Project Approval and Delegations for Sandy Lane Recreation Ground affordable housing scheme

Approved Executive 3 papers

AI summaryOxford City Cabinet approved a £97.5m affordable housing scheme at Sandy Lane Recreation Ground, Blackbird Leys, delivering 331 homes and relocating football pitches to Herschel Crescent.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved100% affordable housing on Sandy Lane Recreation Ground
Money£97,551,302HRA Capital Programme allocation, set February 2026
What happens nextNot stated
Who it affectsResidents of Blackbird LeysGreater Leys Football Club and local football stakeholders

What was decided

Cabinet granted project approval, noting the Full Council's £97,551,302 allocation within the HRA Capital Programme to fund 100% affordable housing at Sandy Lane Recreation Ground. Report P4

Authority was delegated to the Deputy Chief Executive (City and Citizens' Services), in consultation with the Cabinet Member for Housing, the Group Finance Director/Section 151 Officer and the Monitoring Officer, to enter into design and build contracts. Report P4

Cabinet agreed to start the process of appropriating the Sandy Lane site to a planning purpose, following handover of the replacement pitches at Herschel Crescent, and noted a future report on using section 203 of the Housing and Planning Act 2016. Report P4

Why

The scheme forms part of the Council's Affordable Housing Supply Programme, which aims to deliver over 1,600 new affordable homes between April 2025 and March 2029, with at least 850 at Social Rent. Report P9

The site is allocated for residential development in the current Local Plan 2036 and emerging Local Plan 2045, with a minimum of 300 homes proposed. Report P10

Direct delivery by the Council, with OCHL (trading as OX Place) as Development Agent, was considered the most appropriate model for a 100% affordable scheme on Council-owned land. Report P9

What happens next

Football pitch relocation planning submission is targeted for June to November 2026, with new pitches at Herschel Crescent expected to be operational by August 2027. Report P21

An outline planning submission for Sandy Lane is targeted for January 2027, with reserved matters for Phase 1 (60 units) by August 2027 and start on site for Phase 1 in June 2028. Report P22, P23, P24, P26

A further report will be taken to Full Council to appropriate the site from the General Fund to the Housing Revenue Account before practical completion of the first units. Report P27, P34

The money

  • £97,551,302 HRA Capital Programme budget for the Sandy Lane scheme, allocated by Full Council in February 2026 Report P4
  • £385.6m Overall budget envelope (before grant and shared ownership sales) for the Council's affordable housing direct delivery and OCHL purchases Report P32

Options considered

  • Rejected: Do nothing: retain the site in its current recreation use. Would not meet strategic affordable housing objectives and would conflict with current and emerging Local Plan allocations Report P30
  • Rejected: Sell the site on the open market. Would not secure 100% affordable housing or guarantee the desired scale, tenure mix or design quality Report P30
  • Rejected: Partnership or joint venture with registered providers or private sector. Would involve shared control, mixed-tenure outputs and less alignment with the HRA business plan Report P31
  • Rejected: OCHL-led development with sale of land and purchase back of completed homes. Direct delivery by the Council offers stronger value for money and better aligns with HRA financial parameters Report P31
  • Rejected: Alternative housing mixes including market housing or different shared ownership levels. Either financially unviable or would deliver fewer Social Rent homes; would not meet the wholly affordable ambition Report P31
  • Chosen: Direct delivery by the Council with OCHL as Development Agent, fully affordable mix (79% Social Rent, 21% Shared Ownership). Best meets the 100% affordable housing objective, offers value for money for the HRA and aligns with wider strategy Report P9, P15, P31

Implications

  • Financial: The scheme must meet HRA financial parameters: payback of up to 70 years, positive NPV, and IRR of at least 3%; Homes England funding will be sought through the Social and Affordable Housing Programme 26-36. Report P32, P33
  • Legal: Appropriation of the site to planning purposes will rely on section 122 Local Government Act 1972, with possible use of section 203 Housing and Planning Act 2016 to override third-party rights, and a later General Fund to HRA transfer under section 19 Housing Act 1985. Report P34
  • Equalities: An Equalities Impact Assessment found no adverse impacts, with potential to improve provision for those in housing need; 5% of homes will be built to wheelchair accessible M4(3) standard. Report P15, P38
  • Climate: The scheme targets a 40% reduction in carbon emissions against 2022 building standards, zero carbon regulated energy using air-source heat pumps and PV panels, EPC B or above, SuDS and biodiversity net gain. Report P19, P39
  • Risk: Principal risks relate to football pitch reprovision, statutory land appropriation, the planning pathway, HRA financial viability and procurement compliance. Report P37
  • Staffing: OCHL (OX Place) is to be appointed as Development Agent via a Development Services Agreement, which may rely on the teckal exemption subject to legal criteria. Report P9, P35

Who and where

  • People in housing need in Oxford, who will benefit from 331 new affordable homes (261 Social Rent, 70 Shared Ownership) Report P15
  • Greater Leys Football Club and other local football stakeholders, whose pitches will be relocated and upgraded at Herschel Crescent Report P13, P14
  • Residents of Blackbird Leys and surrounding wards, who may be affected by construction and changes to local open space Report P12, P15
  • Littlemore Parish Council, following the surrender of the Herschel Crescent lease back to the City Council Report P14

Timeline

  • February 2026: Full Council allocated £97,551,302 within the HRA Capital Programme for the scheme Report P4
  • June 2026, November 2026: Play pitch relocation planning submission and determination Report P21
  • January 2027: Outline planning submission for Sandy Lane Report P22
  • May 2027, July 2028: Discharge conditions and enabling works Report P25
  • June 2027: Outline planning determination target Report P23
  • August 2027: New playing pitch facilities at Herschel Crescent expected to be operational; reserved matters submission for Phase 1 (60 units) Report P21, P24
  • September 2027: Appropriation of Sandy Lane to a planning purpose Report P22
  • November 2027: Reserved matters determination for Phase 1 Report P25
  • June 2028: Start on site for Phase 1 Report P26
  • November 2029: Appropriation from General Fund to HRA; handover of Phase 1 (60 units) Report P27, P28
  • Summer 2034: Completion of all phases Report P29

Plain English for the jargon

  • HRA: Housing Revenue Account: a ringfenced account local authorities use for income and spending on council housing.
  • OCHL / OX Place: Oxford City Housing Limited, the Council's housing development company, trading as OX Place.
  • DSA: Development Services Agreement between the Council and OCHL setting out the development agent role.
  • Teckal exemption: An exemption from EU/UK procurement rules for contracts awarded to a controlled entity, subject to legal criteria.
  • SuDS: Sustainable Urban Drainage Systems: approaches to manage surface water runoff, such as permeable paving and rain gardens.
  • M4(3): Building regulation standard for wheelchair accessible dwellings.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item172

Resolved

Cabinet resolved to: 1. Grant project approval noting Full Council allocation of the £97,551,302 budget for this scheme within the Housing Revenue Account Capital Programme as part of its budget setting in February 2026, to fund the development of this scheme, as a proposed Housing Revenue Account (“HRA”) project, as set out in this report, within the allocated HRA capital budget and business plan, for the purpose of delivering more affordable housing in Oxford on the Sandy Lane Recreation Ground site; 2. Delegate authority to the Deputy Chief Executive – City and Citizens’ Services in consultation with the Cabinet Member for Housing; the Group Finance Director/Section 151 Officer; and the Council’s Monitoring Officer, to enter into design and build contracts and any other necessary agreements to facilitate the scheme development within the identified budget, except where there is an existing officer delegation within the Council’s Constitution. Facilitating the scheme development includes the relocation of football pitches and providing a pavilion as set out in the report; 3. Agree to commence the process for the appropriation of this Site (as per the red line shown at para 12) to a planning purpose, following completion and handover of the replacement playing pitch facilities at Herschel Crescent and note the intention to bring forward a further report for Cabinet to consider the appropriation of the Site from recreation/open space purposes to planning purposes and the potential to rely on section 203 of the Housing and Planning Act 2016 in the event of interference with private rights; 4. Note the intent to take a report to the Full Council seeking approval for the subsequent appropriation of the Site from the General Fund (GF) to the HRA (prior to practical completion of the scheme or delivery of the first phase, if delivery of the units is phased).
Word for word from the decision Oxford published for this meeting. Source: mycouncil.oxford.gov.uk

Follow this further

Built from Oxford's papers

What the report saysPro

Report to Cabinet

Agenda Item 21

To: Cabinet Date: 18 March 2026 Report of: Director of Economy, Regeneration and Sustainability Title of Report: Project approval and delegations for the Sandy Lane Recreation ground affordable housing development

Summary and recommendations Decision The report seeks project approval and delegations in relation to the being taken: affordable housing scheme at the Sandy Lane Recreation Ground, together with the relocation of football pitches and providing changing facilities and storage as set out in the report. The report also seeks approval to commence the process for the appropriation of the land from its current purpose (including recreation ground and open space) to a planning purpose, within the General Fund. The report further notes the future intention, subject to separate decision of Full Council, to appropriate land from the General Fund (“GF”) to the Housing Revenue Account (“HRA”), prior to completion of the scheme. Key decision: No Issue details - Project Approval and Delegations for Sandy Lane Recreation Ground affordable housing scheme | Oxford City Council Cabinet Councillor Linda Smith, Cabinet Member for Housing Member: Councillor Ed Turner, Cabinet Member for Finance and Asset Management Corporate More Affordable Housing Priority: Policy Housing and Homelessness Strategy 2023 to 2028 Framework:

575 Recommendation(s): That Cabinet resolves to: 1. Grant project approval noting Full Council allocation of the £97,551,302 budget for this scheme within the Housing Revenue Account Capital Programme as part of its budget setting in February 2026, to fund the development of this scheme, as a proposed Housing Revenue Account (“HRA”) project, as set out in this report, within the allocated HRA capital budget and business plan, for the purpose of delivering more affordable housing in Oxford on the Sandy Lane Recreation Ground site; 2. Delegate authority to the Deputy Chief Executive – City and Citizens’ Services in consultation with the Cabinet Member for Housing; the Group Finance Director/Section 151 Officer; and the Council’s Monitoring Officer, to enter into design and build contracts and any other necessary agreements to facilitate the scheme development within the identified budget, except where there is an existing officer delegation within the Council’s Constitution. Facilitating the scheme development includes the relocation of football pitches and providing a pavilion as set out in the report; 3. Agree to commence the process for the appropriation of this Site (as per the red line shown at para 12) to a planning purpose, following completion and handover of the replacement playing pitch facilities at Herschel Crescent and note the intention to bring forward a further report for Cabinet to consider the appropriation of the Site from recreation/open space purposes to planning purposes and the potential to rely on section 203 of the Housing and Planning Act 2016 in the event of interference with private rights; 4. Note the intent to take a report to the Full Council seeking approval for the subsequent appropriation of the Site from the General Fund (GF) to the HRA (prior to practical completion of the scheme or delivery of the first phase, if delivery of the units is phased).

Appendix No. Appendix Title Exempt from Publication Appendix 1 Financial Information This information is exempted from for the Sandy Lane publication under Schedule 12A to the Local Government Act 1972 on the Recreation Ground following basis: development Commercial Sensitivity

Appendix 2 Risk Register No

Appendix 3 Equalities Impact No Assessment

Introduction

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cabinet Sandy Lane Recreation Ground Appendix 2 Risk Register (1)Appendix 105 KB Download
PDF
Project Approval and Delegations for Sandy Lane Recreation Ground affordable housing schemeReport 627 KB DownloadRead as text
PDF
Sandy Lane Full Equalities Impact Assessment v1 (3) (1)Report 190 KB Download

At this meeting

Whole meeting

On this subject at Oxford

Search all
  1. Project Approval and Delegations for Sandy Lane Recreation Ground affordable housing schemeThis decision
  2. Project Approval and Delegations for the Harebell Road affordable housing schemeApproved
  3. Project Approval and Delegations for Redbridge Paddock affordable housing schemeApproved
  4. Project Approval and Allocation of Next Steps Accommodation Programme Funding for Affordable Housing Delivery & Homelessness PreventionAgreed
  5. Pavilions Programme - Project ApprovalApproved

More from Oxford Cabinet

All decisions
MeetingDecisionOutcome
19 Aug 2026 Procurement of a GO strategic partnerCabinet resolved to: Note the update as to the progression of the procurement of a strategic partner for the design a... Noted Open
19 Aug 2026 Controlled Parking Zones (CPZ) Review of existing zones and CIL spendCabinet resolved to: Approve the request to add the West Oxford Controlled Parking Zone (CPZ) to the approved list of... Approved Open
19 Aug 2026 Oxfordshire Infrastructure Strategy (OxIS)Cabinet resolved to: Endorse the Oxfordshire Infrastructure Strategy (OxIS) which has already been endorsed by the Ox... Decided Open
19 Aug 2026 Use of CIL funding to support infrastructure and public realm related to the Cowley Branch LineCabinet resolved to: Ringfence 30% of future CIL income arising from development within 1.5 km of either of the two C... Agreed Open
8 Jul 2026 Thames Valley Strategic Authority Proposal: Update and Implications for Oxford CityCabinet resolved to: 1. Note Oxfordshire County Council’s decision to veto the Thames Valley Foundation Strategic Aut... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies