RESOLVED THAT COMMITTEE: 1. Approved the 2022/23 revised estimate of £1,397,630 for this Committee’s capital programme, as set out in the Annex to the report. 2. Approved the transfer of the following capital budgets from 2022/23 to 2023/24: · Clitheroe Market Improvements, £72,600. · Replacement of Pest Control Van PK13 FJP, £32,280. · Replacement of Dog Warden Van PE64 EYC, £32,500. · Equity Share Option Schemes, £422,130. · Affordable Housing – Longridge, £1,625,950.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO HEALTH AND HOUSING COMMITTEE
meeting date: 19 JANUARY 2023 title: REVISED CAPITAL PROGRAMME 2022/23 submitted by: DIRECTOR OF RESOURCES principal author: ANDREW COOK
1 PURPOSE
1.1To approve the 2022/23 revised estimate for this Committee’s capital programme.
1.2Relevance to the Council’s ambitions and priorities: Community Objectives – none identified. Corporate Priorities – to continue to be a well-managed council, providing efficient services based on identified customer needs. Other Considerations – none identified.
2 2022/23 CAPITAL PROGRAMME BACKGROUND
2.1Six capital schemes for this Committee’s original estimate budget, totalling £782,540, were approved by the Policy and Finance Committee and Full Council at their meetings in February 2022 and March 2022 respectively. This included two new scheme budgets for 2022/23 and budgets on five schemes that had been moved from the 2021/22 capital programme to the 2022/23 capital programme.
2.2In addition to the original estimate budget above, the following budget changes have been made so far in 2022/23:
Two 2021/22 capital schemes were not completed by 31 March 2022 and had unspent budget available at that date. The total unspent budget of £657,620 on those schemes, known as slippage, was moved into the 2022/23 capital programme budget, after approval by this Committee in June 2022.
Two additional capital schemes, with budgets totalling £2,166,450, were approved by Policy and Finance Committee in March 2022. The budget of £118,370 on one of the schemes was funded by reducing the budget on another capital scheme by £118,370. The total additional new budget funding was therefore £2,048,080. NOTE - The budget of £2,048,080 on one of the schemes was subsequently split into two separate schemes for reporting purposes, with budgets of £422,130 and £1,625,950 respectively.
Additional 2022/23 external funding of £48,799 was received from Onward Homes for one scheme, so the budget on that scheme was increased by £48,800.
Additional budgets on two existing schemes, totalling £44,000, were approved by Policy and Finance Committee in September 2022.
2.3As a result of the above, the total approved budget for this Committee’s capital programme of ten schemes was £3,581,040. This is shown at Annex 1.
4-23hh 1 of 6 3 REVISING THE 2022/23 CAPITAL PROGRAMME
3.1We have now discussed each of the schemes in the capital programme with budget holders and revised the programme to reflect their progress and estimated full year expenditure. Following this review, the capital programme revised estimate is £1,397,630 for eight schemes, a reduction of £2,183,410 from the total approved budget. The reasons for this are as follows:
Clitheroe Market Improvements (-£72,600): The consultants work to consider the strategic way forward for the next stage of market improvements is in progress. This work has included meeting with market traders in both October and December 2022. The consultant’s report is expected in early 2023 and following this a plan for the next stage of the market improvements will be drawn up and reported to members of this Committee in March 2023. The improvement works would then be undertaken in 2023/24, subject to the plan being agreed by members. Therefore, the £6,000 cost for the market consultants report, which has now been confirmed as being funded by the UK Shared Prosperity Fund, is the only spend expected on this scheme in 2022/23.
Given the above, it is proposed that £72,600 of the scheme budget is moved to the 2023/24 capital programme and the 2022/23 revised estimate budget is reduced to £6,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Health Act Funerals PolicyRESOLVED THAT COMMITTEE: 1. Approve the proposed policy ‘Public Health Act Funerals Policy/Procedure. 2. Permit the H...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.