2017/18 Budget 2018/19 Budget 2019/20 Budget 2020/21 Budget Funding/Re-profiling Corporate Services £ £ Westminster Council Coroners Court 0 460,000 0 0 New Scheme Merton Funded Housing Company (8,238,530) 1,486,190 4,942,360 1,809,980 Re-profiling Bidding Fund (1,216,400) 1,216,400 0 0 Re-profiling Acquisitions Budget (791,770) 791,770 0 0 Re-profiling Children, Schools and Families Harris Academy Morden (50,000) (1,349,940) 1,399,940 0 Re-profiling Harris Academy Merton (220,000) 220,000 Re-profiling St Mark's Academy 0 (1,423,600) (1,128,700) 2,552,300 Re-profiling New School (566,260) 266,260 300,000 0 Re-profiling Environment & Regeneration Wimbledon Park Lake De-Silting (106,500) (1,143,500) 1,250,000 0 Re-profiling Morden Leisure Centre (705,360) 632,960 72,400 0 Re-profiling Fleet Vehicles (142,000) 142,000 0 0 Re-profiling Merton Priory Chapter House Visitors' Centre 370,370 0 0 0 HLF/S106 Funded Scheme Total (11,666,450) 1,298,540 6,836,000 4,362,280 3. That £170,540 Section 106 funding for Merton Priory Chapter House Visitor Centre for 2017/18 be approved. 1. That the financial reporting data relating to revenue budgetary control, showing a forecast net overspend at year end of £1.1million, 0.3% of the gross budget be noted. 2. That the adjustments to the Capital Programme contained in Appendix 5b to the Cabinet report be noted and the following adjustments to the Capital Programme be approved: Scheme 2017/18 Budget 2018/19 Budget 2019/20 Budget 2020/21 Budget Funding/Re-profiling Corporate Services £ £ Westminster Council Coroners Court 0 460,000 0 0 New Scheme Merton Funded Housing Company (8,238,530) 1,486,190 4,942,360 1,809,980 Re-profiling Bidding Fund (1,216,400) 1,216,400 0 0 Re-profiling Acquisitions Budget (791,770) 791,770 0 0 Re-profiling Children, Schools and Families Harris Academy Morden (50,000) (1,349,940) 1,399,940 0 Re-profiling Harris Academy Merton (220,000) 220,000 Re-profiling St Mark's Academy 0 (1,423,600) (1,128,700) 2,552,300 Re-profiling New School (566,260) 266,260 300,000 0 Re-profiling Environment & Regeneration Wimbledon Park Lake De-Silting (106,500) (1,143,500) 1,250,000 0 Re-profiling Morden Leisure Centre (705,360) 632,960 72,400 0 Re-profiling Fleet Vehicles (142,000) 142,000 0 0 Re-profiling Merton Priory Chapter House Visitors' Centre 370,370 0 0 0 HLF/S106 Funded Scheme Total (11,666,450) 1,298,540 6,836,000 4,362,280 3. That £170,540 Section 106 funding for Merton Priory Chapter House Visitor Centre for 2017/18 be approved.
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Cabinet

Recommendations

A. That Cabinet note the financial reporting data relating to revenue budgetary control, showing a forecast net overspend at year end of £1.1million, 0.3% of the gross budget. That Cabinet note the adjustments to the Capital Programme contained in Appendix 5b and approve the following adjustments to the Capital Programme 2017/18 2018/19 2019/20 2020/21 Scheme Budget Budget Budget Budget Funding/Re-profiling Corporate Services £ £ Westminister Council Coroners Court 0 460,000 0 0 New Scheme Merton Funded Housing Company (8,238,530) 1,486,190 4,942,360 1,809,980 Re-profiling Bidding Fund (1,216,400) 1,216,400 0 0 Re-profiling Acquisitions Budget (791,770) 791,770 0 0 Re-profiling Children, Schools and Families Harris Academy Morden (50,000) (1,349,940) 1,399,940 0 Re-profiling Harris Academy Merton (220,000) 220,000 Re-profiling St Mark's Academy 0 (1,423,600) (1,128,700) 2,552,300 Re-profiling New School (566,260) 266,260 300,000 0 Re-profiling Environment & Regeneration Wimbledon Park Lake De-Silting (106,500) (1,143,500) 1,250,000 0 Re-profiling Morden Leisure Centre (705,360) 632,960 72,400 0 Re-profiling Fleet Vehicles (142,000) 142,000 0 0 Re-profiling Merton Priory Chapter House Visitors' 370,370 0 0 0 Centre HLF/S106 Funded Scheme Total (11,666,450) 1,298,540 6,836,000 4,362,280

B. That Cabinet approve £170,540 Section 106 funding for Merton Priory Chapter House Visitor Centre for 2017/18.

1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY 1.1 This is the financial monitoring report for period 8, 30th November 2017 presented in line with the financial reporting timetable.

This financial monitoring report provides:-

• The income and expenditure at period 8 and a full year forecast projection. • An update on the capital programme and detailed monitoring information; • An update on Corporate Items in the budget 2017/18; • Progress on the delivery of the 2017/18 revenue savings

Page -1- 195 2. THE FINANCIAL REPORTING PROCESS

2.1The budget monitoring process in 2017/18 will continue to focus on adult social care and children’s social care as these areas overspent in 2016/17 and continue to have budget pressures.

2.2Chief Officers, together with budget managers and Service Financial Advisers are responsible for keeping budgets under close scrutiny and ensuring that expenditure within budgets which are overspending is being actively and vigorously controlled and where budgets are underspent, these underspends are retained until year end. Any final overall overspend on the General Fund will result in a call on balances as has been the case for the last two financial years, however this action is not sustainable longer term.

2.32017/18 FORECAST OUTTURN BASED UPON LATEST AVAILABLE DATA Executive summary – At period 8 to 30th November 2017, the year end forecast is a net £1.1m overspend compared to the current budget or 0.3% of the gross budget.

Summary Position as at 30th November 2017

Forecast Forecast Current Full Year Variance at Variance at Outturn Budget Forecast year end year end variance 2017/18 (Nov) (Nov) (Oct) 2016/17 £000s £000s £000s £000s £000s Department 3A.Corporate Services 11,582 11,165 (417) (383) (1,287) 3B.Children, Schools and Families 53,915 55,915 2,000 1,558 1,154 3C.Community and Housing 64,424 65,775 1,351 1,423 10,124 3D.Public Health 0 0 0 (20) 16 3E.Environment & Regeneration 23,379 22,604 (775) (520) 1,011 Overheads 0 0 0 0 12 NET SERVICE EXPENDITURE 153,300 155,459 2,159 2,058 11,030

3E.Corporate Items Impact of Capital on revenue budget 13,415 13,265 (150) (150) 193 Other Central budgets (21,707) (22,621) (914) (464) (8,329) Levies 933 933 0 0 0 TOTAL CORPORATE PROVISIONS (7,359) (8,423) (1,064) (614) (8,136)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Financial Monitoring Report 2017-18: November 2017Report 761 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 25 attended
SA
Stephen AlambritisChair, present
MA
Mark AllisonCommittee Member, present
TB
Tobin ByersCommittee Member, present
CC
Caroline Cooper-MarbiahCommittee Member, present
ND
Nick DraperCommittee Member, present
RG
Ross GarrodCommittee Member, present
EM
Edith Macauley MBECommittee Member, present
KN
Katy NeepCommittee Member, present
MW
Martin WheltonCommittee Member, present
SC
Stephen CroweGuest, in attendance
AJ
Abigail JonesGuest, in attendance
JS
John SargeantGuest, in attendance

All 25 on the meeting page

On this subject at Merton

Search all
  1. Financial Monitoring Report 2017-18 - November 2017This decision
  2. Period 3 Financial Monitoring ReportNoted
  3. Period 9 Financial Monitoring ReportNoted
  4. Period 8 Financial Monitoring ReportNoted
  5. Financial Monitoring Report 2025/26 - Period 5 (including The Merton Legacy Fund)Approved
  6. Period 3 Financial Monitoring ReportNoted

More from Merton Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Council’s New Homes ProgrammeCabinet is asked to: A. Approve the establishment of the (the Programme) as set out in this paper. B. Approve the pro... Approved Open
21 Sep 2026 Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme... Noted Open
21 Sep 2026 Property Asset Strategy Principles and corporate landlord modelCabinet is asked to: A. Approve the Property Asset Strategy principles as set out in this report. B. Agree the implem... Approved Open
21 Sep 2026 Recycling and Waste Collection Services Contract Update 2026Cabinet is asked to: A. Note the key performance indicators for the first year following the award of the contract fo... Noted Open
21 Sep 2026 Environmental Enforcement and Animal Welfare Contract – Extension and VariationCabinet is asked to: A. Approve the extension of the environmental enforcement contract (without the stray/abandoned ... Approved Open