RESOLVED that (i) the progress with the design of the leisure centre and the changes made as a result of the preliminary market engagement sessions with operators, as set out in Report No. REG2503, be noted; (ii) the conclusion of RIBA Stage 2 on schedule, the commencement of RIBA Stage 3 and the timetable for the project to the conclusion of RIBA Stage 4, as set out in the Report, be noted; (iii) the extension of the current Access Agreement for RIBA Stage 4, on the conclusion of RIBA Stage 3, subject to the forecasted operator income being in line with expectations, be approved, with costs for RIBA Stage 4 of up to £660,000 to be drawn from the Levelling Up Fund; (iv) the arrangements for the pre planning consultation, as set out in the Report, be noted; (v) the revised operator procurement consultation, as set out in the Report, be noted; and (vi) the setting up of special meetings of the Cabinet and the Council, as required, to enable the concurrent entering into of both the build and operator contracts, be approved.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
CABINET COUNCILLOR SOPHIE PORTER HEALTHY COMMUNITIES & ACTIVE LIVES PORTFOLIO HOLDER 08 JULY 2025
KEY DECISION? YES REPORT NO. REG2503
FARNBOROUGH LEISURE CENTRE – UPDATE & NEXT STEPS
SUMMARY AND RECOMMENDATIONS:
On the 11th February 2025 Cabinet approved report REG2501 to progress with the revised approach for the delivery of a Leisure Centre in Farnborough town centre, utilising the remaining Levelling Up funding. Approval was given to progress design works to the end of RIBA Stage 3 and planning submission, as well as commencement of the Leisure Operator procurement.
This report provides an up-date on progress with the project and operator procurement. It then sets out next steps in delivering the project within the parameters of the Levelling up Fund timescales.
It is recommended that Cabinet:
1) Notes the progress with the design of the leisure centre and changes made as a result of the preliminary market engagement sessions with operators. 2) Notes the conclusion of RIBA stage 2 on schedule, the commencement of RIBA stage 3 and the timetable for the project to the conclusion of RIBA stage 4. 3) Agrees to extend the current Access Agreement for RIBA stage 4, on the conclusion of RIBA stage 3, subject to the forecast operator income being in line with expectations. Costs for RIBA stage 4 of up to £660K to be funded by the Levelling up Fund. 4) Notes the arrangements for the pre planning consultation. 5) Notes the revised operator procurement programme. 6) Agrees to special meetings of Cabinet and Council as required to enable the concurrent entering into of both the build and operator contracts.
1. INTRODUCTION AND BACKGROUND
1.1In January 2025 the Ministry of Housing, Communities & Local Government (MHCLG) confirmed that the Council could continue to progress the revised scheme to the conclusion of RIBA Stage 3, utilising the residual £18.5m Levelling Up grant.
1.2In February 2025, Cabinet (REG2501) approved the revised approach for the delivery of a Leisure Centre in Farnborough town centre along with the procurement approach to appoint an operator to run the new and existing leisure facilities within the borough.
1.3The project will deliver 2 swimming pools (a 25m 6-lane main pool, 10m x 8m learner pool), 100+ station fitness suite including specialist power-assisted equipment for people who are less mobile or active, studio space including a dedicated spin studio, a café and active play for children. The revised scope also incorporates the provision of a new surface car park.
1.4The revised approach set out an alternative site to the immediate south of the existing town centre high street on Queensmead car park, directly adjacent to existing public transport nodes which will help to improve access for the local community.
1.5The purpose of this report is to provide Cabinet with an up-date on the project progress, the operator procurement, and next steps to deliver the project.
2. Project Progress
Design Update
2.1As set out in the February cabinet report, the Council have entered into an Access Agreement with Alliance Leisure Services Limited (Alliance), via the UK Leisure Framework, for the provision of project management, design and professional services required for the completion of RIBA stages 2 & 3.
2.2Alliance have now appointed their full design team to progress design to the end of RIBA Stage 3. The output from this stage is detailed design and all documentation required to support a planning application.
2.3RIBA stage 2 (concept design) is now complete, and the stage 2 report can be found at Exempt Appendix A to this report. The report outlines design progress to date, setting out the site constraints and opportunities to inform the building design that is being developed in RIBA stage 3.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.