FARNBOROUGH LEISURE CENTRE - CONSTRUCTION CONTRACT AWARD
NotedExecutive2 papers
AI summaryRushmoor Cabinet notes progress on the Farnborough Leisure Centre and authorises officers, subject to planning permission, to enter into a construction contract with Alliance Leisure Services Limited.
Written from the decision and the officer reportPDF Pro
OutcomeNotedSubject to planning permission, Executive Director to sign
Money£18.5m grant plus £8.8m borrowingTotal over £20m capital expenditure
What happens nextAwaiting planning permissionThen enter into Development Management Agreement
Who it affectsFarnborough residents and leisure usersNew leisure centre on Queensmead and Pinehurst sites
What was decided
Cabinet noted design progress and changes made during the leisure centre operator procurement process. [D]
Cabinet noted progress of the planning submission for the Farnborough Leisure Centre. [D]
Subject to planning permission being granted and review of the contractor's proposals, the Executive Director, in consultation with the Executive Head of Finance, the Interim Monitoring Officer, the Corporate Manager for Legal Services and the Healthy Communities and Active Lives Portfolio Holder, was authorised to enter into a Development Management Agreement with Alliance Leisure Services Limited. [D, 10.5, 11.2] Report 10.5, 11.2
Why
A new leisure centre for Farnborough is a significant priority for local people and the Council's Cabinet, and entering into the development agreement with Alliance for the construction phase is considered the most effective and least risk option for delivery. [11.1] Report 11.1
Public consultation between 30 June and 25 July 2025 attracted around 350 residents to in-person events, alongside digital engagement, and stakeholders including local sports clubs, accessibility groups, and national governing bodies were engaged. [9.3, 9.6, 9.7, P8, P9, P10] Report 9.3, 9.6, 9.7, P8, P9, P10
Not providing a new facility would have a significant impact on the leisure procurement and reduce the attractiveness of the current offer to the market, and would likely be unpopular with residents. [9.1, 9.2] Report 9.1, 9.2
What happens next
Officers recommend that Queensmead and Pinehurst Car Parks are appropriated to planning purposes and section 203 of the Housing and Planning Act 2016 is used to override third-party rights, subject to receipt of planning permission. [10.8, 10.9] Report 10.8
The risk register will be agreed and finalised with input from legal prior to entering into contract, and the live risk register is at Exempt Appendix G. [10.2, P41] Report P41
The Council will be required to borrow an additional £8.8m to enable the project, with forecasts included in the 2026/27 budget and MTFS subject to Council approval on 26 February 2026. [10.13, 10.15] Report 10.13, 10.15
The money
£20m Levelling Up Fund (now Local Regeneration Fund) awarded by government in 2023 for a leisure and cultural hub in Farnborough Report 10.12
£18.5m of the Levelling Up Fund to be utilised to deliver the Farnborough Leisure Centre Report 10.12
£8.8m additional borrowing required from the Council to enable the project Report 10.13
over £20m of capital expenditure the Council would be committing to Report 10.20
Options considered
Chosen: Enter into a Development Management Agreement with Alliance Leisure Services Limited for RIBA Stage 5 (construction and handover) onwards. Considered the most effective and least risk option for delivery with protections in place [11.1] Report 11.1, 10.5
Rejected: Not to deliver a new facility and retain the existing Queensmead car park and find an alternative use for the other land. Not in line with Council priorities, would likely be unpopular with residents, and would have a significant impact on the leisure procurement [9.1, 9.2] Report 9.1, 9.2
Implications
Financial: The Council will be accepting financial risks including additional borrowing, interest rate risk, and cost overruns. The MTFS shows a projected situation of not being able to set a legal budget in 2028-2029, so there is no capacity within organisational finances to absorb the impact from contract failure. [10.3, 10.6, 10.13, 10.19] Report 10.3, 10.6, 10.13, 10.19
Risk: Risks include site ground conditions, contractor solvency, cost overruns, inflationary increases, and stakeholder management. The live risk register sets out current risk ownership and the top 10 risks are reported to MHCLG. [10.1, 10.2, 10.4] Report 10.4
Legal: Third-party rights and covenants over the sites will be addressed through appropriation for planning purposes and use of section 203 of the Housing and Planning Act 2016. Compensation may be payable if valid claims are received. [10.8, 10.9, 10.10] Report 10.8, 10.10
Equalities: The project addresses health inequalities and seeks to improve access to leisure facilities; an Equality Impact Assessment screening tool has been completed and details how the design proposals will have a positive impact on groups with protected characteristics and disadvantaged groups. [10.25, 10.26] Report 10.25, 10.26
Staffing: An internal Project Team is in place using existing establishment roles, a client-side technical construction consultant is required, and an additional full-time G4 position has been costed to manage the new leisure operating contract once the centre is open. [10.22, 10.23, 10.24] Report 10.22, 10.23
Other: Ernst and Young LLP raised a growing concern regarding the council's high level of short-term borrowing and budgeted shortfalls within the MTFS. MHCLG may consider issuing a Best Value Notice if there are concerns over financial sustainability or value for money. [10.20, 10.21] Report 10.20, 10.21
Who and where
Farnborough residents and leisure users Report 9.3, 11.1
Local sports clubs and interest groups including scuba training providers, artistic swimming groups, Rushmoor Royals Swimming Club, BMX and skateboarding representatives, and GKR Karate Report P8
Community and accessibility groups including Henry Tyndale School and the Rushmoor Accessibility Action Group (RAAG) Report P9
National Governing Bodies: Sport England, Swim England, Badminton England, England Netball, England Basketball, England Volleyball Report P10
Owners of third-party rights over the Queensmead and Pinehurst Car Parks sites Report 10.8, 10.10
Timeline
20 June 2025: Dedicated public consultation microsite launched Report 9.4
30 June to 25 July 2025: Public consultation undertaken, comprising three in-person events attended by approximately 350 residents Report 9.3
14 October 2025: Cabinet received Report LEG2505 and delegated handling of third-party rights constraints to the Executive Director Report 10.8
26 February 2026: Council to consider 2026/27 budget and MTFS which includes forecasts for project costs Report 10.15
31 March 2028: Deadline by which the Levelling Up Fund (now Local Regeneration Fund) must be utilised Report 10.12
April 2028: New unitary council anticipated to be in place as part of Local Government Reorganisation Report 10.18
Plain English for the jargon
RIBA Stage 5: Royal Institute of British Architects work stage covering construction and handover
Development Management Agreement: An agreement under which a developer manages the construction phase of a project on behalf of the client
Levelling Up Fund (now Local Regeneration Fund): Government funding awarded to the Council in 2023 to deliver a leisure and cultural hub in Farnborough
MTFS: Medium-Term Financial Strategy, the Council's multi-year financial planning document
LGR: Local Government Reorganisation, the planned creation of a new unitary council from April 2028
Section 203 of the Housing and Planning Act 2016: Legal power allowing the Council to override third-party rights to carry out building and operational works
Best Value Notice: A notice that may be issued by MHCLG under the Local Government Act 1999 to secure compliance with the Best Value Duty
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item72
Resolved
RESOLVED that (a) the progress with the design of the leisure centre and changes made as a result of feedback during the leisure centre operator procurement process, as set out in Report No.REG2601, be noted; (b) the progress of the planning submission for the Farnborough Leisure Centre, as set out in the Report, be noted; (c) subject to planning permission being granted and review of the contractor’s proposals, the Executive Director, in consultation with the Executive Head of Finance, the Interim Monitoring Officer and Corporate Manager – Legal Services and the Healthy Communities & Active Lives Portfolio Holder, be authorised to enter into a ... view the full minutes text for item 72.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
CABINET COUNCILLOR SOPHIE PORTER HEALTHY COMMUNITIES & ACTIVE LIVES PORTFOLIO HOLDER 03 MARCH 2026
KEY DECISION? YES REPORT NO. REG2601
FARNBOROUGH LEISURE CENTRE – CONSTRUCTION CONTRACT AWARD
SUMMARY AND RECOMMENDATIONS:
This report provides an update on the Farnborough Leisure Centre Project and seeks approval to enter into a Development Management Agreement for RIBA stage 5 (Construction and handover) onwards for the delivery of the new leisure centre.
A. It is RECOMMENDED that Cabinet:
1) Notes the progress with the design of the leisure centre and changes made as a result of feedback during the leisure operator procurement process.
2) Notes the progress of the planning submission for the new Farnborough Leisure Centre.
3) Subject to planning permission being granted and review of the contractors proposals that authority be delegated to the Executive Director, in consultation with the Executive Head of Finance (S151 officer), the Interim Monitoring Officer and Corporate Manager Legal Services and Portfolio Holder for Healthy Communities & Active Lives, to enter in a Development Management Agreement with Alliance Leisure Services Ltd as set out in section 6.3 of this report, for the delivery of a new leisure centre and surface car park in Farnborough town centre.
4) Confirm that revenue capacity funding received from MHCLG continue to be utilised against revenue costs associated with the project.
5) Delegates authority to the Executive Head of Finance (S151 officer) to update the Capital Strategy and Treasury Management Strategy in line with the approval of capital budget and funding as above.
6) Authorises the use of the Council’s powers to appropriate the Queensmead Car Park, Farnborough and the site of the previous Pinehurst Car Park, as set out in the plan at Appendix K Farnborough for planning purposes under section 122 of the Local Government Act 1972. 7) Authorises the use of Section 203 of the Housing and Planning Act 2016 to remove any legal constraints to development and delegates authority to the Interim Monitoring Officer and Corporate Manager Legal Services and Section 151 Officer in consultation with the Executive Head of Property and Growth to agree any compensation payable to beneficiaries of rights under section 204 of the Housing and Planning Act 2016 following due diligence of their claim.
8) Notes the decision of the Interim Corporate Manager Legal Services as to protective measures and authorises her, in consultation with the Executive Head of Finance (Section 151 Officer) to negotiate the terms of the protective measures to not exceed £100,000. Cabinet should note the £100,000 does not appear in projected costs below as the outcome of the negotiations is not yet known.
B. That the COUNCIL BE RECOMMENDED to delegate authority to the Executive Head of Finance (S151 officer) to put in place a Capital Budget up to £27.5m for the project to be funded by external funding (Levelling Up Programme), S106 funds and borrowing as set out in section 4.2 of this report.
1. BACKGROUND AND SUMMARY OF DECISIONS
1.1In February 2025, Cabinet (REG2501) approved a revised approach for the delivery of a Leisure Centre in Farnborough town centre along with the procurement approach to appoint an operator to run the existing leisure facilities within the borough and the proposed new leisure centre.
1.2The Ministry of Housing, Communities & Local Government (MHCLG) gave full approval in April 2025 for the Council to deliver the revised scheme utilising the remaining £18.5m Levelling Up grant (now known as the Local Regeneration Fund). At that time the Cabinet noted that the scheme would also require some borrowing that would be funded by operator income payments.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.