Ribble Valley Borough Council
Community Services, Tuesday 6 January 2026 at 6.30pm

Capital Programme Review 2026/27 to 2029/30

Agreed Committee 1 paper

AI summaryCommunity Services Committee approved a £4,035,150 capital programme for 2026/27 to 2029/30, raising the refuse collection vehicle budget by £8,970 and cutting the total by £2,030.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedFor onward recommendation to Policy and Finance Committee
Money£4,035,150Net decrease of £2,030 from original £4,037,180
What happens nextForward to Policy and Finance CommitteeFurther amendments likely at Revised Estimate
Who it affectsCommunity Services Committee schemes35 schemes across refuse, parks, vehicles, pitches

What was decided

Approve the future capital programme for Community Services for 2026/27 to 2029/30, based on the report's proposals. Report P6

Increase the 2026/27 refuse collection vehicle purchase budget by £8,970 following a recent procurement exercise and tendered price. Report P3, P5

Net result is a £2,030 decrease in the Committee's capital programme, taking the total to £4,035,150. Report P3, P4, P6

Why

The report reviews schemes that were approved into the capital programme in March 2025 for 2026/27 to 2029/30. Report P3

Policy and Finance Committee on 16 September 2025 asked that no 2030/31 bids be invited, given uncertainty over finance reform and local government reorganisation, and that the existing programme be reviewed for reprofiling. Report P3

The refuse vehicle budget increase reflects the actual tendered price from a recent procurement exercise that included that vehicle. Report P3, P5

What happens next

The approved programme goes to Policy and Finance Committee for the next stage of approval. Report P6

Further amendments to 2026/27 are likely as part of the current-year capital programme review at Revised Estimate, covered in a separate report to this Committee. Report P3

Heads of Service have been asked to identify essential capital schemes needed for business as usual in 2030/31, which would require fresh capital bids if brought forward. Report P3

The money

  • £4,037,180 Original total of 35 schemes approved for 2026/27 to 2029/30 Report P3, P5
  • £11,000 Chatburn/Edisford/Bolton-by-Bowland Public Conveniences refurbishment brought forward from 2026/27 to 2025/26 Report P3, P5
  • £8,970 Increase to Replacement of Refuse Collection Vehicle VE18 JXP based on tendered price Report P3, P5
  • £4,035,150 Revised Community Services Committee capital programme total across 35 schemes Report P3, P5, P6
  • £2,030 Net decrease to the previously approved capital programme Report P6

Options considered

  • Chosen: Approve the proposed capital programme as set out in the report. Reflects review of existing schemes and updated refuse vehicle tender price Report P3, P6

Implications

  • Financial: Capital programme for this Committee reduces by £2,030 to £4,035,150 across the four-year period. Report P3, P6
  • Risk: Sound financial planning for known capital commitments is said to safeguard the Council's reputation. Report P6
  • Equalities: Equality and Diversity issues are examined as part of the capital bid appraisal process. Report P6
  • Other: No technical, environmental, legal or political implications identified by officers. Report P6

Who and where

  • Community Services Committee services, including refuse collection, play areas, car parks, public conveniences, parks and grounds maintenance, and the Salthill Depot refurbishment Report P9, P10, P11, P12, P13
  • Policy and Finance Committee, which will consider the programme next Report P6

Timeline

  • March 2025: Schemes originally approved into the capital programme for 2026/27 to 2029/30 Report P3
  • 16 September 2025: Policy and Finance Committee gave guidance not to invite 2030/31 bids and to review for reprofiling Report P3
  • December 2025: Report signed off by the Senior Accountant and Director of Resources and Deputy Chief Executive Report P7
  • 6 January 2026: Community Services Committee approved the revised four-year capital programme Report P2
  • Revised Estimate: Further amendments to 2026/27 expected, covered in a separate report to this Committee Report P3

Plain English for the jargon

  • Capital programme: The council's planned spending on long-term assets such as vehicles, equipment and building works, spread over several financial years.
  • Reprofile: Move a planned scheme from one financial year to another, usually to a later year.
  • Revised Estimate: A mid-year review of the current year's budget and capital programme.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item522

Resolved

It was further agreed to increase the budget for 2026/27 by £8,970 for the refuse collection vehicles purchase scheme. As such, the proposed amendments to the previously approved capital programme would decrease the capital programme by £2,030 to £4,035,150. RESOLVED THAT COMMITTEE: Approve the future capital programme for this Committee’s services for onward recommendation to Policy and Finance Committee for the period 2026/27 to 2029/30, based on the proposals included in the report.
Word for word from the decision Ribble Valley published for this meeting. Source: democracy.ribblevalley.gov.uk

Follow this further

Built from Ribble Valley's papers

What the report saysPro

Report to Community Services

DECISION RIBBLE VALLEY BOROUGH COUNCIL REPORT TO COMMUNITY SERVICES COMMITTEE

meeting date: 6 JANUARY 2026 title: CAPITAL PROGRAMME REVIEW submitted by: DIRECTOR OF RESOURCES principal author: JEAN WADDINGTON

1. PURPOSE 1.1. To ask Committee to consider the future capital programme for this Committee, covering the period 2026/27 to 2029/30. 2. BACKGROUND 2.1. This report reviews the schemes that were approved into the capital programme in March 2025, for the financial years 2026/27 to 2029/30. 2.2. Due to the uncertainty regarding the outcome of the finance reforms and also local government reorganisation, at their meeting on 16 September 2025, Policy and Finance Committee gave guidance that no bids for 2030/31 of the capital programme should be invited and that the existing programme should be reviewed for any schemes that could be reprofiled to a later year. 2.3. In respect of 2030/31, Heads of Service have instead been asked to identify essential capital schemes or items that are necessary for the continuation of ‘business as usual’, so that these can be separately noted. If these were to be brought forward as proposals for inclusion in the capital programme in the future, this would involve the submission of detailed capital bids and consideration by committee. 3. REVIEW OF THE EXISTING CAPITAL PROGRAMME 2026/27 TO 2029/30 3.1. For this Committee there were originally 35 schemes approved for the financial years 2026/27 to 2029/30, totalling £4,037,180. 3.2. Part of one scheme (Refurbishment of Chatburn/Edisford/Bolton-by-Bowland Public Conveniences) totalling £11,000 has since been brought forward from 2026/27 to 2025/26. 3.3. A further amendment was also agreed to the refuse collection vehicle purchase scheme in 2026/27 following a recent procurement exercise that included that vehicle. It was agreed that this budget be increased by £8,970 based on the tendered price. 3.4. This amendment has resulted in a capital programme for this committee of 35 schemes totalling £4,035,150, and is shown at Annex 1. 3.5. Further amendments to the capital programme 2026/27 are likely to occur as a result of the review of the current year capital programme that takes place at Revised Estimate. These changes are covered in a separate report presented to this Committee. 3.6. A summary of the reviewed Capital Programme is given below:

Scheme Name 2026/27 2027/28 2028/29 2029/30 TOTAL

Current Approved 1,592,150 715,000 1,210,300 519,730 4,037,180 Capital Programme Refurbishment of Chatburn -11,000 -11,000 Public Conveniences Increased Cost of Refuse Collection Vehicle scheme: - Replacement of Refuse 8,970 8,970 Collection Vehicle VE18 JXP Capital Programme 1,590,120 715,000 1,210,300 519,730 4,035,150 Following Review

4. CONCLUSION 4.1. The proposed amendments to the previously approved capital programme would decrease the capital programme by £2,030 to £4,035,150. 5. RISK ASSESSMENT 5.1. The approval of this report may have the following implications: • Resources – The proposed amendments to the existing approved capital programme would decrease the capital programme by £2,030. • Technical, Environmental and Legal – None. • Political – None. • Reputation – Sound financial planning for known capital commitments safeguards the reputation of the Council. • Equality and Diversity – Equality and Diversity issues are examined as part of the capital bid appraisal process. 6. RECOMMENDED THAT COMMITTEE 6.1. Consider and propose a future capital programme for this Committee’s services for onward recommendation to Policy and Finance Committee for the period 2026/27 to 2029/30, based on the proposals included in this report.

SENIOR ACCOUNTANT DIRECTOR OF RESOURCES AND DEPUTY CHIEF EXECUTIVE CMX-26/JW/AC December 2025

For further background information please ask for Jean Waddington. BACKGROUND PAPERS – None ANNEX 1 Community Services Committee Proposed Four Year Capital Programme 2026/27 to 2029/30

2026/27 2027/28 2028/29 2029/30 TOTAL SCHEME TITLE £ £ £ £ £

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Review 2026/27 to 2029/30Report 157 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 24 attended
SH
Councillor Stuart HirstChair, present
JA
Councillor Jan Alcock JPCommittee Member, present
SA
Councillor Stephen AtkinsonCommittee Member, present
KB
Councillor Karl BarnsleyCommittee Member, present
DB
Councillor David BirtwhistleCommittee Member, present
IB
Councillor Ian BrownCommittee Member, present
SB
Councillor Stella Brunskill JPCommittee Member, present
RC
Councillor Ryan CorneyCommittee Member, expected
SC
Councillor Sophie CowmanVice-Chair, present
LE
Councillor Louise EdgeCommittee Member, expected
MG
Councillor Michael GravestonCommittee Member, present
DO
Councillor Donna O'RourkeCommittee Member, present

All 24 on the meeting page

On this subject at Ribble Valley

Search all
  1. Capital Programme Review 2026/27 to 2029/30This decision
  2. Overall Revised Capital Programme 2025/26Approved
  3. Four Year Capital Programme 2026/27 to 2029/30Decided
  4. Revised Capital Programme 2025/26Approved
  5. Capital Programme Review 2026/27 - 2029/30Approved
  6. Revised Capital Programme 2025/26Approved

More from Ribble Valley Community Services

All decisions
MeetingDecisionOutcome
25 Aug 2026 Ribblesdale PoolIt was agreed that the solar panel element should be removed from the current contract and considered separately. Thi... Agreed Open
25 Aug 2026 Clitheroe WellsRESOLVED THAT COMMITTEE: Authorise to the Director of Community Services to continue to take the required steps towar... Decided Open
25 Aug 2026 Former Bowling Green, LongridgeRESOLVED THAT COMMITTEE: 1. Approve in principle the Council entering into a licence to occupy with Longridge Town Co... Approved Open
25 Aug 2026 Exclusion of Press and PublicThat by virtue of the next item of business being exempt information under Paragraph 3 of Part 1 of Schedule 12A of t... Decided Open
26 May 2026 Capital Outturn 2025/26RESOLVED THAT COMMITTEE: Approved the slippage of £1,000,940 as set out at paragraph 3.6 of the report. Approved Open