Approved Executive 1 paper

AI summaryMerton Cabinet notes a £0.498m revenue underspend for 2025/26 and approves capital programme reprofiling, with a cumulative DSG deficit of £69.126m carried forward.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNet underspend after corporate and funding items
MoneyNot stated
What happens nextReprofile capital programme into 2026/27 onwardsSend budget adjustments into future years
Who it affectsCouncil services, schools, capital projectsTemporary accommodation, children, housing schemes

What was decided

Cabinet noted the 2025/26 revenue outturn as a net underspend of £0.498m when corporate and other funding items are included. Report P1, P35

Cabinet considered the capital programme outturn and approved the adjustments in Appendices 3b, 3c and 3c1, noting the programme requires considerable reprofiling. Report P1, P54

Why

Demand-led pressures in temporary accommodation (£7.413m unfavourable) and Children, Lifelong Learning and Families (£2.397m overspend) drove the position, partly offset by underspends elsewhere. Report P15, P27, P103

Merton's cumulative Dedicated Schools Grant deficit reached £69.126m at end of 2025/26, with Safety Valve ending and a new High Needs Stability Grant announced to cover 90% of historic deficits. Report P18, P19, P21, P126

What happens next

A SEND local reform plan must be submitted and approved to access the new High Needs Stability Grant covering 90% of eligible DSG deficits, with the Council contributing the remaining 10% locally. Report P19, P20, P129, P130, P131

Updates on SEND reform and DSG position will be provided throughout 2026/27, with further savings of £4.3m to be delivered in Adult Social Care next year. Report P22, P146

The money

  • £0.498m Net revenue underspend transferred to reserves Report P35, P36
  • £69.126m Cumulative DSG deficit at end of 2025/26 Report P18, P128
  • £7.413m Unfavourable variance on temporary accommodation Report P27
  • £2.397m Overspend in Children, Lifelong Learning and Families Report P27, P93
  • £15.570m In-year DSG deficit for 2025/26 Report P123, P128
  • £4.9bn National funding package for SEND deficits Report P20

Options considered

  • Chosen: Approve the capital programme adjustments in Appendices 3b, 3c and 3c1 and reprofile into future years. To align the capital programme with actual delivery and rephase slipped schemes into 2026/27 onwards Report P1, P54
  • Chosen: Note the revenue outturn as a £0.498m net underspend. Required to confirm the financial position for 2025/26 including corporate and funding items Report P1, P35

Implications

  • Financial: Adult Social Care must deliver £4.3m of savings in 2026/27 alongside continued demand and complexity pressures. Report P146
  • Legal: A statutory override separates DSG deficits from wider council finances until March 2028, but a local 10% contribution is still required for the High Needs Stability Grant. Report P17, P20, P131
  • Risk: Temporary accommodation costs surged in 2025/26, contributing £7.413m of unfavourable variance despite a recovery plan and Cabinet-approved housing crisis response. Report P15, P27, P30
  • Staffing: Several directorates reported underspends driven by vacancies and held posts, including Resources, Human Resources, and Communications and Engagement. Report P68, P81, P84

Who and where

  • Residents in temporary accommodation, facing ongoing cost pressures and a comprehensive recovery plan Report P15, P30
  • Children in care and families, with rising placement costs and a new in-house children's home feasibility work Report P100, P101, P103, P133
  • Schools and pupils with SEND, dependent on the High Needs Stability Grant and the new SEND local reform plan Report P19, P129, P130
  • Council departments and capital scheme managers delivering Housing and Sustainable Development projects including Mitcham Gas Works and temporary accommodation purchases Report P47, P50

Timeline

  • 2025/26 financial year: Revenue outturn delivered a £0.498m net underspend after corporate and funding items Report P35
  • End of 2025/26: Cumulative DSG deficit reached £69.126m and Safety Valve programme ended Report P18, P21, P128
  • January 2026 (Period 10): Previous monitoring period against which outturn movements are reported Report P27, P33
  • 25th Feb 2026: Budget Council approved the MTFS 2026/30 incorporating Fair Funding Review 2.0 impact Report P26
  • March 2028: Statutory override separating DSG deficits from council finances currently expected to end Report P17, P131

Plain English for the jargon

  • DSG: Dedicated Schools Grant, government funding for schools split into four blocks, with the High Needs Block in deficit
  • Safety Valve: Department for Education programme for councils with significant DSG deficits, ending for Merton at the close of 2025/26
  • High Needs Stability Grant: New government grant covering 90% of eligible historic DSG deficits, subject to a SEND local reform plan
  • MTFS: Medium Term Financial Strategy, the council's multi-year financial planning document
  • SEND: Special Educational Needs and Disabilities, services for children and young people with additional needs
  • Statutory override: Government accounting measure separating DSG deficits from wider council finances, in place until March 2028
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

A That Cabinet note that the financial outturn position on revenue for 2025/26 is showing a net underspend of £0.498m when corporate and other funding items are included. B That Cabinet consider the outturn position on the Capital Programme and approve the adjustments to the capital programme in Appendix 3b, 3c and 3c1 and note that the programme requires considerable reprofiling. A That Cabinet note that the financial outturn position on revenue for 2025/26 is showing a net underspend of £0.498m when corporate and other funding items are included. B That Cabinet consider the outturn position on the Capital Programme and approve the adjustments to the capital programme in Appendix 3b, 3c and 3c1 and note that the programme requires considerable reprofiling.
Word for word from the decision Merton published for this meeting. Source: democracy.merton.gov.uk

Follow this further

Built from Merton's papers

What the report saysPro

Report to Cabinet

Recommendations

A That Cabinet note that the financial outturn position on revenue for 2025/26 is showing a net underspend of £0.498m when corporate and other funding items are included. B That Cabinet consider the outturn position on the Capital Programme and approve the adjustments to the capital programme in Appendix 3b, 3c and 3c1 and note that the programme requires considerable reprofiling.

Page 127 Report summary and relevance to strategic priorities

Executive summary

2.1This report outlines the outturn position for the financial year (2025/26) and the issues that arise from it. The report: • Summarises the revenue outturn position of the Authority. • Reviews the detailed outturn position for service departments. • Reviews the outturn position for corporate items. • Provides information on Reserves. • Provides information on the capital outturn. • Reviews the progress on savings position.

3. Relevance to strategic priorities, including Council Plan priorities

Strategic priority Relevant Brief explanation of relevance

Building a sustainable x The report outlines the forecast financial future position of the Council for the year ending 31 March 2026. The financial health and sustainability of the authority underpin every area of the Council’s services and is therefore vital for delivering against the Council’s strategic priorities. Nurturing civic pride

Other service delivery priority

Organisational development

to strategic priorities, priorities

Page 128 Background, options and next steps

4. Introduction and background

Chief Officers, together with budget managers and with support from finance officers, are responsible for keeping budgets under scrutiny and ensuring that expenditure within areas which are above budget is being actively and vigorously controlled. Any final overall variance on the General Fund will result in a call or transfer to reserve balances.

5. 2025/26 Revenue Outturn 6. O Executive Summary

Local authorities operate in a highly challenging financial climate, with forecasts highly sensitive to interest rate and inflation fluctuations. Uncertainty caused by macroeconomic and geopolitical factors complicates forward funding, pay, and inflation projections.

Merton Council faces unprecedented pressures in demand-led services such as adults and children’s social care and homelessness. Temporary accommodation costs surged sharply during 2025/26, contributing to the position, despite the Council having relatively low numbers in temporary accommodation compared to other London boroughs. Actions to mitigate these pressures were implemented and will continue, as managing these challenges is critical for financial stability.

DSG

A significant financial challenge is the Dedicated Schools Grant (DSG) High Needs budget, which has been in deficit since 2018/19. Merton joined the Department for Education’s High Needs Safety Valve programme in 2022 due to its significant deficits. The government introduced a statutory override to separate DSG deficits from broader council finances, extended until March 2028, which provides an accounting solution to the problem but does not solve the funding problem.

The cumulative DSG deficit at the end of 2025/26 is £69.126m.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Outturn Report 2025/26Report 1.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 22 attended
SE
Sharon EvansCouncil Staff, in attendance
LA
Lewis Addlington-LeeCouncil Staff, expected
RG
Ross GarrodChair, present
ES
Eleanor StringerCommittee Member, present
CC
Caroline Cooper-MarbiahCommittee Member, present
AJ
Andrew JudgeCommittee Member, present
SK
Sally KennyCommittee Member, present
PM
Peter McCabeCommittee Member, present
UK
Usaama KaweesaCommittee Member, present
TO
Test OfficerCouncil Staff, expected
EM
Edith Macauley MBECommittee Member, present
SN
Stuart NeaversonCommittee Member, present

All 22 on the meeting page

On this subject at Merton

Search all
  1. Outturn Report 2025/26This decision
  2. Financial Outturn Report 2024/25 - Capital Programme Amendments Requiring Council ApprovalApproved
  3. Outturn Report 2024/25Noted
  4. Outturn Report 2023/24Noted
  5. Outturn 2022/23 ReportApproved
  6. Outturn 2021/22 ReportNoted

More from Merton Cabinet

All decisions
MeetingDecisionOutcome
21 Sep 2026 Council’s New Homes ProgrammeCabinet is asked to: A. Approve the establishment of the (the Programme) as set out in this paper. B. Approve the pro... Approved Open
21 Sep 2026 Morden Town Centre RegenerationCabinet is asked to: A. Note the progress made on the Programme since Cabinet approved the procurement of a developme... Noted Open
21 Sep 2026 Property Asset Strategy Principles and corporate landlord modelCabinet is asked to: A. Approve the Property Asset Strategy principles as set out in this report. B. Agree the implem... Approved Open
21 Sep 2026 Recycling and Waste Collection Services Contract Update 2026Cabinet is asked to: A. Note the key performance indicators for the first year following the award of the contract fo... Noted Open
21 Sep 2026 Environmental Enforcement and Animal Welfare Contract – Extension and VariationCabinet is asked to: A. Approve the extension of the environmental enforcement contract (without the stray/abandoned ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies