COUNCIL DELIVERY PLAN 2023-24 (END OF YEAR)

Noted Executive 2 papers

Cabinet noted this item on Tuesday 25 June 2024. Below is the council's own wording, with the papers it was decided on.

Item20

Resolved

That Cabinet: (1) Noted the progress against Council projects as set out in the Council Delivery Plan (Appendix A) including new milestones and changes to milestone dates. (2) Noted the completion in Q4 of the projects detailed in paragraph 8.5. REASON FOR DECISIONS: The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities. That Cabinet: (1) Noted the progress against Council projects as set out in the Council Delivery Plan (Appendix A) including new milestones and changes to milestone dates. (2) Noted the completion in Q4 of the projects detailed in paragraph 8.5. REASON FOR DECISIONS: The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet, 6 pages

Executive summary

This report presents progress on delivering the Council Delivery Plan for 23-24 at the end of Quarter 4, which includes:

 Progress against the completion of Council projects and milestones  Requests to change milestone dates  New milestones

Recommendations

2.1That Cabinet notes the progress against Council projects as set out in the Council Delivery Plan (Appendix A) including new milestones and changes to milestone dates.

2.2That Cabinet note the completion in Q4 of the projects detailed in paragraph 8.5.

Reasons for recommendations

3.1The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities.

Alternative options considered

4.1In developing the CDP, it was agreed that Cabinet would receive quarterly updates. The updates are also provided to Overview and Scrutiny Committee so that they can provide additional oversight and support to Cabinet. 5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Service Directors and Service Managers have provided updates on progress and will have made Executive Members aware of progress made.

5.2A draft of the Quarter 4 update was provided to Risk and Performance Management Group (RPMG) in May. The Group has a standing invite to the Executive Member for Finance and IT (has responsibility for performance monitoring), the Chair of Overview and Scrutiny (O&S) and the Chair of Finance, Audit and Risk Committee (FAR). Other members of O&S and FAR are also encouraged to attend when they can. RPMG were asked to comment on the content and format of the CDP Q4 update. Unfortunately due to the timing of the meeting, no Councillors were able to attend.

5.3The CDP is reviewed by Overview and Scrutiny Committee, and they are asked to provide comments and recommendations to Cabinet.

6. FORWARD PLAN

6.1This report contains a recommendation on a key Executive decision first notified on the Forward Plan on the 28 March 2024.

Background

7.1The CDP brings together projects, risks, and performance indicators together in one document. The content for the 2023/24 Delivery Plan was set by Cabinet in March 2023, with the intention that it is updated throughout the year.

7.2In March 2024, Cabinet agreed a revised set of projects for the 2024/25 Delivery Plan. This means that some of the projects contained within this update will not feature on the 2024/25 Delivery Plan, but will be monitored as part of Service Plans. This is reflected in some of the comments against the milestones.

8. RELEVANT CONSIDERATIONS

8.1Appendix A provides an update on the progress made in delivering the Council Plan 2023-24. Whilst it is labelled as a Quarter 4 update, it generally reflects the latest position at the time that the report was written. Milestones completed before January 2024, and reported in previous updates, have been removed.

8.2The intention is that the CDP reports provide an overview, as providing all the details on project milestones would lead to a report that was too long. Requests can be made (especially by O&S) to look at individual projects in more detail. Any such request would be incorporated into the next monitoring report. The progress made to date against each project and resulting impacts on future milestones, is detailed in the commentary against each project in Appendix A.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CDP monitoring reportAppendix A 26 pages Download
PDF
COUNCIL DELIVERY PLAN 2023-24 (END OF YEAR)Report 6 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 15 attended
DA
Councillor Daniel AllenChair, present
VB
Councillor Val BryantVice-Chair, present
IA
Councillor Ian AlbertCommittee Member, present
AA
Councillor Amy AllenCommittee Member, present
CH
Councillor Chris HinchliffCommittee Member, present
TT
Councillor Tamsin ThomasCommittee Member, apologies
MD
Councillor Mick DebenhamCommittee Member, present
DW
Councillor Dave WinstanleyCommittee Member, present
IC
Ian CouperOfficer, present
SK
Sarah KingsleyOfficer, present
AR
Anthony RocheOfficer, present
IA
Isabelle AlajoozOfficer, present

All 15 on the meeting page

On this subject at North Hertfordshire

Search all
  1. COUNCIL DELIVERY PLAN 2023-24 (END OF YEAR)This decision
  2. 2026-27 q1 council delivery plan updateNoted
  3. Council delivery plan 2025-26 (quarter 3 update)Noted
  4. Council delivery plan 2025-26 (q3 update)Approved
  5. Council delivery plan 2025-26 (quarter 2 update)Noted
  6. Council delivery plan 2025-26 (quarter 2 update)Approved

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open
22 Sep 2026 Public participationThe Chair invited [name removed] to provide a 5-minute verbal presentation relating to Agenda Item 8 – Local Plan – C... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies