That Cabinet noted progress against Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A), and approved new milestones and changes to milestones. REASON FOR DECISION: The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities. That Cabinet noted progress against Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A), and approved new milestones and changes to milestones. REASON FOR DECISION: The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities.
Word for word from the decision North Hertfordshire published for this meeting.Source: democracy.north-herts.gov.uk
This report presents progress on delivering the Council Delivery Plan for 2025-26. This is a Quarter 1 update but generally reflects progress up to the point that this report was prepared (mid- August). The report includes:
For the projects identified by Cabinet, it details milestones and progress against them. The risks in relation to the delivery of those projects, as well as the corporate risks that could impact the delivery of all our projects and services. Latest data for the Council’s key performance indicators (KPIs).
Two projects have an amber delivery status (digital transformation and leisure centre decarbonisation). Four projects have a red risk status (leisure centre decarbonisation, decarbonisation phase 2, Churchgate and Local Plan review). All the over-arching corporate risks are at red status. There are 3 KPIs that have a red status (2 relating to Careline installations and the other relating to CSC calls answered in 45 seconds).
This report also sets out intentions in relation to developing KPIs that align better to the objectives within our Council Plan.
Recommendations
2.1That Cabinet notes progress against Council projects and performance indicators, as set out in the Council Delivery Plan (Appendix A), and approves new milestones and changes to milestones. 3. REASONS FOR RECOMMENDATIONS
3.1The Council Delivery Plan (CDP) monitoring reports provide Overview and Scrutiny Committee, and Cabinet, with an opportunity to monitor progress against the key Council projects, and understand any new issues, risks, or opportunities.
Alternative options considered
4.1In developing the CDP, it was agreed that Cabinet would receive quarterly updates. The updates are also provided to Overview and Scrutiny Committee (when requested) so that they can provide additional oversight and support to Cabinet.
4.2In relation to adding new KPIs to better reflect delivery of the Council Plan, there would be an option to just retain the current KPIs and accept that they are primarily focused on delivery of core services.
5. CONSULTATION WITH RELEVANT MEMBERS AND EXTERNAL ORGANISATIONS
5.1Directors and Service Managers have provided updates on progress and will have made Executive Members aware of progress made.
5.2A draft of the Quarter 1 update was provided to the Risk and Performance Management Group (RPMG) in August. The Group has a standing invite to the Executive Member for Resources (has responsibility for performance monitoring), the Chair of Overview and Scrutiny Committee (O&S) and the Chair of Finance, Audit and Risk Committee (FAR). Other members of O&S and FAR are also encouraged to attend when they can. RPMG were asked to comment on Q1 update. There were no specific issues raised by the Group.
5.3The Overview and Scrutiny Committee are asked to provide comments on the current progress of the CDP, including recommendations to Cabinet.
5.4In August, proposals in relation to adding new KPIs to better reflect the Council Plan were discussed at the internal informal Political Liaison Board of the Executive and the Leadership team. The conclusion was that it would be desirable to have additional KPIs that described the outcomes achieved by the Council Plan.
6. FORWARD PLAN
6.1This report does not contain a recommendation on a key Executive decision and has therefore not been referred to in the Forward Plan.
Background
7.1The CDP brings together projects, risks, and performance indicators in one document. The projects and performance indicators have been rolled forward from 2024/25 into the current year. There has been one project added (decarbonisation phase 2). 8. RELEVANT CONSIDERATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.