RESOLVED THAT COMMITTEE: Considered and proposed a future 5-year capital programme for this Committee’s services of £753,300 for onward recommendation to the Special Policy and Finance Committee meeting for the period 2023/24 to 2027/28, based on: · The proposals included in the report; and · Any capital bid suggestions and amendments that members wished to make, of which there were none.
Word for word from the decision Ribble Valley published for this meeting.Source: democracy.ribblevalley.gov.uk
2.1The Council usually operates a five-year capital programme, but only a three-year capital programme for 2022/23 to 2024/25 was approved last year. This is because the Council was awaiting the outcome of the Government’s fair funding review before committing to setting a longer-term five-year capital programme. Committees had however submitted capital scheme bids for 2025/26 to 2026/27 as part of last year’s capital programme review.
2.2This year, the aim is to return to a five-year capital programme, covering the period 2023/24 to 2027/28. Therefore, Heads of Service were asked to: review the capital schemes already approved for 2023/24 to 2024/25 review any previously submitted capital scheme bids for 2025/26 to 2026/27; and submit new capital scheme bids for 2027/28.
2.3Once this Committee has considered the schemes within this report, and any further schemes that members may wish to submit, the capital programme reviews and new bids for each committee area will then be considered alongside each other by the Budget Working Group and Policy and Finance Committee in producing the Council’s capital programme for 2023/24 to 2027/28.
3 REVIEW OF PREVIOUSLY APPROVED CAPITAL PROGRAMME SCHEMES FOR 2023/24 TO 2024/25
3.1For this Committee there were originally six schemes approved for the 2023/24 to 2024/25 capital programme, totalling £206,280. These schemes are shown in Annex 1.
3.2Review of the schemes by Heads of Service has resulted in proposed amendments to all of the previously approved schemes. This is mainly as a result of updating the scheme values for increased levels of price inflation since last year’s capital programme review. The one exception to this is the Revenues and Benefits Replacement Server scheme, where an updated 2022 quote for the server plus inflation uplift to 2023/24 prices showed the amended scheme value to be lower than the previously approved amount.
16-23pf 3.3 The table below shows the financial impact of the proposed amendments put forward by Heads of Service. The proposed amendments for each scheme are shown in Annex 1.
2023/24 2024/25 TOTAL £ £ £ Previously Approved Capital Programme Costs for Policy and 118,200 88,080 206,280 Finance Committee Proposed Cost Amendments to the Previously Approved Capital 6,500 6,220 12,720 Programme Amended Capital Programme for 124,700 94,300 219,000 Policy and Finance Committee
3.4The proposed amendments to the previously approved capital schemes for 2023/24 to 2024/25 will result in increased costs of £12,720, thus increasing the previously approved capital programme for this Committee to £219,000.
4 REVIEW OF PREVIOUSLY SUBMITTED CAPITAL SCHEME BIDS FOR 2025/26 TO 2026/27
4.1For this Committee, six capital scheme bids were submitted last year (2021) for the financial years 2025/26 to 2026/27, totalling £415,100. A list of the scheme bids are shown in Annex 2. The individual scheme bid documents were reported to this Committee in January 2022.
4.2Review of these previously submitted bids by Heads of Service has resulted in proposed amendments to all the bids, mainly as a result of updating the bid values for inflation since the bids were submitted last year. Please note that for three of the bids, currently included as 2025/26 bids, it has been requested that they are brought forward to as soon as possible, which would be inclusion in the 2023/24 capital programme.
4.3The table below shows the financial impact of the proposed bid amendments put forward by Heads of Service. The proposed bid amendments for each scheme are shown in Annex 2.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.