AGREED that the contents of the report and the ongoing work of the planning enforcement team be noted. Further information on how developments are considered to be breaches, but not expedient to take action is requested as part of the next performance report as well as the process for enforcement investigations. Member questioned whether the public and ward members could be consulted/notified of breaches.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
This report relates to the first quarter from the 1st April to the 30th June 2023 and provides an update on enforcement activity during this period, including cases where formal action has been taken. It also includes case studies which show how the breaches of planning control have been resolved through negotiation, and where Notices that have been complied with.
Schedule A outlines the enforcement activity for Q1 in terms of the numbers of cases that have been received and closed (Chart 1) and also provides a breakdown of the reasons that cases have been closed (Chart 2). Chart 4 details the performance of the enforcement team when compared against time limits set out within the Newark and Sherwood District Planning Enforcement Plan (PEP) and Chart 5 charts the overall performance since the targets were introduced in September 2020.
Schedule B includes a small number of examples of where formal planning enforcement action has been taken (such as a notice being issued).
Schedule C provides just a few examples of how officers have resolved breaches through dialogue and negotiation during the last quarter. 2.0 Schedule A – Outline of Enforcement Activity
Members will note from Chart 1 that the Planning Enforcement team, now made up of four members of staff, continue to receive a high number of alleged breaches that need investigating, having received more cases in Q1 of 2023 than during the same period in 2021 and 2022. This follows an unusually busy Q4, for which many of the cases received during that period continue to be addressed in Q1; either through formal action or ongoing investigation.
Chart 2 details the number of enforcement cases that have been received and closed, since Q2 in 2021. The figures demonstrate that the team has continued to be busy with a high number of cases which are continuing to prove to be complex and require significant officer resource.
Case Numbers Received and Closed During Q1 50 47 46 45 37 Number of ENF cases
40 33 35 30 25 21 20 17 15 10 5 0 April May June
Received Closed
Chart 1
Chart 2
Members will note from Chart 3 that almost 75% of cases that were closed during Q1 were so because they were either not a breach of planning control (including instances where works being undertaken did not require consent or where there was already planning permission granted) or because a breach has been resolved, either through dialogue or formal enforcement action. Although many cases are not a breach of planning control, they nevertheless often still require significant investigative work from officers, including site meetings and desk-based assessments to establish that this is the case.
Reasons for Case Closures During Q1
13 38
No Breach Breach Resolved Breach No Further Action Other
Chart 3
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.