Q3 UPDATE ON COUNCIL DELIVERY PLAN

Noted Executive 2 papers

Cabinet noted this item on Tuesday 14 March 2023. Below is the council's own wording, with the papers it was decided on.

Item179

Resolved

That Cabinet noted the: (1) Progress against Council projects as set out in the Council Delivery Plan (Appendix A) including changes to milestone dates and risks. (2) Completion of the Business Recovery Grants, EV Charging for Council Vehicles and the Help Residents make payments at convenient Location milestones for this year. (3) Reduction in the Local Plan risk score from a 9, to a risk score of 6 following the end of the Judicial review period. REASONS FOR DECISIONS: The Council Delivery Plan (CDP) monitoring reports provide Cabinet with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities. That Cabinet noted the: (1) Progress against Council projects as set out in the Council Delivery Plan (Appendix A) including changes to milestone dates and risks. (2) Completion of the Business Recovery Grants, EV Charging for Council Vehicles and the Help Residents make payments at convenient Location milestones for this year. (3) Reduction in the Local Plan risk score from a 9, to a risk score of 6 following the end of the Judicial review period. REASONS FOR DECISIONS: The Council Delivery Plan (CDP) monitoring reports provide Cabinet with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet, 5 pages

Executive summary

This report presents progress on delivering the Council Delivery Plan for 22-23 at the end of Quarter 3, which includes:

• Progress against the completion of Council projects and milestones • Requests to change milestone dates • Commentary on progress made and any new issues, risks, or opportunities

Recommendations

2.1That Cabinet notes the progress against Council projects as set out in the Council Delivery Plan (Appendix A) including changes to milestone dates and risks. 2.2. That Cabinet notes the completion of the Business Recovery Grants, EV Charging for Council Vehicles and the Help Residents make payments at convenient Location milestones for this year. 2.3. That Cabinet notes the reduction in the Local Plan risk score from a 9, to a risk score of 6 following the end of the Judicial review period.

Reasons for recommendations

3.1The Council Delivery Plan (CDP) monitoring reports provide Cabinet with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities.

Alternative options considered

4.1In developing the CDP, it was agreed that Cabinet would receive quarterly updates. The updates are also provided to Overview and Scrutiny Committee so that they can provide additional oversight and support to Cabinet. 5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Service Directors and Service Managers have provided updates on progress and will have made Executive Members (and Deputies) aware of progress made.

5.2A draft of the Quarter 3 update was provided to Risk Management Group (RMG) in February. The Group has a standing invite to the Executive Member for Finance and IT (has responsibility for performance monitoring), the Deputy Executive Member for Finance and IT, the Chair of Overview and Scrutiny (O&S) and the Chair of Finance, Audit and Risk Committee (FAR). Other members of O&S and FAR are also encouraged to attend when they can. RMG were asked to comment on the content and format of the CDP Q3 update.

5.3The CDP is reviewed by Overview and Scrutiny Committee, and they are asked to provide comments and recommendations to Cabinet.

6. FORWARD PLAN

6.1This report contains a recommendation on a key Executive decision first notified on the Forward Plan on the 23 January 2023.

Background

7.1The CDP brings together projects, risks, and performance indicators together in one document. It was adopted by Cabinet in March 2022, which included the projects to be included within the CDP.

8. RELEVANT CONSIDERATIONS

8.1Appendix A provides an update on the progress made in delivering the Council Delivery Plan. Whilst it is labelled as a Quarter 3 update, it generally reflects the latest position at the time that the report was written (mid-February).

8.2Cabinet are asked to approve the following:

• The proposed change to current milestone dates for Town Centre Recovery, , Cycling Networks, Town Centre Strategies, Empty Homes Strategy and Museum Storage with reasons detailed in Appendix A.

• The progress made to date against each project and resulting impacts on future milestones, as detailed in the commentary against each project in Appendix A. Future updates will provide monitoring against any revised milestones.

8.3Cabinet are asked to note the following: • The Completion of the Business Recovery: Grants, the EV Charging for Council Vehicles and the Help Residents make payment at convenient location milestones for this year.

8.4The intention is that the CDP reports provide an overview, as providing all the details on project milestones would lead to a report that was too long. Requests can be made (especially by O&S) to look at individual projects in more detail. Any such request would be incorporated into the next monitoring report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Council Delivery Plan 22-23 Q3 monitoring report.pdfAppendix A 23 pages Download
PDF
Q3 UPDATE ON COUNCIL DELIVERY PLANReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. Q3 UPDATE ON COUNCIL DELIVERY PLANThis decision
  2. 2026-27 q1 council delivery plan updateNoted
  3. Council delivery plan 2025-26 (quarter 3 update)Noted
  4. Council delivery plan 2025-26 (q3 update)Approved
  5. Council delivery plan 2025-26 (quarter 2 update)Noted
  6. Council delivery plan 2025-26 (quarter 2 update)Approved

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open
22 Sep 2026 Public participationThe Chair invited [name removed] to provide a 5-minute verbal presentation relating to Agenda Item 8 – Local Plan – C... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies