COUNCIL DELIVERY PLAN 2025-26 (Q3 UPDATE)

Approved Scrutiny 2 papers

AI summaryNorth Herts Overview and Scrutiny Committee reviews Q3 progress on 13 Council Delivery Plan projects, with two amber and four red-risk projects, and recommends Cabinet note progress and approve milestone changes.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRecommended Cabinet notes progress and approves milestone changes
MoneyNo direct financial implications from the report
What happens nextCabinet to consider recommendationNext quarterly monitoring report to follow
Who it affectsCouncil projects and services13 projects, 14 KPIs, 17 risk entries monitored

What was decided

The Committee provided comment on the Council Delivery Plan Quarter 3 monitoring report. Report 2.1

The Committee recommended that Cabinet notes progress against Council projects and performance indicators, and approves new milestones and changes to milestones. Report 2.1

Why

Quarterly monitoring gives the Committee and Cabinet oversight of progress against key projects, and highlights new issues, risks or opportunities. Report 3.1, 4.1

It was agreed Cabinet would receive quarterly updates, with Overview and Scrutiny providing additional oversight, so no alternative options were considered. Report 4.2

What happens next

Cabinet will be asked to approve any changes to milestones following prior review by Overview and Scrutiny.

The Committee may ask for more detail on any project, provided as a written update or in the next quarterly report. Report 2.2, 8.11

Most new KPIs linking to Council Plan actions are expected to appear in the year-end monitoring report with 2025-26 data. Report 8.9

Options considered

  • Chosen: Quarterly CDP update to Cabinet with prior Overview and Scrutiny review. Provides Cabinet oversight plus additional scrutiny Report 4.1, 4.2

Implications

  • Legal: No direct legal implications; robust monitoring supports the best value duty under Section 3 of the Local Government Act. Report 9.3, 9.4
  • Equalities: No direct equalities implications arising from the report. Report 12.2
  • Risk: Four projects are rated high (red) risk: Churchgate, Decarbonisation of Council Buildings Phase 2, Local Plan Review, and Museum Collection Facility. Three of four corporate risks are red; Financial Sustainability is amber. Report P4, 8.7, 8.8
  • Staffing: Careline installation performance is held back by two technicians on office-based duties and Christmas leave; new technician recruitment is underway. Report P26
  • Other: Three KPIs are red: two Careline installation measures and the percentage of Customer Service Centre calls answered in 45 seconds. Report P4, 8.4, P26, P27
  • Other: No direct financial, social value, human resources, or environmental implications arise from the report itself. Report 10.1, 13.1, 14.1, 15.1

Who and where

  • Cabinet Report 4.1
  • Overview and Scrutiny Committee Report 3.1, 5.3
  • Risk and Performance Management Group (RPMG) Report 5.2
  • Residents waiting for Careline installations Report P26
  • Callers to the Council's Customer Service Centre Report P27
  • Users of domestic waste collection services across East and North Herts Report 8.6

Timeline

  • February 2026: Draft Q3 update considered by the Risk and Performance Management Group. Report 5.2
  • 26 February 2026: Engaging the community on our finances project completed following approval of the 2026-27 budget at Full Council. Report P4
  • early March 2026: Report prepared, reflecting latest position. Report 8.1
  • end of March 2026: Professional Technical Services contractor for Museum Collection Facility expected to be appointed. Report 8.2
  • 12 March 2026: New Safety Advisory Group (SAG) platform go live (delayed). Report 8.3
  • 31 March 2026: Target date for completing waste process TechnologyOne automations (delayed). Report 8.3
  • May 2026: Churchgate soft market testing at UKREiiF. Report 8.3
  • June 2026: Expected presentation of Churchgate reports to relevant committees. Report 8.3
  • Summer 2027: Current estimate for completion of Museum Collection Facility renovation, followed by relocation of the collection. Report 8.2

Plain English for the jargon

  • CDP: Council Delivery Plan, the document bringing together projects, risks, and performance indicators.
  • KPI: Key Performance Indicator, a measure of Council performance rated green, amber, or red.
  • RPMG: Risk and Performance Management Group, an internal group consulted on the draft Q3 update.
  • SAG: Safety Advisory Group, a new platform delayed to 12 March 2026.
  • UKREiiF: UK Real Estate Investment and Infrastructure Forum, the May 2026 event at which Churchgate soft market testing will take place.
  • CSC: Customer Service Centre, the Council's main contact centre.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item72

Resolved

That the Overview and Scrutiny Committee provided comment on the Council Delivery Plan Quarter 2 monitoring report. RECOMMENDED TO CABINET: That Cabinet notes progress against Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A), and approves new milestones and changes to milestones. REASON FOR RECOMMENDATION: The Council Delivery Plan (CDP) monitoring report provides the Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Overview and Scrutiny Committee, 8 pages

Executive summary

This report presents progress on delivering the Council Delivery Plan for 2025-26. This is a Quarter 3 update but generally reflects progress up to the point that the report was prepared (early March 2026). The report includes:

• For the projects identified by Cabinet, it details milestones and progress against them. • The risks in relation to the delivery of those projects, as well as the corporate risks that could impact the delivery of all our projects and services. • Latest data for the Council’s key performance indicators (KPIs).

Points to note:

• A new item relating to the Museum Collection Facility project and associated risks has been added to the Council Delivery Plan. • Three projects are complete and associated risks have been managed to the target level. Two of these were reported in the Quarter 2 Update (King George V Skate Park and Waste and Street Cleansing Contract) and the other one was completed following approval of the 2026-27 budget at Full Council on 26 February 2026 (Engaging the community on our finances). • Two projects have an amber delivery status (Churchgate, and Digital Transformation). • Four projects have a high risk (red) status (Churchgate, Decarbonisation of Council Buildings - Phase 2, Local Plan Review, and Museum Collection Facility). • Three of the four over-arching Corporate Risks also have a red status, with the other one (Financial Sustainability) now assessed as a medium (amber) risk. • There are three KPIs that have a red status (two relating to Careline installations and one relating to CSC calls answered in 45 seconds).

This report also provides an update on developing agreed new KPIs that align with Council Plan objectives and the proposed timing for these to be included in future Council Delivery Plan monitoring reports. 2. RECOMMENDATIONS

It is recommended that Overview and Scrutiny Committee:

2.1Provide comment on the Council Delivery Plan Quarter 3 monitoring report, including the recommendation to be made to Cabinet: - That Cabinet notes progress against Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A), and approves new milestones and changes to milestones.

2.2Determine any project they want to receive more detail on, as part of the next monitoring report.

Reasons for recommendations

3.1The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities.

Alternative options considered

4.1In developing the CDP, it was agreed that Cabinet would receive quarterly updates. The updates are also provided to Overview and Scrutiny Committee so that they can provide additional oversight and support to Cabinet.

4.2Therefore, no alternative options were considered for this report.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Directors and Service Managers have provided updates on progress and will have made Executive Members aware of progress made.

5.2A draft of the Quarter 3 update was provided to the Risk and Performance Management Group (RPMG) in February 2026. The Group has a standing invite to the Executive Member for Resources (who has responsibility for performance monitoring), the Chair of Overview and Scrutiny Committee (O&S) and the Chair of Finance, Audit and Risk Committee (FAR). Other members of O&S, FAR, and Cabinet are also encouraged to attend if they can. RPMG were asked to comment on the Q3 update. There were no specific issues raised by the Group.

5.3The Overview and Scrutiny Committee are asked to provide comments on the current progress of the CDP, including recommendations to Cabinet.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
COUNCIL DELIVERY PLAN 2025-26 (Q3 UPDATE)Report 8 pages DownloadRead as text
PDF
FINAL Appendix A: Council Delivery Plan 2025-26 Q3 Monitoring Report.docxAppendix 33 pages Download

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. COUNCIL DELIVERY PLAN 2025-26 (Q3 UPDATE)This decision
  2. 2026-27 q1 council delivery plan updateNoted
  3. Council delivery plan 2025-26 (quarter 3 update)Noted
  4. Council delivery plan 2025-26 (quarter 2 update)Noted
  5. Council delivery plan 2025-26 (quarter 2 update)Approved
  6. Council delivery plan 2025/26 (quarter 1 update)Noted

More from North Hertfordshire Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for absenceThere were no apologies for absence received. Decided Open
8 Sep 2026 Minutes - 9 june 2026That the Minutes of the meeting of the Committee held on 9 June 2026 were approved as a true record of the proceeding... Approved Open
8 Sep 2026 Notification of other businessThere was no notification of other business. Decided Open
8 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Approved Open
8 Sep 2026 Public participationThere was no public participation at this meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies