Capital Programmes - General Fund, Coalville Special Expenses and Housing Revenue Account (H.R.A). Projected Outturn 2016/17 and Draft Programmes 2017/18 to 2021/22
NotedExecutive3 papers
Cabinet noted this item on Tuesday 13 December 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED THAT: a) The estimated General Fund, Coalville Special Expenses and HRA Capital Outturn for 2016/17 and planned financing be noted. b) The consultation for the draft Capital Programmes in 2017/18 be approved as detailed at: (i) Appendix A – General Fund and Special Expenses Capital Schemes (ii) Appendix B – HRA Capital Schemes And in 2018/19 the following scheme only: (iii) Paragraphs 3.2 to 3.2.3 - £935,000 for the vehicle replacement programme. c) The indicative Capital Programme Schemes for 2018.19 to 2021/22 be noted. d) The proposed procurement routes be noted and authority to award the contracts and any associated agreements in furtherance of the projects as detailed in section 7 of the report, be delegated to the Director of Services in consultation with the Portfolio Holder, subject to final approval of the Capital Programmes in February 2017. Reason for decision: To enable projects to be included in the programmes for consultation.
Word for word from the decision North West Leicestershire published for this meeting.Source: minutes-1.nwleics.gov.uk
CAPITAL PROGRAMMES – GENERAL FUND, COALVILLE SPECIAL EXPENSES AND HOUSING REVENUE ACCOUNT Title of Report (H.R.A). PROJECTED OUTTURN 2016/17 AND DRAFT PROGRAMMES 2017/18 TO 2021/22
To advise Members of the likely Capital Outturn and the relevant financing for 2016/17 for the General Fund, Coalville Special Expenses and the H.R.A. Purpose of Report To seek approval to the Draft General Fund, Coalville Special Expenses and H.R.A Capital Programmes for 2017/18 and to note indications for future years and associated funding for consultation.
To enable projects to be included in the Programmes for Reason for Decision consultation.
The projects in the Capital Programmes help the Council achieve Council Priorities all its priorities. Implications
Financial / Staff As contained in the report.
The Capital programmes are potentially relevant to all Corporate Links to relevant CAT Action Teams (CATs).
The Capital Programmes are monitored at project level to ensure Risk Management they are delivered on time and within budget.
Equalities Impact Screening No impact at this stage.
Human Rights None identified.
Transformational The Programmes attached are integral to delivering better Government services.
Comments of Deputy Chief Report is satisfactory Executive
Comments of Deputy As author, the report is satisfactory Section 151 Officer
Comments of Deputy Report is satisfactory Monitoring Officer
Consultees CLT and Budget Holders.
Capital Programmes - General Fund, Coalville Special Expenses and Housing Revenue Account (H.R.A). Projected Outturn 2015/16 and Background Papers Programmes 2016/17 to 2020/21– Cabinet 9 February 2016
A. THAT THE ESTIMATED GENERAL FUND, COALVILLE SPECIAL EXPENSES AND H.R.A. CAPITAL OUTTURN FOR 2016/17 AND PLANNED FINANCING BE NOTED. Recommendations B. THAT CABINET APPROVES FOR CONSULTATION THE DRAFT CAPITAL PROGRAMMES IN 2017/18 DETAILED IN: APPENDIX “A” GENERAL FUND AND SPECIAL EXPENSES CAPITAL SCHEMES APPENDIX “B” FOR HRA CAPITAL SCHEMES
AND IN 2018/19 THESE SCHEMES ONLY: £935,000 FOR THE VEHICLE REPLACEMENT PROGRAMME, AS DETAILED IN PARAGRAPHS 3.2 to 3.2.3
C. THAT CABINET NOTES INDICATIVE CAPITAL PROGRAMME SCHEMES FOR 2018/19 TO 2021/22.
D. THAT CABINET NOTES THE PROPOSED PROCUREMENT ROUTES AND DELEGATES THE AUTHORITY TO AWARD THE CONTRACTS, AND ANY ASSOCIATED AGREEMENTS IN FURTHERANCE OF THE PROJECTS, AS DETAILED IN SECTION 7 (PROCUREMENT ROUTES) OF THIS REPORT SUBJECT TO FINAL APPROVAL OF THE CAPITAL PROGRAMMES IN FEBRUARY 2017.
1.0INTRODUCTION
1.1Appendix “A” shows the proposed General Fund and Special Expenses Capital Programme for 2017/18 to 2021/22.
1.2Appendix “B” shows the H.R.A. proposed Capital Programme for 2017/18 to 2021/22.
1.3The Appendices also present the estimated outturn for the current year for approval.
2.0GENERAL FUND - ESTIMATED OUTTURN 2016/17
2.1The projected outturn for 2016/17 on General Fund schemes totals £2,991,215. This is a managed increase of £192,705 on the original budget for the year of £2,798,510.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Programmes: General Fund, Coalville Special Expenses and Housing Revenue Account (H.R.A). Projected Outturn 2016/17 and Draft Programmes 2017/18 to 2021/22Minutes
69Capital Programmes - General Fund, Coalville Special Expenses and Housing Revenue Account (H.R.A). Projected Outturn 2016/17 and Draft Programmes 2017/18 to 2021/22This decision
Capital Programmes - General Fund, Coalville Special Expenses and Housing Revenue Account (H.R.A). Projected Outturn 2016/17 and Draft Programmes 2017/18 to 2021/22This decision
Ashby Business Improvement DistrictRESOLVED THAT: 1) The Ashby BID proposals, set out in this report, be reviewed. 2) Authority be delegated to the Stra...
Consultancy Services for the Local PlanRESOLVED THAT: 1) The procurement for Planning Policy Consultancy Support from the Council’s Contract Procedure Rules...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.