Project Approval and Delegations for Redbridge Paddock affordable housing scheme
ApprovedExecutive2 papers
AI summaryOxford City Cabinet approved the Redbridge Paddock scheme, 237 homes on a former landfill in Hinksey Park ward, with 118 affordable homes to be held in the HRA, within a £385.6m budget envelope.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedLand sale and affordable housing acquisition approved
Money£385.6m budget envelopeMTFP, before grant and shared ownership sales
What happens nextOutline planning submissionTargeted for August 2026
Who it affectsHinksey Park ward residentsPlus housing register and shared ownership buyers
What was decided
Project approval was given for the Redbridge Paddock development, including the sale of the land from the General Fund to OCH(D)L and the subsequent purchase of the affordable homes into the Housing Revenue Account. Report P4, P9, P11
Authority was delegated to the Deputy Chief Executive for City and Citizens' Services, in consultation with the Cabinet Member for Housing, the Section 151 Officer and the Monitoring Officer, to finalise the scheme design, financial appraisals and enter contracts to buy the affordable housing from OCH(D)L within the identified budget. Report P4
Authority was delegated to the Deputy Chief Executive (Place), in consultation with the Cabinet Member for Finance and Asset Management, the Section 151 Officer and the Monitoring Officer, to approve the final Section 123 compliant terms and enter the sale agreement for the site from the General Fund to OCH(D)L. Report P5
Why
The Council is continuing a programme to deliver more affordable housing through multiple routes, including direct delivery by Oxford City Housing Limited, which trades as OX Place. Report P3, P8
The site is a former landfill used from the late 1960s until 1972, requiring extensive remediation and enabling works, so the scheme is only viable with subsidy support, including a Homes England grant bid being prepared. Report P15
Selling the land to a third party for housing was considered but rejected because the cost of remediation is not expected to generate sufficient land values. Report P31
What happens next
An outline planning application is targeted for August 2026, with outline determination expected in March 2027 and reserved matters submission in June 2027. Report P20, P24, P25, P26
Discharge of conditions and enabling works are scheduled to run up to February 2029, with start on site for Phase 1 in February 2029 and final phased practical completion handovers between 2030/31 and 2033. Report P28, P29
Officers will revert to Cabinet for re-approval if the HRA financial parameters are not met or the scheme delivery approach changes substantially. Report P20
The money
£385.6m (before grant and shared ownership sales) Overall MTFP budget envelope supporting the 40 year HRA Business Plan and purchases from OCHL's 10 year development programme alongside direct delivery Report P32
Options considered
Chosen: Progress with the scheme as outlined, with land sold to OCH(D)L and affordable homes bought back into the HRA. Considered the approach that best ensures feasibility and a viable deliverable scheme Report P31
Rejected: Sell the land for housing to a third party. Viability gap from remediation costs is not expected to generate land values beyond current assumptions Report P31
Implications
Financial: HRA parameters that must be met are a payback period of up to 70 years, a positive net present value over 70 years, and an internal rate of return of at least 3%; the decision must sit within the £385.6m MTFP envelope. Report P32, P33
Legal: The Council has power to dispose of land under section 123 and to acquire land under section 121 of the Local Government Act 1972; procurement of goods and services must comply with the Council's Constitution, Contract Rules and the Procurement Act 2023. Report P34
Equalities: No adverse equality impacts identified; 5% of the affordable homes (six properties) will be built to the M4(3) wheelchair accessible standard, and the scheme is expected to improve provision for those in housing need. Report P17, P36
Climate: The scheme is intended as a sustainability exemplar: all-electric homes with air-source heat pumps and photovoltaic technology, a fabric first approach, and a 40% or more reduction in carbon emissions on 2022 building regulations. Report P30
Risk: Risks include planning risk from the absence of any current consent, landfill contamination and remediation costs, density and parking issues, and potential cost overruns; mitigations are detailed financial appraisals, established governance delegations and legal oversight. Report P18, P19, P35
Other: The site is held in the General Fund for General Municipal Purposes; around 20 of the market sale properties are provisionally earmarked for sale to Oxfordshire Cohousing for a co-housing scheme. Report P15, P18
Who and where
Households on the housing register allocated 94 social and council rent homes Report P16
Shared ownership buyers taking up 25 of the affordable homes Report P16
Buyers of 119 properties for outright market sale Report P16
Oxfordshire Cohousing, which is provisionally acquiring around 20 market sale properties for a co-housing scheme Report P18
Existing residents of Hinksey Park ward, including through the minimum 10% public open space Report P13, P17
Oxford City Housing Limited (trading as OX Place) and Oxford City Housing (Development) Ltd, which are delivering the scheme Report P8, P9
Oxford City Council as freeholder of the affordable homes and associated land on completion Report P11, P25
Timeline
late 1960s to 1972: Site used as a landfill, operations ceased in 1972 and land was infilled and covered Report P15
2013 to 2023: Tenant grazed horses on the land Report P15
September 2024: Public consultation on the scheme took place Report P21
January 2026: Regulation 19 consultation on the Local Plan 2045 opened, proposing a minimum of 200 homes at Redbridge Paddock Report P13
26th January 2026: Council approved Regulation 19 consultation for the emerging Local Plan 2045 Report P13
11 February 2026: Council approved the Medium Term Financial Plan supporting the 40 year HRA Business Plan Report P32
18 March 2026: Cabinet considered this report and approved the recommendations Report P2
August 2026: Target date for outline planning submission Report P24
March 2027: Target date for outline planning determination Report P25
June 2027: Target date for reserved matters planning submission Report P26
