Ribble Valley Borough Council
Community Services, Tuesday 28 May 2024 at 6.30pm

Capital Outturn 2023/24

Approved Committee 1 paper

Community Services approved this item on Tuesday 28 May 2024. Below is the council's own wording, with the papers it was decided on.

Item19

Resolved

RESOLVED THAT COMMITTEE: 1. Approve the slippage of £287,850 as set out at paragraph 3.6 of the report. 2. Approve an additional £42,000 for the Changing Places Toilet Scheme in 2024/25, fully funded from DLUHC grant.
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Community Services

DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO COMMUNITY SERVICES COMMITTEE

meeting date: 28 MAY 2024 title: CAPITAL OUTTURN 2023/24 submitted by: DIRECTOR OF RESOURCES AND DEPUTY CHIEF EXECUTIVE principal author: LAWSON ODDIE

1 PURPOSE

1.1The purpose of this report is to review the final outturn of the 2023/24 capital programme for this Committee and to seek member approval for the slippage of some capital scheme budgets from the 2023/24 financial year to the 2024/25 financial year.

1.2Relevance to the Council’s ambitions and priorities:  Community Objectives – none identified.  Corporate Priorities - to continue to be a well-managed council providing efficient services based on identified customer need.  Other Considerations – none identified.

2 2023/24 CAPITAL PROGRAMME BACKGROUND

2.1There were 14 capital schemes for this Committee’s original estimate budget, totalling £1,095,750. These were approved by the Special Policy and Finance Committee and Full Council at their meetings in February 2023 and March 2023 respectively. This included 9 new schemes for 2023/24 and budget for 5 schemes that had been moved from the 2022/23 capital programme.

2.2In addition, at the end of the 2022/23 financial year a total budget of £53,950 covering 6 schemes was unspent at year end and was moved to the 2023/24 financial year (two of these were schemes where other budget had also previously been moved from the 2022/23 financial year).

2.3This unspent budget that was moved is known as slippage and was moved into the 2023/24 capital programme budget after approval by this Committee in May 2023.

2.4There were 4 further capital programme scheme approvals in year totalling £321,510.

2.5As a result of the above elements, the total approved budget for this Committee’s capital programme of 21 schemes was £1,471,210.

2.6Later in the year the capital programme budget was revised to £960,410 in respect of 19 schemes and was then approved by the Special Policy and Finance Committee in February 2024. This followed a review of progress on all schemes in the capital programme and included moving budget of £440,170 on 5 schemes into the 2024/25 financial year. The revised estimate budget is shown at Annex 1.

2.7During the financial year this Committee has received reports monitoring the progress of schemes within the capital programme.

7-24cm 1 of 24 3 CAPITAL OUTTURN 2023/24

3.1Annex 1 shows this Committee’s capital programme outturn position by scheme, including budget approvals, actual expenditure in-year and requested slippage into 2024/25. The table below summarises the final outturn position.

Total Requested Budget Original Slippage Additional Approved Revised Budget Actual Slippage Moved from Estimate from Approvals Budget Estimate Moved to Expenditure into 2022/23 2023/24 2022/23 2023/24 2023/24 2023/24 2024/25 2023/24 2024/25 £ £ £ £ £ £ £ £ £

616,310 479,440 53,950 321,510 1,471,210 960,410 440,410 625,177 287,850

3.2Actual expenditure on this Committee’s capital programme was £625,177, which is 65% of the revised estimate budget. 3.3 Of the 19 schemes in the revised capital programme 10 were completed in year. 3.4 The remaining 9 schemes were not completed in-year, resulting in slippage from the 2023/24 financial year in to the 2024/25 financial year. 3.5 Annex 2 shows details for each scheme of:  the outcomes achieved for schemes that have been completed  where schemes have yet to be completed, requests for committee approval for slippage into the 2024/25 financial year. 3.6 Shown below is a summary of the slippage requests for this committee:

Slippage Cost Requested Scheme Centre £

BGCAF Refurbishment of Bowling Green Café - Castle Grounds 2,040

CASKP** Castle Keep Lime Repointing Works and Repairs -2,950

CBAYS Replacement of Concrete Bays to rear of Depot 32,400

CHPLT Changing Places Toilet Scheme 134,120

LDASR** Longridge Depot 'Ambulance Shed' Refurbishment -590

MARPD Mardale Playing Pitches Drainage 12,730

PLYRP Play Areas Refurbishment Programme 17,070

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Outturn 2023/24Report 194 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 24 attended
SH
Councillor Stuart HirstChair, present
RN
Councillor Richard NewmarkVice-Chair, apologies
JA
Councillor Jan Alcock JPCommittee Member, present
JA
Councillor John AthertonCommittee Member, expected
KB
Councillor Karl BarnsleyCommittee Member, present
IB
Councillor Ian BrownCommittee Member, present
SB
Councillor Stella Brunskill JPCommittee Member, present
RC
Councillor Ryan CorneyCommittee Member, present
SC
Councillor Sophie CowmanCommittee Member, present
MG
Councillor Michael GravestonCommittee Member, present
DO
Councillor Donna O'RourkeCommittee Member, present
MR
Councillor Mary RobinsonCommittee Member, apologies

All 24 on the meeting page

On this subject at Ribble Valley

Search all
  1. Capital Outturn 2023/24This decision
  2. Capital Outturn 2025/26Approved
  3. Capital Outturn 2025/26Approved
  4. Capital Outturn 2025/26Approved
  5. Capital Outturn 2024/25Approved
  6. Capital Outturn 2024/25Approved

More from Ribble Valley Community Services

All decisions
MeetingDecisionOutcome
25 Aug 2026 Ribblesdale PoolIt was agreed that the solar panel element should be removed from the current contract and considered separately. Thi... Agreed Open
25 Aug 2026 Clitheroe WellsRESOLVED THAT COMMITTEE: Authorise to the Director of Community Services to continue to take the required steps towar... Decided Open
25 Aug 2026 Former Bowling Green, LongridgeRESOLVED THAT COMMITTEE: 1. Approve in principle the Council entering into a licence to occupy with Longridge Town Co... Approved Open
25 Aug 2026 Exclusion of Press and PublicThat by virtue of the next item of business being exempt information under Paragraph 3 of Part 1 of Schedule 12A of t... Decided Open
26 May 2026 Capital Outturn 2025/26RESOLVED THAT COMMITTEE: Approved the slippage of £1,000,940 as set out at paragraph 3.6 of the report. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies