Resolved
Resolved : That the report on the delivery of the Town Deal and Future High Street Funds projects be noted. Watch the debate here
AI summaryNewcastle-under-Lyme scrutiny committee notes progress on Town Deal and Future High Street Funds, with £11.0m FHSF fully spent and major works underway at Astley Place, Ryepark and Karparc.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Resolved : That the report on the delivery of the Town Deal and Future High Street Funds projects be noted. Watch the debate here
That:-
1. Scrutiny Committee notes this report on the delivery of the Town Deal and Future High Street Funds projects.
Reasons
To update the Scrutiny Committee on the progress with the various projects that are being funded or part funded through the two Town Deals – Newcastle and Kidsgrove, and the Future High Street Funds for Newcastle Town Centre.
1.1As reported to previous Scrutiny meetings, the Council has secured Future High Street Funding and Town Deal Funds for the redevelopment of several key regeneration sites across the Town Centre and the wider Borough.
2. Updates
2.1Future High Street Fund
Work across this programme has now completed and the fund is spent. The current (and final) position regarding each is as follows:
2.1.1 Market improvements
Works to the digital screen, benching and planters has now been completed and are operational with content promoting the Council and BID priorities and will be showing
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
adverts after the Christmas period bringing in income. It is also planned to show movies and events on the screen on special occasions. 2.1.2 Astley Place
Capital&Centric and their contractor AC1 have commenced works (October 2025) with the development due to be completed in November 2026.
RyePark
2.1.3 Castle Car Park
The new car park has now opened and is fully operational and continues to be used regularly by visitors to the Town Centre.
2.1.4 McCarthy and Stone Residential Development
McCarthy and Stone’s planning application was approved by the planning committee at its April 25 meeting. It is now anticipated that the works will commence in the autumn of 2025 with completion in later 2026 at the same time as the Capital&Centric works.
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
2.1.5 Ryepark
Capital&Centric have now appointed Henry Boot to undertake the Ryepark constructions works. Site clearance and ground works commenced in October 2025 and completion is expected in late 2026.
2.2Newcastle Town Deal
2.2.1 Karparc
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
As with the previous schemes noted above Capital&Centric have now appointed Glegg Construction to undertake the works to this development. Works started in early November and will be completed by the summer of 2027.
2.2.2 Astley Performing Arts Centre
This Centre is now open and operational. 2.2.3 Knutton and Chesterton
Knutton
Aspire have commenced works on the residential development at High Street.
Works on the former community centre site development by Aspire commenced with ground works on October 2025.
Classification: NULBC UNCLASSIFIED Classification: NULBC UNCLASSIFIED
The extension to the Enterprise Centre Is now substantially complete and has been awaiting the connection to a sub-station before the units can be occupied. This connection will now take place in Mid-December so the units should be handed over for occupation in the new Year.
The plans for a village hall have been adapted to incorporate new enterprise units with a community facility available for hire within the structure / development. The scope of the works has altered as no community group was identified to operate the new facility. The scheme is being priced up in order to give an indication to the Town Deal Board for its consideration later in the year.
The development of the football changing rooms at the Wammy is now complete and Newcastle Town Football Club are operating the facility.
Cross Street Chesterton
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
TOWN DEAL AND FUTURE HIGH STREET FUNDS UPDATEReport | 7.2 MB | DownloadRead as text |
Follow Finance, Assets & Performance Scrutiny Committee at Newcastle-under-Lyme and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of a previous meetingResolved : That the minutes of the meeting held on 26 th March 2026 be agreed as a true and accurate record. Watch th... | Agreed | Open |
| 2 Jul 2026 | Work programmeThat the work Programme be noted and the additions be received. Watch the debate here | Noted | Open |
| 26 Mar 2026 | Minutes of a previous meetingResolved : That the minutes of the meeting held on 15 th January 2026 be agreed as a true and accurate record. | Agreed | Open |
| 26 Mar 2026 | Financial and performance review report - third quarter 2025/26Resolved : That the contents of the report and appendices be noted and that the Council’s service and financial perfo... | Noted | Open |
| 26 Mar 2026 | Town deal and future high street funds updateResolved : That the report on the delivery of the Town Deal and Future High Street Funds projects be noted. Watch the... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.