RESOLVED THAT COMMITTEE: 1. Approve the 2020/21 revised estimate of £381,370 for this committee’s capital programme as set out in Annex 1 of the report; 2. Approve the move of the following capital budgets for 2020/21 to 2021/22: Play Area Improvements 2020/21 - £40,000 Installation of a second parking deck on Chester Ave car park - £1,230,000 and; 3. Recommend to Policy and Finance committee the approval of the following additional scheme budgets: Replacement of Pickup Ford Ranger PK60 HKN - £5,130 Edisford Sports Complex - £5,820 Replacement of CCTV System - £2,800 Replacement of Works Vehicle (Toilet van) YP66 PZF - £14,560
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO COMMUNITY SERVICES COMMITTEE
meeting date: 5 JANUARY 2021 title: REVISED CAPITAL PROGRAMME 2020/21 submitted by: DIRECTOR OF RESOURCES principal author: ANDREW COOK
1 PURPOSE
1.1To approve the 2020/21 revised estimate for this Committee’s capital programme.
1.2Relevance to the Council’s ambitions and priorities:
Community Objectives – none identified. Corporate Priorities – to continue to be a well-managed council, providing efficient services based on identified customer needs. Other Considerations – none identified.
2 2020/21 CAPITAL PROGRAMME BACKGROUND
2.1Eight capital schemes for this Committee’s original estimate budget, totalling £1,614,000, were approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2020 and March 2020 respectively. This included six new schemes for 2020/21 and budget for two 2019/20 schemes that had been moved from the 2019/20 capital programme to the 2020/21 capital programme.
2.2In addition to the original estimate budget above, the following budget changes have been made so far in 2020/21:
Five 2019/20 capital schemes were not completed by 31 March 2020 and had unspent budget available at that date. The total unspent budget of £13,360 on those schemes, known as slippage, has been moved into the 2020/21 capital programme budget, after slippage requests from the budget holders were agreed by the Director of Resources.
One new scheme, Replacement of Works Vehicle (Toilet Van) YP66 PZF, was added to the 2020/21 capital programme at short notice after agreement between the Head of Engineering Services, Director of Resources and Chief Executive in March 2020. This is because the scheme is for the replacement of a toilet van that was written off in a crash, so senior officers agreed prompt ordering of the replacement vehicle so as to minimise the time period where the Council would have to pay hire costs for a stand-in vehicle. No formal budget has been set for this scheme at this stage.
2.3The above slippage and new scheme changes were agreed at senior officer level given that there were no Community Services Committee meetings between March 2020 and September 2020 because of Covid-19. Formal approval for these budget changes is now being sought from members as the changes are incorporated into the proposed revised estimate capital programme that members are being asked to approve in this report.
2.4As a result of the above, the total approved budget for this Committee’s capital programme of twelve schemes was £1,627,360. This is shown at Annex 1.
$vuljrr0d 3 REVISING THE 2020/21 CAPITAL PROGRAMME
3.1We have now discussed each of the schemes in the capital programme with budget holders and revised the programme to reflect their progress and estimated full year expenditure. Following this review, the proposed revised estimate is £381,370 for ten schemes, a reduction of £1,245,990 from the total approved budget. The reasons for this are:
Play Area Improvements 2020/21 (-£40,000): It was initially planned that £12,000 of the 2020/21 play areas budget plus the £28,000 play areas budget moved from 2019/20 in January 2020 was to be spent on a large refurbishment scheme at Kestor Lane play area in Longridge in 2020/21. However, this scheme will not take place this financial year and will need to be moved to 2021/22. This is because the companies we would seek quotes from are still not operating at full capacity due to Covid-19 lockdown periods in- year and staff furlough. This meant getting meaningful quotes from them and then arranging work would have been problematic before the winter period and carrying out groundworks over the winter period is not satisfactory for large play installations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Former Bowling Green, LongridgeRESOLVED THAT COMMITTEE: 1. Approve in principle the Council entering into a licence to occupy with Longridge Town Co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.