Oldham Metropolitan Borough Council
Cabinet, Monday 23 March 2026 at 6.00pm

Capital Works (Kingsland)

Approved Executive 1 paper

AI summaryOldham Cabinet approves tier 2 alternative provision at Kingsland School and a £1.36m building project at the former Limehurst Youth Centre in Limeside.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTier 2 provision and capital works at Limehurst
Money£1,361,250 capital costFunded from Basic Needs and/or HNPCA Grant
What happens nextBegin capital works at LimehurstStep Out provision to start once built
Who it affectsSecondary aged pupils at risk of exclusion. Across Oldham mainstream schools

What was decided

Cabinet authorised Kingsland School to deliver a tier 2 service, with Step Out short term placements of 6 to 12 weeks for up to 36 pupils at a time at the Limehurst site in Limeside. Report 2.4, P20

Cabinet approved the project to replace the single storey derelict modular building at the former Limehurst Youth Centre, with works charged to the educational capital programme 2025/26 and funded from the Basic Needs and/or HNPCA Grant. Report 6.1

Option 1 was the preferred option, with base funding of £360,000 (36 places at £10,000 each) to ensure sustainability, charged to schools at £90 per pupil per day. Report 4.1, 3.1, P25, P26

Why

National and local suspensions and permanent exclusions have reached the highest levels since records began in 2006, and Oldham has no tier 2 alternative provision for secondary pupils. Report 1.3, 1.4, P10, P12

The current tier 3 provision at Kingsland School's PRU is overcrowded and faces safety risks, with pupils at risk of serious violence on the same site. Report P11, P30

Oldham LA currently spends £1.2 million per year on externally commissioned unregistered alternative provision from the high needs block of the DSG, while 13 local secondary schools reported spending £20,000 to £550,000 each on unregistered AP at £150 to £285 per pupil per day. Report 1.6, P17

What happens next

Capital works to make the Limehurst building suitable will proceed, with the cost analysis set out in the appendix Limehurst 2 Storey Budget Costs. Report 6.1, P37, 13.1

Schools will refer pupils into Step Out using a standard referral form, and any contracts, land transactions and financial transactions must comply with the Council's Contract Procedure Rules, Financial Procedure Rules and Land and Property Protocol. Report P20, 7.3

Officers must work with legal, finance and audit colleagues to approve the terms of any grant agreement and comply with conditions attached to the funding. Report 7.5

The money

  • £1,361,250 Cost of capital works including 10% contingency, charged to educational capital programme 2025/26, funded from Basic Needs and/or HNPCA Grant Report 6.1
  • £360,000 Base funding for 36 places at £10,000 per place, to ensure sustainability and initial staffing Report P26
  • £1.2 million per year Current Oldham LA SEND Team spend on externally provided alternative provision, from the high needs block of the DSG Report 1.6
  • £615,600 Income if Step Out runs at full capacity across 38 weeks at £90 per pupil per day Report P25
  • £307,800 Income if Step Out runs at 50% capacity across the year Report P25
  • £90 per pupil per day Proposed charge to schools for Step Out places Report P25
  • £180,000 Estimated lower base funding under Option 3, around 50% of Option 1 base funding Report 3.3

Options considered

  • Chosen: Option 1: Limehurst site with full base funding of £360,000 for 36 places, charged at £90 per pupil per day, funded from SEND Capital Provision Funding. Strongest and most robust tier 2 offer, fully meets SEND and AP Improvement Plan, supports sustainability and earlier identification of need Report 3.1, 4.1, P25, P26, P33
  • Rejected: Option 2: Agree capital costs of part remodelling at Limehurst with SEND Capital Provision Funding, but rely on income generation alone for staffing Report 3.2
  • Rejected: Option 3: Limehurst site with lower base funding of about £180,000, calculated from surplus DSG. Risk that tier 2 provision would not be strong enough to meet secondary school needs, would increase pressure on an already overcrowded PRU and continue late intervention Report 3.3, P29

Implications

  • Financial: Capital cost of £1,361,250 including 10% contingency charged to educational capital programme 2025/26, with any unspent budget returned to the provision budget; revenue funded from High Needs Block of the DSG. Report 6.1, 6.2, P40
  • Legal: Contracts must comply with the Council's Contract Procedure Rules, land transactions with the Land and Property Protocol, and financial transactions with the Financial Procedure Rules; officers must agree terms of any grant agreement. Report 7.3, 7.4, 7.5
  • Equalities: No negative implications for vulnerable groups or children and young people identified; project supports the government's inclusion agenda and aims to reduce overrepresentation of minority groups in AP. Report 8.1, 1.2, P33
  • Risk: Without tier 2 provision, the overcrowded PRU at Kingsland School is at imminent risk of becoming unsustainable, with health and safety and Ofsted risks; lower funding option would worsen capacity and late intervention. Report P11, P29, P30
  • Other: Supports the SEND and Inclusion Strategy 2023 to 2027 and the Sufficiency Strategy, and aligns with the 2026 White Paper Every Child Achieving and Thriving and the SEND and AP Improvement Plan. Report 1.2, P9, 12.1

Who and where

  • Secondary aged children and young people in Oldham at risk of exclusion or with SEMH needs, including those with EHCPs and EOTAS placements Report 2.4, P21
  • 13 local mainstream secondary schools and the Multi Academy Trusts operating in Oldham Report P15, P17, 5.1, P35
  • Children moving into the borough under the 'difficult transfer' category Report P21
  • Oldham LA SEND Team and the high needs block of the DSG Report 1.6, P40

Timeline

  • Academic year 2023/24: Kingsland School funded the Secondary Outreach Service and Alternative Provision Specialist Taskforce in Oldham Report 1.5
  • Academic year 2024/25: PARE panel oversaw an average of 4 cases per week, around 156 children and young people identified as at high risk of exclusion Report P15
  • 2025/26: Capital works charged to the educational capital programme 2025/26 Report 6.1
  • Once built: Step Out tier 2 provision to operate, offering 6 to 12 week placements for up to 36 pupils at a time Report 2.4, P20

Plain English for the jargon

  • AP: Alternative Provision, education arranged by local authorities or schools for pupils who do not attend mainstream school
  • SEND: Special Educational Needs and Disabilities
  • DSG: Dedicated Schools Grant, the main ringfenced funding for schools
  • High Needs Block: Part of the DSG that funds provision for pupils and students with SEND from early years to age 25
  • PRU: Pupil Referral Unit, a type of alternative provision for pupils who cannot attend mainstream school
  • EHCP: Education, Health and Care Plan, a legal document setting out support for a child or young person with SEND
  • EOTAS: Education Other Than At School, a type of provision named in an EHCP
  • SEMH: Social, Emotional and Mental Health, a category of SEND
  • PARE: Pupils at Risk of Exclusion, a panel operated by Kingsland School
  • HNPCA: High Needs Provision Capital Allocation, a DfE capital grant for SEND provision
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item20

Resolved

That the implementation of tier 2 support and provision for secondary aged children, commissioned from and provided by Kingsland School, be authorised and the project proposal, detailed in the submitted report, to replace a single storey derelict modular building (former Limehurst Youth Centre), be approved.
Word for word from the decision Oldham published for this meeting. Source: committees.oldham.gov.uk

Follow this further

Built from Oldham's papers

What the report saysPro

Report to Cabinet

Background

1.1Following the consultation of the SEND & Alternative Provision (AP) Green Paper (2022), several concerning themes emerged around the SEND & AP system including poor and inconsistent outcomes for many children and young people accessing AP. In response, the DfE have published the SEND & Alternative Provision (AP) Improvement Plan. Relating to Alternative Provision, the DfE have discussed an AP system with a three-tiered approach: targeted early support within mainstream school (tier 1), time-limited intensive placements in an alternative provision setting (tier 2); and longer-term placements to support a return to mainstream or a suitable post-16 destination (tier 3)

1.2This development also directly supports the strengthened national inclusion agenda set out in the 2026 White Paper Every Child Achieving and Thriving. The White Paper places a clear emphasis on shifting the system “from sidelined to included,” ensuring that children with additional needs are supported earlier, remain connected to their mainstream school communities, and experience broader, more inclusive learning opportunities. By establishing a high‑quality Tier 2 provision that enables short‑term, time‑limited interventions and reintegration support, this project aligns with the government’s ambition to build a more consistent and inclusive SEND system, reducing exclusions through proactive support and ensuring vulnerable pupils receive the right help in the right place at the right time

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Works (Kingsland)Report 458 KB DownloadRead as text

At this meeting

Whole meeting
5MinutesApproved 6Adult Social Care CQC Assessment OutcomeNoted 7Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026Approved 8Proposal to update Smokefree policyDecided 9Extension of the Current Commissioning Arrangements for Care at HomeApproved 10Approval to Tender the Domestic Property Disability Adaptions FrameworkApproved 11Procurement of a Crisis Payment ProviderAgreed 12Crisis and Resilience Fund – Utilisation of Grant AllocationAgreed 13Arts Council - Development Extension GrantApproved 14Bikeability Core and Bikeability Plus delivery 2026 - 2029Approved 15Grant Acceptance: City Region Sustainable Transport Settlement (CRSTS) - Revenue FundingApproved 16Staying Close Leaving Care OfferApproved 17Greater Manchester’s Integrated Settlement for Education, Work and SkillsAgreed 18Special Education Needs (SEN) Travel Assistance Service – Contract ExtensionDecided 19High Needs Provision in Mainstream Settings Capital WorkApproved
20Capital Works (Kingsland)This decision
21Proposal to Undertake Statutory Consultation on the Establishment of an Oldham Mayoral Development CorporationApproved 22Housing Allocations Scheme 2026Approved 23Infrastructure Funding Statement 2024/25Approved 24Oldham's Monitoring Report 2024/25Approved 25Biodiversity Duty ReportApproved 26Princes Gate – Development Update (St Mary’s)Decided 27Sale of Land at Rosary Road, Fitton Hill (Medlock Vale)Decided 28Economic Development and Regeneration Flexible Grant AcceptanceDecided 29Revenue Monitor and Capital Investment Programme 2025/26 - Month 10Approved 30Local Taxation Discretionary Policies 2026/27Approved 31Greater Manchester Empty Homes and Leasing Programme - Acceptance of FundingApproved 32Local Authority Housing Fund (LAHF) - Acceptance of FundingApproved 33Acceptance of 2026/27 GMCA Community Safety Partnership, Voluntary and Community Sector, Hate Crime, GM Violence Reduction and Cohesion GrantsApproved 34Exclusion of the Press and PublicOn the agenda 35Princes Gate – Development Update (St Mary’s) PART BPrivate 36Sale of Land at Rosary Road, Fitton Hill (Medlock Vale)Private 37Economic Development and Regeneration Flexible Grant AcceptancePrivate 38Upgrade of E3 to E5 Licences for remaining user basePrivate 39CAF CompliancePrivate 40Telephony Contract RenewalPrivate 41Cyber - Server ProtectionPrivate 42Oldham Council MFD Print SolutionPrivate 43Security Operations CentrePrivate 44ZTNA – Zero Trust Network AccessPrivate

Who was there

7 of 30 attended
MA
Mohon AliCommittee Member, present
JB
Jack BaileyOfficer, expected
MB
Mike BarkerOfficer, expected
MB
Mike BarkerOfficer, expected
EB
Emma BartonOfficer, expected
AB
Alex BougatefOfficer, expected
BB
Barbara BrownridgeCommittee Member, present
MB
Matthew BulmerOfficer, expected
NC
Neil ConsterdineOfficer, expected
ND
Nasir DadOfficer, expected
JD
Julie DanielsOfficer, expected
PD
Peter DeanCommittee Member, apologies

All 30 on the meeting page

On this subject at Oldham

Search all
  1. Capital Works (Kingsland)This decision
  2. Yew Tree Community School - Capital WorksApproved
  3. Spring Brook Capital WorksApproved

More from Oldham Cabinet

All decisions
MeetingDecisionOutcome
23 Mar 2026 MinutesThat the minutes of the meeting of the Cabinet held on 23 rd February 2026, be approved as a correct record. Approved Open
23 Mar 2026 Adult Social Care CQC Assessment OutcomeThat the report be noted and welcomed. 2. That the congratulations of the Cabinet be extended to the Deputy Chief Exe... Noted Open
23 Mar 2026 Extension to the Adult Social Care Service Level Agreement with Miocare Group CIC 2026That the Cabinet: 1. Approves the Service Level Agreement with Miocare Group CIC. 2. Approves the refreshed Service L... Approved Open
23 Mar 2026 Proposal to update Smokefree policyThat the Council revise and update its smokefree policy, in line with the narrative detailed in the submitted report ... Decided Open
23 Mar 2026 Extension of the Current Commissioning Arrangements for Care at HomeThat the Cabinet approves a three-month extension of the current contracts for Care at Home, Extra Care and Night Pro... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies