Resolved
Resolved : That the report on the delivery of the Town Deal and Future High Street Funds projects be noted. Watch the debate here
Finance, Assets & Performance Scrutiny Committee noted this item on Wednesday 18 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved : That the report on the delivery of the Town Deal and Future High Street Funds projects be noted. Watch the debate here
That
1. Scrutiny Committee notes this report on the delivery of the Town Deal and Future High Street Funds projects.
Reasons
To update the Scrutiny Committee on the progress with the various projects that are being funded or part funded through the two Town Deals – Newcastle and Kidsgrove, and the Future High Street Funds for Newcastle Town Centre.
1.1As reported to previous Scrutiny meetings, the Council has secured Future High Street Funding and Town Deal Funds for the redevelopment of several key regeneration sites across the Town Centre and the wider Borough.
2. Updates
2.1Future High Street Fund
Work has been continuing in the development of the schemes for the past couple of years, and the current position regarding each is as follows:
2.1.1 Market improvements
The contract for public realm works to lower High Street completed in August and the benching and planters are due early September. As previously reported 18 fixed Classification: NULBC UNCLASSIFIED
stalls have been removed, leaving 27 fixed stalls which have had new canopies fitted and some have been relocated into more appropriate areas. New temporary stalls have arrived for markets which require more than the remaining 27 fixed stalls.
2.1.2 York Place
The demolition / strip out contract for the removal of the building fabric, exposing the framework for future development commenced in September 2024, in readiness for the build out stages once planning permission is agreed and construction costs are finalised. Planning permission is due to be submitted in September.
Ryecroft
2.1.3 Castle Car Park
Construction continues on the project with completion due in late November 2024. The ticketing system and highworks to the entrance and former site entrance have been ordered. The EV Charging are being installed (Funding £12m (£3.50m from FSHF). Classification: NULBC UNCLASSIFIED
2.1.4 McCarthy and Stone Residential Development
McCarthy and Stone signed a land acquisition agreement with the Council in August and are now working on the preparation of a planning application for the new development.
2.1.5 New Hotel
Capital and Centric are continuing their design feasibility works for the whole Ryecroft site which will include the new Hotel build, which is now anticipated to be developed on the corner of Merrial St and Corporation St. A planning application is due to be submitted as part of the wider Ryecroft development submission, due in September 2024.
2.1.6 Aspire Housing
Aspire have agreed with Capital and Centric a site boundary and the works that will be undertaken to develop out residential units.
2.2Newcastle Town Deal
2.2.1 Midway Car Park
Capital and Centric have been developing plans for the re-development of the Midway structure, based around the principle of retaining the concrete frame and floors and re-engineering the structure for residential purposes and are due to submit a planning application for the works in September 2024.
2.2.2 Astley Performing Arts Centre
The Philip Astley CIC are continuing their investigation for Phase 2 for the circus skills training space, for ariel work etc. It is unlikely to be within the remodelled York Place due to the 6.5m height requirements. Classification: NULBC UNCLASSIFIED
2.2.3 Knutton and Chesterton
Knutton
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
TOWN DEAL AND FUTURE HIGH STREET FUND UPDATEReport | 654 KB | DownloadRead as text |
Follow Finance, Assets & Performance Scrutiny Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of a previous meetingResolved : That the minutes of the meeting held on 26 th March 2026 be agreed as a true and accurate record. Watch th... | Agreed | Open |
| 2 Jul 2026 | Work programmeThat the work Programme be noted and the additions be received. Watch the debate here | Noted | Open |
| 26 Mar 2026 | Minutes of a previous meetingResolved : That the minutes of the meeting held on 15 th January 2026 be agreed as a true and accurate record. | Agreed | Open |
| 26 Mar 2026 | Financial and performance review report - third quarter 2025/26Resolved : That the contents of the report and appendices be noted and that the Council’s service and financial perfo... | Noted | Open |
| 26 Mar 2026 | Town deal and future high street funds updateResolved : That the report on the delivery of the Town Deal and Future High Street Funds projects be noted. Watch the... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.