RESOLVED THAT COMMITTEE: 1. Approve the 2021/22 revised estimate of £70,910 for this committee’s capital programme as set out in the report, and 2. Approve the transfer of the following capital budgets from 2021/22 to 2022/23 · Dewhurst Road, Langho – Resurfacing works - £62,850 · Network Infrastructure - £30,000 · Committee Administration IT System - £7,600 · Financial system upgrade - £8,430 3. Agree to move the Special Policy and Finance committee to 15 February 2022 to allow officers and budget working group time to manage the budget process.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
RIBBLE VALLEY BOROUGH COUNCIL DECISION REPORT TO POLICY AND FINANCE COMMITTEE
meeting date: 18 JANUARY 2022 title: REVISED CAPITAL PROGRAMME 2021/22 submitted by: DIRECTOR OF RESOURCES principal author: ANDREW COOK
1 PURPOSE
1.1To approve the 2021/22 revised estimate for this Committee’s capital programme.
1.2Relevance to the Council’s ambitions and priorities:
• Community Objectives – none identified.
• Corporate Priorities – to continue to be a well-managed council, providing efficient services based on identified customer needs.
• Other Considerations – none identified.
2 2021/22 CAPITAL PROGRAMME BACKGROUND
2.1Four capital schemes for this Committee’s original estimate budget, totalling £105,510, were approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2021 and March 2021 respectively. All four scheme budgets had been moved from the 2020/21 capital programme to the 2021/22 capital programme.
2.2In addition to the original estimate budget above, the following budget changes have been made so far in 2021/22:
• Four capital schemes were not completed by 31 March 2021 and had unspent budget available at that date. The total unspent budget of £34,280 on those schemes, known as slippage, has been moved into the 2021/22 capital programme budget, after approval by this Committee in June 2021.
• One additional capital scheme with a budget of £40,000 was approved by this Committee in September 2021.
2.3As a result of the above, the total approved budget for this Committee’s capital programme of eight schemes is £179,790. This is shown at Annex 1.
3 REVISING THE 2021/22 CAPITAL PROGRAMME
3.1We have now discussed each of the schemes in the capital programme with budget holders and revised the programme to reflect their progress and estimated full year expenditure. Following this review, the proposed revised estimate is £70,910 for five schemes, which is a reduction of £108,880 from the total approved capital budget. The reasons for this are as follows:
• Dewhurst Road, Langho – Resurfacing Works (Decrease of £62,850): Following the completion of the pre-tender works, there has been less progress than previously planned on specifying the main contract works required and this has been exacerbated by the recent vacancy in the post of Engineering Services Manager. It is expected that the main contract works will now take place in 2022/23, but there may be some survey
04-22pf 1 of 5 design expenditure before 2021/22 year-end to support the main contract works tender specification.
Given the above, it is proposed that the 2021/22 revised estimate is reduced to £6,800 to cover the completed pre-tender works and anticipated survey design costs and that the remainder of the scheme budget, £62,850, is moved to 2022/23.
• Network Infrastructure (Decrease of £30,000): No progress has been able to be made on this scheme since the update in September due to other pressures on the ICT service. This has since been exacerbated by the recent vacancy in the post of ICT Infrastructure Officer and the re-introduction of home working. The ICT Infrastructure Officer's post has now been filled and we expect to engage with suppliers in relation to this scheme in the next month or so. We do not expect the scheme to be complete this financial year.
Given the above, it is proposed that the 2021/22 revised estimate is reduced to nil and the £30,000 scheme budget is moved to 2022/23.
• Committee Administration IT System (Decrease of £7,600): The budget moved from 2020/21 was set aside to fund any IT hardware purchases required to support the use of the system (possibly some laptops). The Head of Legal and Democratic Services wants the system to be used for face-to-face meetings in the Council chamber for a full year before deciding whether any IT hardware is required. Given this, it is proposed that the 2021/22 revised estimate is reduced to nil and the £7,600 scheme budget is moved to 2022/23.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.