Capital Programme Review 2021/22 - 2023/2024

Approved Committee 1 paper

Economic Development approved this item on Thursday 21 January 2021. Below is the council's own wording, with the papers it was decided on.

Item952

Resolved

RESOLVED THAT COMMITTEE 1. Approve the proposed four-year capital programme (2021/22 to 2024/25) of £66,750 f or this committee, and 2. Recommend to Special Policy and Finance committee the proposed four-year capital programme (2021/22 to 2024/25) of £66,750 for this Committee.
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Economic Development

RIBBLE VALLEY BOROUGH COUNCIL DECISION REPORT TO ECONOMIC DEVELOPMENT COMMITTEE

meeting date: 21 JANUARY 2021 title: CAPITAL PROGRAMME REVIEW 2021/22 TO 2024/25 submitted by: DIRECTOR OF RESOURCES principal author: ANDREW COOK

1 PURPOSE

1.1To recommend the proposed future four-year capital programme (2021/22 to 2024/25) for this Committee.

2 CAPITAL PROGRAMME (2021/22 to 2024/25) BUDGET PROCESS

2.1The future capital programme budget is reviewed and updated each year. In recent years, the Council has been setting a proposed and fully funded five-year capital programme each year. The process of updating the programme has involved reviewing and updating the schemes that were approved in the previous year’s programme for what will become the first four years of the new five-year programme and submitting new bids for year five of the new five-year programme.

2.2Given the additional burdens caused by and priority focus on Covid-19 issues throughout 2020, Budget Working Group has streamlined the capital programme budget update process for this year. This involves moving to a four-year capital programme only, covering 2021/22 to 2024/25, and there being no new capital bids for 2025/26 (year five).

2.3Heads of Service/Directors were therefore asked to review and update the proposed four-year capital programme, as follows:

 Review the 2021/22 capital schemes already in the capital programme to confirm that costings are correct and that they will be able to be completed in that year.

 Review the current year’s (2020/21) capital schemes to identify whether any may need to be moved to the 2021/22 financial year.

2.4Each committee are being asked to consider and approve the proposed four-year capital programme for their own committee and then the proposed programmes from all committees will be considered alongside each other by the Budget Working Group and Special Policy and Finance Committee.

2.5The proposed four-year capital programme (2021/22 to 2024/25) for this Committee is set out in this report for members to consider and approve.

3 REVIEW OF THE 2021/22 CAPITAL PROGRAMME SCHEMES

3.1There were no schemes in the previously approved 2021/22 capital programme for this Committee, so no changes have been made.

1-21ed 1 of 3 4 REVIEW OF THE CURRENT YEAR’S (2020/21) CAPITAL SCHEMES

4.1Review of progress on the 2020/21 current year schemes by Heads of Service identified part of the budget for one scheme that is proposed to be moved from 2020/21 to the 2021/22 capital programme:

 Economic Development Initiatives, +£66,750: The overall scheme budget for 2020/21 is £81,750. There is currently just one development initiative scheme being considered that, if given the go ahead, would incur expenditure in 2020/21. If that scheme is approved to go ahead the Council’s expenditure is estimated to be no more than £15,000 in 2020/21. Therefore, it is proposed that the 2020/21 revised estimate for the overall scheme is reduced to £15,000 and £66,750 of the overall scheme budget is moved to the 2021/22 financial year.

5 PROPOSED FOUR-YEAR CAPITAL PROGRAMME (2021/22 TO 2024/25) 5.1 For this Committee, there were no schemes in the previously approved four-year capital programme 2021/22 to 2024/25. Therefore, the one proposed change from the review of the current year’s 2020/21 capital programme creates a proposed four-year capital programme of one scheme for this Committee, totalling £66,750. This is shown in the table below.

Economic Development 2021/22 2022/23 2023/24 2024/25 TOTAL Committee £ £ £ £ £ Economic Development Initiatives 66,750 66,750 **Moved from 2020/21 Proposed Capital Programme (2021/22 to 2024/25) for this 66,750 0 0 0 66,750 Committee

5.2Members are asked to consider the proposed four-year capital programme (2021/22 to 2024/25) for this Committee and recommend the programme to the Special Policy and Finance Committee for approval.

6 RISK ASSESSMENT

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Review 2021/22: 2023/2024Report 87 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 20 attended
SH
Councillor Stuart HirstChair, present
DB
Councillor David BerrymanCommittee Member, present
SB
Councillor Susan BibbyCommittee Member, present
DB
Councillor David BirtwhistleCommittee Member, present
IB
Councillor Ian BrownCommittee Member, absent
R(
Councillor Robert (Bob) BullerCommittee Member, present
JC
Councillor Judith ClarkCommittee Member, present
R(
Councillor Rosemary (Rosie) ElmsCommittee Member, absent
SF
Councillor Stewart FletcherCommittee Member, present
MF
Councillor Mark FrenchCommittee Member, present
MH
Councillor Mark HindleCommittee Member, absent
SH
Councillor Simon HoreCommittee Member, present

All 20 on the meeting page

On this subject at Ribble Valley

Search all
  1. Capital Programme Review 2021/22 - 2023/2024This decision
  2. Overall Revised Capital Programme 2025/26Approved
  3. Four Year Capital Programme 2026/27 to 2029/30Decided
  4. Revised Capital Programme 2025/26Approved
  5. Capital Programme Review 2026/27 - 2029/30Approved
  6. Revised Capital Programme 2025/26Approved

More from Ribble Valley Economic Development

All decisions
MeetingDecisionOutcome
11 Jun 2026 2026/2027 Climate Change Action PlanRESOLVED THAT COMMITTEE: Approve the 2026/27 Climate Change Action Plan at Appendix 1 of the report for formal adoption. Approved Open
11 Jun 2026 2025/2026 Climate Change Annual ReportRESOLVED THAT COMMITTEE: Note the content of the 2025/2026 Annual Climate Change Report that includes an update on th... Noted Open
11 Jun 2026 Lobbying letter to Government re. Fuel Duty and VATRESOLVED THAT COMMITTEE: Approve the letter at Appendix 1 of the report to use the Council's influence to lobby Gover... Approved Open
11 Jun 2026 Tourism Budget and Service ChangesRESOLVED THAT COMMITTEE: 1. Approve the proposed virement to create a temporary staffing budget. 2. Confirm acceptanc... Approved Open
11 Jun 2026 Appointment to Working GroupsRESOLVED THAT COMMITTEE: Approve the continuation of the Climate Emergency Working Group for 2026/27 municipal year w... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies