Resolved

That Cabinet: (1) Noted the progress against Council projects as set out in the Council Delivery Plan and approved the changes to the milestones (Appendix A). (2) Noted the performance against the performance indicators and confirms the actions detailed in paragraph 8.4. (3) Approved the addition of a new Corporate Risk for Local Government Reorganisation and Devolution. REASON FOR DECISIONS: The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities. Overview and Scrutiny are trialling having a focus on a specific Executive Member area of responsibility at each meeting. For their March meeting it is Planning and Transport. An extract of the Council Delivery Plan has therefore been provided for their meeting (i.e. focused on Planning and Transport projects, KPIs and risks), but the overall Council Delivery Plan will be publicised to all Members via the Members Information Service. That Cabinet: (1) Noted the progress against Council projects as set out in the Council Delivery Plan and approved the changes to the milestones (Appendix A). (2) Noted the performance against the performance indicators and confirms the actions detailed in paragraph 8.4. (3) Approved the addition of a new Corporate Risk for Local Government Reorganisation and Devolution. REASON FOR DECISIONS: The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities. Overview and Scrutiny are trialling having a focus on a specific Executive Member area of responsibility at each meeting. For their March meeting it is Planning and Transport. An extract of the Council Delivery Plan has therefore been provided for their meeting (i.e. focused on Planning and Transport projects, KPIs and risks), but the overall Council Delivery Plan will be publicised to all Members via the Members Information Service.
Word for word from the decision North Hertfordshire published for this meeting. Source: democracy.north-herts.gov.uk

Follow this further

Built from North Hertfordshire's papers

What the report saysPro

Report to Cabinet, 7 pages

Executive summary

This report presents progress on delivering the Council Delivery Plan for 2024-25. This is a Quarter 3 update, but generally reflects progress up to the point that this report was prepared (mid-February). The report includes:

 For the projects identified by Cabinet in March 2024, it details milestones and progress against them.  The risks in relation to the delivery of those projects, as well as the corporate risks that could impact the delivery of all our projects and services. This includes a proposal for a new corporate risk related to Local Government Reorganisation and Devolution.  Latest data for the performance indicators identified by Cabinet in June 2024.

There are 8 projects with delayed milestones, 4 projects with new milestones and 2 projects with deleted milestones.

There are two red performance indicators relating to calls answered within 45 seconds and percentage of NNDR (Business Rates) collected in-year. The actions to correct this are set out in paragraph 8.4. 2. RECOMMENDATIONS

2.1That Cabinet notes the progress against Council projects as set out in the Council Delivery Plan, and approves the changes to the milestones (Appendix A)

2.2That Cabinet notes the performance against the performance indicators and confirms the actions detailed in paragraph 8.4.

2.3That Cabinet approves the addition of a new Corporate Risk for Local Government Reorganisation and Devolution. 3. REASONS FOR RECOMMENDATIONS

3.1The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities. Overview and Scrutiny are trialling having a focus on a specific Executive Member area of responsibility at each meeting. For their March meeting it is Planning and Transport. An extract of the Council Delivery Plan has therefore been provided for their meeting (i.e. focused on Planning and Transport projects, KPIs and risks), but the overall Council Delivery Plan will be publicised to all Members via the Members Information Service.

Alternative options considered

4.1In developing the CDP, it was agreed that Cabinet would receive quarterly updates. The updates are made available to Overview and Scrutiny Committee so that they can provide additional oversight and support to Cabinet.

5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS

5.1Directors and Service Managers have provided updates on progress and will have made Executive Members aware of progress made.

5.2A draft of the Quarter 3 update was provided to Risk and Performance Management Group (RPMG) in February. The Group has a standing invite to the Executive Member for Finance and IT (has responsibility for performance monitoring), the Chair of Overview and Scrutiny (O&S) and the Chair of Finance, Audit and Risk Committee (FAR). Other members of O&S and FAR are also encouraged to attend when they can. RPMG were asked to comment on the Q3 update. There were no specific issues raised by the group.

5.3The CDP is able to be reviewed by Overview and Scrutiny Committee, and they can make comments and recommendations to Cabinet. Although their change of approach is detailed in paragraph 3.1 above.

6. FORWARD PLAN

6.1This report contains a recommendation on a key Executive decision first notified on the Forward Plan on the 13 December 2024.

Background

7.1The CDP brings together projects, risks, and performance indicators together in one document. The projects to be included in the 2024/25 Council Delivery Plan were agreed by Cabinet in March 2024, following a project prioritisation exercise. The performance indicators that are included were determined by Cabinet in June 2024. 8. RELEVANT CONSIDERATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Council Delivery Plan 24-25 Q3 Monitoring ReportAppendix A 22 pages Download
PDF
Risk- Local Government Reorganisation and DevolutionAppendix B 2 pages Download
PDF
COUNCIL DELIVERY PLAN 2024-25 (QUARTER 3 UPDATE)Report 7 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at North Hertfordshire

Search all
  1. COUNCIL DELIVERY PLAN 2024-25 (QUARTER 3 UPDATE)This decision
  2. 2026-27 q1 council delivery plan updateNoted
  3. Council delivery plan 2025-26 (quarter 3 update)Noted
  4. Council delivery plan 2025-26 (q3 update)Approved
  5. Council delivery plan 2025-26 (quarter 2 update)Noted
  6. Council delivery plan 2025-26 (quarter 2 update)Approved

More from North Hertfordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Apologies for absenceApologies for absence were received from Councillor Laura Williams. Decided Open
22 Sep 2026 Minutes - 16 june 2026That the Minutes of the Meeting of the Committee held on 16 June 2026 be approved as a true record of the proceedings... Approved Open
22 Sep 2026 Notification of other businessThere was no other business notified . Decided Open
22 Sep 2026 Chair's announcements(1) The Chair advised that, in accordance with Council Policy, the meeting would be recorded. (2) The Chair reminded ... Decided Open
22 Sep 2026 Public participationThe Chair invited [name removed] to provide a 5-minute verbal presentation relating to Agenda Item 8 – Local Plan – C... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies