Overview and Scrutiny Committee, Tuesday 12 September 2023 at 7.30pm

Q1 2023-2024 UPDATE ON THE COUNCIL DELIVERY PLAN

Noted Scrutiny 3 papers

Overview and Scrutiny Committee noted this item on Tuesday 12 September 2023. Below is the council's own wording, with the papers it was decided on.

Item234

Resolved

That the Committee: (1) Noted the progress against the Council projects as set out in the Council Delivery Plan (appendix A) including changes to milestones, performance indicators and risks, and makes any recommendations or comments to Cabinet. (2) Considered the presentation of the report for future meetings, especially in relation to milestones and project status, and made any recommendations or comments to Cabinet. REASON FOR DECISIONS: The Council Delivery Plan (CDP) monitoring reports provide Cabinet with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks or opportunities.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Overview and Scrutiny Committee, 4 pages

This document includes questions asked prior to the Overview & Scrutiny Committee on 12 September 2023, or where a response was required to be given after the meeting. The agenda and recording of the Overview & Scrutiny Committee on 12 September 2023 can be accessed here: Agenda for Overview and Scrutiny Committee on Tuesday, 12th September, 2023, 7.30 pm | North Herts Council (north-herts.gov.uk).

Item 11: Q1 2023-2024 Update on the Council Delivery Plan

Questions from Councillor Matt Barnes:

(1) EV Charging – how much is the grant funding and what is the contingency plan if it is not secured?

The grant funding application was for a maximum amount of £135,000 which equates to 60% of the estimated project costs. The other 40% will need to be covered by our partner. We have now received notification that we are being offered the grant, subject to our partner agreeing to the conditions of the grant payment. Therefore ,the risk of not receiving the funding has not materialised. There is a small risk that our partner may not agree to the funding obligations.

(2) RLC Solar Thermal – seems like this project is blocked on all milestones, should it be Red?

We have been successful in getting external funding to complete a heat decarbonisation plan for our leisure centres, and have identified a provider (under a framework contract) to produce those plans. This will enable us to fully determine what measures can be put in place (covering solar PV, solar thermal and new heating systems) and bid in the next round of Decarbonisation funding (expected in the Autumn) for any eligible projects. External funding will help with the viability of these projects, and the decarbonisation plans will help us target what to focus on. So we would go through that process before making any final decision on the Solar Thermal project.

(3) Pay on Exit – “there is uncertainty about public reaction to the changes and associated disruption”: could members be provided with details of how the proposals will work please so that we can anticipate and handle this effectively?

The Council is going out to tender for a partner to deliver the alternative methods of payment required for the pay on exit project. Part of the tender process will require a full communications plan to be put in place by the supplier, which will then be rolled out to members and the public once the successful supplier has been awarded the contract.

Questions from Councillor Ralph Muncer:

(1) Churchgate: The due date for a consultant to be appointed was 31 August 2023. Has one now been appointed and if so, when are they expected to begin work on the project?

Yes. They have already started the initial work required and set out in their work programme.

(2) Churchgate: The target date for the opening of the In-Person Project Hub and the launch of the Digital Hub has been changed to the 30 September, is this target on course to be achieved?

Contact Officer: [email protected] The in-person hub is on hold until further notice, due to an ongoing dispute with the previous tenant regarding utility bills. The Estates team are working hard with Legal to resolve this as soon as possible. Until then, we cannot access the property.

We are adding final touches to the digital hub, and hope to have this live by the end of September as stated.

(3) New Ways of Delivering Housing on Council Land: The review of the report findings/recommendations was due to take place by 30 June 2023, however due to resourcing issues was pushed back to 31 August 2023. Has this target been achieved, and if not when is a realistic date for the review to take place?

Report now delivered and initial reviews have taken place. This is leading to further clarifications and more detailed focus on specifics. Anticipated timeline for further advice would be Mid November due to consultant surveyor’s leave arrangements and other commitments on behalf of the Council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CDP.pdfAppendix A 32 pages Download
PDF
Council Delivery Plan 23-24 Q1: Questions and ResponsesReport 4 pages DownloadRead as text
PDF
Q1 2023-2024 UPDATE ON THE COUNCIL DELIVERY PLANReport 6 pages Download

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. Q1 2023-2024 UPDATE ON THE COUNCIL DELIVERY PLANThis decision
  2. 2026-27 q1 council delivery plan updateNoted
  3. Council delivery plan 2025-26 (quarter 3 update)Noted
  4. Council delivery plan 2025-26 (q3 update)Approved
  5. Council delivery plan 2025-26 (quarter 2 update)Noted
  6. Council delivery plan 2025-26 (quarter 2 update)Approved

More from North Hertfordshire Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for absenceThere were no apologies for absence received. Decided Open
8 Sep 2026 Minutes - 9 june 2026That the Minutes of the meeting of the Committee held on 9 June 2026 were approved as a true record of the proceeding... Approved Open
8 Sep 2026 Notification of other businessThere was no notification of other business. Decided Open
8 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair drew atte... Approved Open
8 Sep 2026 Public participationThere was no public participation at this meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies