RESOLVED THAT COMMITTEE 1. Approve the proposed four-year capital programme (2021/22 to 2024/25) of £538,390 for this committee as set out in Annex 1 to the report, and 2. Recommend to Special Policy and Finance committee the proposed four-year capital programme (2021/22 to 2024/25) of £538,390 for this committee.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
RIBBLE VALLEY BOROUGH COUNCIL DECISION REPORT TO POLICY AND FINANCE COMMITTEE
meeting date: 19 JANUARY 2021 title: CAPITAL PROGRAMME REVIEW 2021/22 TO 2024/25 submitted by: DIRECTOR OF RESOURCES principal author: ANDREW COOK
1 PURPOSE
1.1To recommend the proposed future four-year capital programme (2021/22 to 2024/25) for this Committee.
2 CAPITAL PROGRAMME (2021/22 to 2024/25) BUDGET PROCESS
2.1The future capital programme budget is reviewed and updated each year. In recent years, the Council has been setting a proposed and fully funded five-year capital programme each year. The process of updating the programme has involved reviewing and updating the schemes that were approved in the previous year’s programme for what will become the first four years of the new five-year programme and submitting new bids for year five of the new five-year programme.
2.2Given the additional burdens caused by and priority focus on Covid-19 issues throughout 2020, Budget Working Group has streamlined the capital programme budget update process for this year. This involves moving to a four-year capital programme only, covering 2021/22 to 2024/25, and there being no new capital bids for 2025/26 (year five).
2.3Heads of Service/Directors were therefore asked to review and update the proposed four-year capital programme, as follows:
Review the 2021/22 capital schemes already in the capital programme to confirm that costings are correct and that they will be able to be completed in that year.
Review the current year’s (2020/21) capital schemes to identify whether any may need to be moved to the 2021/22 financial year.
2.4Each committee are being asked to consider and approve the proposed four-year capital programme for their own committee and then the proposed programmes from all committees will be considered alongside each other by the Budget Working Group and Special Policy and Finance Committee.
2.5The proposed four-year capital programme (2021/22 to 2024/25) for this Committee is set out in this report for members to consider and approve.
3 REVIEW OF THE 2021/22 CAPITAL PROGRAMME SCHEMES
3.1There were no schemes in the previously approved 2021/22 capital programme for this Committee, so no changes have been made.
4 REVIEW OF THE CURRENT YEAR’S (2020/21) CAPITAL SCHEMES
4.1Review of progress on the 2020/21 current year schemes by Heads of Service has identified budgets on four schemes proposed to be moved from 2020/21 to the 2021/22 capital programme:
9-21pf 1 of 4 Dewhurst Road, Langho – Resurfacing Works, £65,800: The main resurfacing contract works on this scheme, estimated at £65,800, will now not take place in 2020/21. This is because of additional pre-tender flooding and drainage works needing to be completed first, to enable the site to be clear for the main resurfacing works to take place, and the timescales then involved in the specification and tender process for the main resurfacing contract works. Therefore, the main resurfacing contract works will need to be moved to 2021/22.
Network Infrastructure, £30,000: As reported to this Committee in November 2020, there has been no progress to date on this scheme because ICT staff resources have been focussed on supporting the Council’s Covid-19 response and new ways of working since the end of March 2020. Therefore, the scheme will not take place in 2020/21 and will need to be moved to 2021/22.
Lift replacement at Council Offices, £2,110: The main contract works are now complete. However, the final retention payment of £2,103 on the main contract is still to be paid, because this is not due until twelve months after practical completion of the contract works, which will be summer 2021. Therefore, budget to cover the final retention payment will need to be moved to 2021/22.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.