Dec 2028: Target date for reserved matters determination Report P27
Up to Feb 2029: Discharge of conditions and enabling works Report P28
Feb 2029: Start on site (Phase 1) Report P28
2030/31 to 2033: Final phased practical completion handovers Report P29
Plain English for the jargon
HRA: Housing Revenue Account: the ringfenced account the Council uses for income and spending on its own council housing stock
OCH(D)L: Oxford City Housing (Development) Ltd: a Council owned company set up to develop affordable housing
OCHL: Oxford City Housing Limited, which trades as OX Place
MTFP: Medium Term Financial Plan: the Council's multi-year budget and spending plan
Section 123: Section 123 of the Local Government Act 1972, which sets the Council's power to dispose of land
NPV: Net Present Value: a measure of an investment's future cashflows discounted to today's values
IRR: Internal Rate of Return: the discount rate at which an investment's NPV equals zero
M4(3): Building regulation standard for wheelchair accessible homes, applying here to 5% of the affordable homes
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item171
Resolved
Cabinet resolved to: 1. Give project approval for the development, including the land sale and acquisition of affordable dwellings developed by Oxford City Housing (Development) Ltd (OCH(D)L) for which budgetary provision has been made in the Council’s Housing Revenue Account (HRA) in respect of Redbridge Paddock; 2. Delegate authority to the Deputy Chief Executive - City and Citizens' Services, in consultation with the Cabinet Member for Housing; the Head of Financial Services/Section 151 Officer; and the Head of Law and Governance/Monitoring Officer, to finalise the scheme design and financial appraisals and enter into any necessary agreements and contracts to facilitate the agreed purchase by the Council of the affordable housing (to be held in the HRA) and any associated land, within the identified budget, for the provision of the affordable homes, as set out in this report, on the Redbridge Paddock development, within the project approval; 3. Delegate authority to the Deputy Chief Executive (Place), in consultation with the Cabinet Member for Finance and Asset Management; the Head of Financial Services/Section 151 Officer; and the Head of Law and Governance/Monitoring Officer, to approve the final terms, which will be S123 compliant, and enter into the sale agreement for the Redbridge Paddock site from the General Fund to OCH(D)L;
Word for word from the decision Oxford published for this meeting.Source: mycouncil.oxford.gov.uk
To: Cabinet Date: 18 March 2026 Report of: Clive Tritton/ Carolyn Ploszynski, Director of Economy, Regeneration and Sustainability Title of Report: Project approvals and delegations for Redbridge Paddock affordable housing development
Summary and recommendations Decision being This report seeks project approval and delegations to enable taken: the continued delivery of more affordable housing at the Redbridge Paddock site Key decision: Yes https://mycouncil.oxford.gov.uk/mgIssueHistoryHome.aspx?II d=41810&PlanId=572&RPID=66080022 Cabinet Member: Councillor Linda Smith, Cabinet Member for Housing Councillor Ed Turner, Cabinet Member for Finance and Asset Management Corporate Priority: More Affordable Housing Policy Framework: Housing and Homelessness Strategy 2023 to 2028
Recommendation(s): That Cabinet resolves to: 1. Give project approval for the development, including the land sale and acquisition of affordable dwellings developed by Oxford City Housing (Development) Ltd (OCH(D)L) for which budgetary provision has been made in the Council’s Housing Revenue Account (HRA) in respect of Redbridge Paddock; 2. Delegate authority to the Deputy Chief Executive - City and Citizens' Services, in consultation with the Cabinet Member for Housing; the Head of Financial Services/Section 151 Officer; and the Head of Law and Governance/Monitoring Officer, to finalise the scheme design and financial appraisals and enter into any necessary agreements and contracts to facilitate the agreed purchase by the Council of the affordable housing (to be held in the HRA) and any associated land, within the identified budget, for the provision of the affordable homes, as set out in this report, on the Redbridge Paddock development, within the project approval;
561 3. Delegate authority to the Deputy Chief Executive (Place), in consultation with the Cabinet Member for Finance and Asset Management; the Head of Financial Services/Section 151 Officer; and the Head of Law and Governance/Monitoring Officer, to approve the final terms, which will be S123 compliant, and enter into the sale agreement for the Redbridge Paddock site from the General Fund to OCH(D)L;
Appendix No. Appendix Title Exempt from Publication Appendix 1 Financial Information Yes and risk for Redbridge This information is exempted from Paddock publication under Schedule 12A to the Local Government Act 1972 on the following basis: Commercial Sensitivity Appendix 2 Risk Register
Introduction and background
1. The Council continues to develop a supply programme to deliver more affordable housing through multiple delivery routes. These include direct delivery schemes; partnerships and joint ventures; regeneration projects; acquisitions and advance purchase agreements; and enabling work with Registered Providers, community- led Housing groups, and other partners. Direct delivery schemes can comprise of developments delivered directly by the Council (in the HRA) and also developments brought forward by Oxford City Housing Limited (OCHL) – trading as OX Place.
2. This report relates specifically to the Redbridge Paddock scheme. It seeks to secure Cabinet approvals to progress this OCH(D)L scheme including the sale of the land to OCH(D)L, who will undertake the development, and then the subsequent purchase of all affordable homes into the HRA (as freehold) on completion.
Development programme
3. As an OCHL delivered scheme, this model of delivery proposed would commit the Council to selling the land for development and then buying back the affordable homes and any associated land. The Council will hold the affordable housing stock, and any directly associated land, within the HRA on completion.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement of a GO strategic partnerCabinet resolved to: Note the update as to the progression of the procurement of a strategic partner for the design a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.