RESOLVED THAT COMMITTEE 1. Approved the 2020/21 revised estimate of £35,000 for this committee’s capital programme as set out in Annex 1 of the report, and 2. Approved the move of £66,750 of the Economic Development Initiatives capital budget from 2020/21 to 2021/22.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
RIBBLE VALLEY BOROUGH COUNCIL DECISION REPORT TO ECONOMIC DEVELOPMENT COMMITTEE
meeting date: 21 JANUARY 2021 title: REVISED CAPITAL PROGRAMME 2020/21 submitted by: DIRECTOR OF RESOURCES principal author: ANDREW COOK
1 PURPOSE
1.1To approve the 2020/21 revised estimate for this Committee’s capital programme.
1.2Relevance to the Council’s ambitions and priorities:
Community Objectives – none identified.
Corporate Priorities – to continue to be a well-managed council, providing efficient services based on identified customer needs.
Other Considerations – none identified.
2 2020/21 CAPITAL PROGRAMME BACKGROUND
2.1One capital scheme for this Committee’s original estimate budget, totalling £81,750, was approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2020 and March 2020 respectively. The scheme budget had been moved from the 2019/20 capital programme to the 2020/21 capital programme.
2.2In addition to the original estimate budget, there was one 2019/20 capital scheme that was not completed by 31 March 2020. The total unspent budget of £20,000 on that scheme, known as slippage, was moved into the 2020/21 capital programme budget after the slippage request from the budget holder was agreed by the Director of Resources. The slippage request was agreed by the Director of Resources because there were no Economic Development Committee meetings between March 2020 and September 2020 because of Covid-19.
2.3As a result of the above, the total approved budget for this Committee’s capital programme of two schemes was £101,750. This is shown at Annex 1.
3 REVISING THE 2020/21 CAPITAL PROGRAMME
3.1We have now discussed each of the schemes in the capital programme with budget holders and revised the programme to reflect their progress and estimated full year expenditure. Following this review, the proposed revised estimate is £35,000 for two schemes, a reduction of £66,750 from the total approved budget.
3.2The reduction relates to the Economic Development Initiatives scheme, which currently has an overall scheme budget of £81,750. There is currently just one development initiative scheme being considered that, if given the go ahead, would incur expenditure in 2020/21. That scheme is a joint-funded site investigation and development modelling scheme for improving employment land site access at Salthill. If that scheme is approved to go ahead the Council’s expenditure is estimated to be no more than £15,000 in 2020/21.
3.3Therefore, it is recommended that the 2020/21 revised estimate for the overall scheme is reduced to £15,000 and £66,750 of the overall scheme budget is moved to the 2021/22 financial year.
2-21ed 1 of 4 3.4 Annex 1 shows the full capital programme by scheme, including the budget and expenditure to date. The summary position is shown below.
Actual Expenditure including Total commitments Original Budget Slippage Approved Revised Budget as at end of Estimate Moved from from Budget Estimate Moved to December 2020/21 2019/20 2019/20 2020/21 2020/21 2021/22 2020 £ £ £ £ £ £ £ 0 81,750 20,000 101,750 35,000 66,750 0
3.5At the end of December 2020 there had been no spend on the two schemes in this Committee’s revised capital programme, as follows:
Economic Development Initiatives (£15,000): The joint-funded site investigation and development modelling scheme for improving employment land site access at Salthill has still to be approved and bid for. If the scheme is approved to go ahead it is estimated at this stage that the expenditure will be completed before financial year-end.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2026/2027 Climate Change Action PlanRESOLVED THAT COMMITTEE: Approve the 2026/27 Climate Change Action Plan at Appendix 1 of the report for formal adoption.
2025/2026 Climate Change Annual ReportRESOLVED THAT COMMITTEE: Note the content of the 2025/2026 Annual Climate Change Report that includes an update on th...
Tourism Budget and Service ChangesRESOLVED THAT COMMITTEE: 1. Approve the proposed virement to create a temporary staffing budget. 2. Confirm acceptanc...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.