FARNBOROUGH LEISURE CENTRE - DEMOLITION

Approved Executive 1 paper

Cabinet approved this item on Tuesday 8 June 2021. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

RESOLVED that (i) the appointment of Wilmott Dixon Construction Limited, through the Procurement Hub Framework, to carry out the demolition and site clearance of Farnborough Leisure Centre and to undertake further survey works upon completion of the site clearance, as set out in Report No. RP2103, be approved; (ii) the release of £1,135,000 funding from the Capital Programme for the demolition works and associated project management, as agreed by the Council on 25th February, 2021, be approved; (iii) a further budget of £20,000 to fund ongoing project delivery costs and the consideration of alternative options, be approved; and (iv) following further investigation of the available options for the preservation of the mosaic murals, the Chief Executive, in consultation with the Major Projects and Property Portfolio Holder, be authorised to commission the necessary works.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

Summary

This report requests the approval of funding and the appointment of contractors to enable the Council to proceed with the demolition of the vacant Farnborough leisure centre building.

Recommendations

Cabinet is recommended to:

1. Confirm the appointment of Willmottt Dixon Construction Limited through the Procurement Hub framework to carry out the demolition and site clearance of Farnborough Leisure Centre and to undertake further survey works upon completion of site clearance.

2. Agree the release of £1,135,000 funding from the Capital Programme, as approved by Council on 25 February 2021 for the demolition works and associated project management.

3. Note that a further budget of £20,000 is required to fund ongoing project delivery costs and consideration of alternative options.

1. INTRODUCTION

1.1The purpose of this report is to seek approval to proceed with the demolition and site clearance of Farnborough Leisure Centre and to undertake the required site investigation works following site clearance to inform costs for the development of the new Leisure and Civic Hub building prior to Final Business Case.

1.2This is a key decision because of the level of capital spend required to deliver the works.

Background

2.1In January 2021, Cabinet took the decision not to re-open Farnborough Leisure Centre due to the significant cost implications on the extension of the leisure contract as a result of the COVID-19 pandemic. Following an interim use as a community testing venue the building is now vacant and can be cleared for demolition.

2.2From 1st May, the vacant site will attract a rate payment requirement of £3,471 per week which the Council will need to fund until the Centre is decommissioned and demolished. There will be a three-month rates exemption period applicable during which time the Council could commence demolition work to ensure rates are not applicable.

2.3Work is underway to develop a detailed feasibility study for the delivery of a new Leisure Centre or Leisure and Civic Hub project to replace the existing Leisure Centre and relocate Council offices within the Civic Quarter regeneration programme. This work is ongoing, and the Council is committed to developing a new Leisure Centre in Farnborough as part of its town centre regeneration. The emerging Masterplan for the Civic Quarter identifies the current site as the location for the new facility and will be part of a wider public consultation this summer.

2.4As part of the commitment for a new leisure centre, Cabinet have already approved the procurement of Willmottt Dixon Construction through the Procurement Hub Framework for delivery of the scheme following final business case approval. In line with this framework, Willmottt Dixon have been working with the project team during feasibility to develop the scheme and undertake surveys and other activities to inform project scope and cost development.

2.5Following the decision not to re-open the Leisure Centre, Willmottt Dixon were asked to prepare a fee proposal for the demolition, site clearance and intrusive ground investigation work at the Leisure Centre as well as a detailed programme for the works on a ‘as soon as possible’ basis.

2.6A detailed fee proposal including evidence of market testing has been submitted by Willmottt Dixon. This has been reviewed by the projects Technical Advisor and Cost Consultants, Artelia UK, who have recommended acceptance of the proposal (Appendix 1).

3. DETAILS OF THE PROPOSAL

General

3.1Cabinet is asked to approve the appointment of Willmott Dixon Construction to undertake demolition of the existing Farnborough Leisure Centre as soon as possible in line with the fee proposal and tender report which has been reviewed and validated by our Technical Advisor and Cost Consultant.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FARNBOROUGH LEISURE CENTRE: DEMOLITIONReport 127 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
DC
Councillor David CliffordChairman, present
KM
Councillor Ken MuschampVice-Chair, present
MM
Councillor Marina MunroCommittee Member, present
AN
Councillor Adrian NewellCommittee Member, present
MS
Councillor Maurice SheehanCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantCommittee Member, present

On this subject at Rushmoor

Search all
  1. FARNBOROUGH LEISURE CENTRE - DEMOLITIONThis decision
  2. Proposed New Farnborough Leisure Centre, Queensmead Car Park, Kingsmead, Farnborough - Application No. 25/00583/FULPPAgreed
  3. Farnborough leisure centre - construction contract awardNoted
  4. Farnborough leisure centre - update and next stepsNoted
  5. Farnborough leisure centre - next stepsApproved
  6. Farnborough regeneration and leisure and cultural hub - next stepsNoted

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies