Capital Programmes - General Fund, Coalville Special Expenses and Housing Revenue Account (H.R.A). Projected Outturn 2015/16 and Programmes 2016/17 to 2020/21
NotedExecutive3 papers
Cabinet noted this item on Tuesday 9 February 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED THAT: A. The estimated General Fund, Coalville Special Expenses and H.R.A. Capital Outturn for 2015/16 and Planned Financing be noted. B. Council be recommended to approve expenditure in 2016/17 as per: · appendix “A” General Fund and Special Expenses Capital Schemes · appendix “B” for HRA Capital Schemes and in 2017/18 these schemes only: · £630,000 for the vehicle replacement programme, as detailed in paragraph 3.2 C. The proposed procurement routes be noted and the authority to award the contracts, and any associated agreements in furtherance of the projects, as detailed in section 7 (procurement routes) of this report be delegated. Reason for decision: To enable projects to be included in the Programmes and proceed.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
2016 - 2021 Decent Homes Decent Homes Programme 4,281,900 5,081,900 2,097,370 1,139,014 3,998,415 2,498,586 817,160 Decent Homes Refusals/Deferrals Provision 222,000 222,000 Capital Works (Voids & Tenanted) 850,000 850,000 850,000 800,000 750,000 700,000 650,000 2016 - 2021 Decent Homes Total 5,353,900 6,153,900 2,947,370 1,939,014 4,748,415 3,198,586 1,467,160
2016 - 2021 Other Planned Investment Non Decency Improvements 1,028,124 1,170,914 1,170,914 1,170,914 1,470,414 Hard Wired Smoke Detectors 47,000 47,000 47,000 47,000 47,000 47,000 Fire Risk Assessment Remedial Works 40,000 40,000 40,000 40,000 40,000 40,000 Remedial Works (Damp & Structural) 210,000 210,000 187,500 187,500 187,500 187,500 Fuel swaps (solid fuel to gas supply) 25,000 25,000 25,000 25,000 25,000 25,000 2016 - 2021 Other Planned Investment Total 322,000 322,000 1,327,624 1,470,414 1,470,414 1,470,414 1,470,414
New Build / Affordable Housing Programme New Build Programme - use of RTB one for one reserve 122,178 33,750 496,919 105,916 New Build Programme - NWLDC contribution to RTB one 285,082 78,750 385,961 1,663,964 New Build Programme - NWLDC additional provision 319,000
Support for Acquiring Affordable Housing 559,000 887,000 Support for Affordable Housing - (Waterloo Hsg Grp, 444,000 EMH Assoc, Nottingham Com grp) Support for Affordable Housing - EMH Assoc (Pick & 500,000 Shovel site) Acquisition of sites 400,000 New Build / Affordable Housing Programme Total 1,285,260 1,456,500 1,769,880 1,769,880 - - -
Othe Schemes / Miscellaneous Off Street Parking 100,000 100,000 - - -
Major Aids & Adaptations 450,000 450,000 350,000 300,000 275,000 250,000 250,000 Development Site Preparations 40,000 40,000 - - - - Energy Insulation Works 250,000 250,000 - - - - Renewable/Replacement Energy Installations 100,000 100,000 250,000 250,000 250,000 250,000 Programme Speech Module 50,000 50,000 50,000 50,000 50,000 Capital Programme Delivery Costs 654,000 710,000 530,160 541,824 553,744 565,926 578,376 Unallocated/Contingency 500,000 500,000 339,744 288,965 339,691 260,950 Disposal of High Value Assets 500,000 500,000 500,000 500,000 500,000 Othe Schemes / Miscellaneous Total 2,144,000 2,050,000 2,119,904 1,930,789 1,968,435 1,876,876 1,328,376
Capital Allowances Programme to be defined Capital Allowances Total - - - - - - -
Total Programme Costs 9,105,160 9,982,400 8,164,778 7,110,097 8,187,264 6,545,876 4,265,950
2016/17 - 2020/21 HOUSING CAPITAL PROGRAMME FUNDING
Capital Programmes: General Fund, Coalville Special Expenses and Housing Revenue Account (H.R.A). Projected Outturn 2015/16 and Programmes 2016/17 to 2020/21Minutes
77Capital Programmes - General Fund, Coalville Special Expenses and Housing Revenue Account (H.R.A). Projected Outturn 2015/16 and Programmes 2016/17 to 2020/21This decision
Capital Programmes - General Fund, Coalville Special Expenses and Housing Revenue Account (H.R.A). Projected Outturn 2015/16 and Programmes 2016/17 to 2020/21This decision
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.