What was decided
Councillors noted housing compliance exceptions for 2025/26 across gas, fire, asbestos, water, electrical, stairlifts, solid fuel and oil servicing. Report 2.1, 2.2, 2.3, 2.8
They noted interim arrangements for monitoring damp and mould ahead of Awaab's Law, including a new triage process and a dedicated damp and mould manager. Report P19, P20
They noted ongoing actions to improve and maintain performance, with new housing management system reporting interim arrangements in place. Report 1.5
Why
Several compliance areas sat outside the council's target parameters during 2025/26, particularly solid fuel and oil servicing (rated Red) and several other areas (Amber). Report 2.1, 2.8
A new housing management system is being embedded and Phase 2 of the Social Housing (Regulation) Act, likely from October 2026, will extend statutory hazards covered. Report 1.5, 1.6, P8
The council wants oversight of health and safety performance at board level and assurance that exceptions are being actively managed. Report 1.1, 1.3
What happens next
Complete the remaining 2 non-compliant EICR properties, with one progressing via legal action. Report P16
Achieve 100% domestic asbestos compliance by the end of the financial year, with 81 properties still outstanding at year end. Report P13
Continue interim damp and mould reporting until new system functionality is aligned to Awaab's Law and Phase 2 regulatory requirements. Report 1.5, P20
Options considered
Chosen: Continue strengthened no-access processes and cross-team working for gas, electrical and other compliance programmes. Drove compliance improvements and reduced non-compliant cases over the year Report 2.1, P16
Chosen: Maintain interim damp and mould monitoring arrangements. New housing management system functionality not yet fully aligned to regulatory requirements Report 1.5
Chosen: Centralise asbestos management within the Compliance Team from 1 May 2025. Strengthened oversight and improved domestic compliance from 95.01% to 98.41% Report P13
Implications
Legal: Council must meet landlord responsibilities under the Social Housing (Regulation) Act, with Phase 2 likely from October 2026 adding new statutory hazards. Report 1.6, P8
Staffing: A dedicated damp and mould manager has been appointed, leading surveyors and operatives focused on these cases. Report P20
Risk: Solid fuel servicing was rated Red at 90% compliance, with oil servicing at 95.74%; data quality and asset records are under continuous review. Report 2.8
Other: Interim reporting arrangements remain in place pending full embedding of the new housing management system. Report 1.5
Who and where
Tenants in 386 properties who reported damp and mould between 27 October 2025 and March 2026 Report 2.9
Residents of 106 residential blocks and around 31 community centres covered by fire risk assessments Report 2.2
Tenants in properties with outstanding asbestos, EICR, hoist, solid fuel or oil servicing compliance Report 2.6, 2.8
Timeline
January 2025: Asbestos surveys undertaken for all blocks and community centres Report P13
From 1 May 2025: Asbestos management centralised under the Compliance Team
Between 27 October 2025 and March 2026: 386 damp and mould reports received and 1,635 works orders raised Report 2.9
From November 2025: Multi-service water safety delivery model mobilised, integrating with annual gas servicing Report 2.5
Likely October 2026: Phase 2 of the Social Housing (Regulation) Act expected to take effect, extending statutory HHSRS hazards Report 1.6
Plain English for the jargon
Awaab's Law: Legal requirements placing time limits on social landlords to fix hazards such as damp and mould, referenced as upcoming.
HHSRS: Housing Health and Safety Rating System, the national standard for assessing housing hazards.
EICR: Electrical Installation Condition Report, a safety check of a property's electrical systems.
FRA: Fire Risk Assessment, a review of fire safety in residential blocks and community buildings.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item250
Resolved
AGREED (unanimously) that the following be noted: a) the exceptions to performance of the housing service compliance functions for the financial year 2025/2026; b) the interim arrangements for monitoring damp and mould ahead of the introduction of Awaab’s Law; and c) the ongoing actions to improve and maintain performance.
Word for word from the decision Newark and Sherwood published for this meeting.Source: democracy.newark-sherwooddc.gov.uk
Report to Policy & Performance Improvement Committee
Background
This report provides Members with the performance of housing compliance services for the financial year 2025 - 2026, focusing on exceptions performance, which is outside the Council’s target parameters.
1.1The full performance summary is shared with SLT; the Portfolio Holder for Housing and discussed as a standard agenda item for the Tenant Influence & Assurance Board meetings ensuring that Health & Safety are at the heart of our conversations and actions. Performance is also discussed at Policy and Performance Committee (PPIC) before being presented quarterly at Cabinet (Performance) to ensure there is oversight at Board level. 1.2 This report sets out the Council’s performance against the Council’s legal and regulatory landlord responsibilities for a range of building safety measures including fire protection, gas, asbestos, electrical and water. Further information on the Council’s responsibilities can be found here: https://www.gov.uk/government/publications/safety-and-quality-standard
1.3The Council’s performance in the report is rated as set out in the table below - as recommended by external auditors and the Regulator of Social Housing:
RAG Rating Old Rating New Rating Colour in 2023/24 2024/25 Appendix Report Green At Target 100% Amber Within 2% 98 – 99.9% Red Below 2% 0 – 97.99%
1.4The report also includes a summary of the damp and mould cases for 2025 to 2026 outlining key operational metrics, including inspection volumes, works orders raised and completed, delivery timescales. Performance as a comprehensive overview of service delivery effectiveness and resource allocation.
1.5Following the implementation of the new Housing Management System, interim reporting arrangements remain in place. Ensuring continued oversight of damp and mould activity while system functionality is embedded and aligned to emerging regulatory requirements. Transitioning to a more automated and consistent framework, to strengthen data quality and performance visibility whilst keeping in site Phase 2 impact. Phase 2’s implication will affect operational service deliverables and the development of Housing Management System.
1.6Phase 2 of the Social Housing (Regulation) Act has a likely implementation date of October 2026, the purpose is to expand the scope of requirements to include additional Housing Health and Safety Rating System (HHSRS) hazards enforcing identified hazards to a statutory time-bound repair for:
• Excess cold / excess heat • Falls (stairs, level surfaces • Structural collapse / explosions • Fire and electrical hazards • Domestic hygiene, pests and food safety
2.0Performance Report Details
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy & Performance Improvement Committee at Newark and Sherwood and we tell you when its next papers are published, before the meeting rather than after it.
Q4 Community Plan Performance ReportAGREED (unanimously) that: a) the Community Plan Performance, the Annual Community Plan Performance and the Complianc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.