CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rushmoor Borough Council
Cabinet, Tuesday 19 October 2021 at 7.00pm

FARNBOROUGH LEISURE CENTRE - DEMOLITION UPDATE AND BUDGET

Noted Executive 1 paper

Cabinet noted this item on Tuesday 19 October 2021. Below is the council's own wording, with the papers it was decided on.

Item39

Resolved

RESOLVED that (i) the update in relation to the revised contract sum and programme for demolition, as set out in Report No. REG2101, be noted; and (ii) the release of a further £204,000 funding from the approved Capital Programme, to increase the demolition project budget to £1,339,000 as a result of the removal of the additional asbestos and other additional costs, as set out in the Report, be approved.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

Summary

This report requests the release of additional funding from the approved capital programme to enable the completion of the demolition of Farnborough Leisure Centre.

Recommendations

Cabinet is recommended to:

1. Note the update in regards to the revised contract sum and programme for demolition.

2. Agree the release of a further £204,000 funding from the approved Capital Programme, to increase the demolition project budget to £1,339,000 (from £1,135,000) as a result of the removal of the additional asbestos and other additional costs as set out in the report.

1. INTRODUCTION

1.1The purpose of this report is to seek approval to release additional funding, from the Capital Programme to enable the demolition and site clearance of Farnborough Leisure Centre, further to intrusive surveys being carried out.

1.2This is a key decision because of the overall level of capital spend required to deliver the works.

Background

2.1In June 2021, Cabinet approved funding and the appointment of contractors Willmott Dixon Construction Limited to enable the Council to proceed with the demolition of the vacant Farnborough Leisure Centre building.

2.2Vacant possession of the building was handed to Willmott Dixon (WD) on the 12th July 2021. The relevant notices have been served, intrusive demolition and asbestos surveys have been carried out and soft strip and full hoarding of the site are underway. These works have been carried out to date under a letter of intent to allow an early mobilisation and to gain more certainty over asbestos and utility disconnection risks before committing to a full contract.

3. Outcome from Survey work and Impact on Contract Sum and Project budget

3.1Following the intrusive demolition asbestos survey Willmott Dixon have now submitted their costs for the removal of the additional asbestos and subsequent programme implications. These figures have been interrogated by our Technical Advisor and Cost Consultants, Artelia UK, who have recommended acceptance of the final revised contract sum (see Exempt Appendix 1).

Asbestos

3.2Significant additional asbestos has been found following the Refurbishment and Demolition (R and D) Survey over that included in the original project estimate.

3.3Whilst the survey was extensive the surveyor was unable to get access to some remaining areas. Therefore there is a risk of further asbestos discovery. An allowance has therefore been made for this within a revised contract sum for these works.

3.4Given the extent of the asbestos discovered a longer period will be needed for this work than previously programmed which incurs additional costs over and above that of the asbestos removal and disposal.

Utilities

3.5The Council are in the process of progressing the utilities disconnections required to demolish the site in tandem with the work described in 2.2 above. The initial applications were made to the energy providers in late April/early May 2021. Despite these early requests getting commitment to dates for the works has proven difficult and continues to impact on the programme.

Programme

3.6The revised programme shows completion by April 2022 with main demolition completed by the end of January. The demolition will be phased commencing with the swimming pool side of the facility first followed by the dry side in the new year.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FARNBOROUGH LEISURE CENTRE: DEMOLITION UPDATE AND BUDGETReport 127 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
DC
Councillor David CliffordChairman, present
KM
Councillor Ken MuschampVice-Chair, present
MM
Councillor Marina MunroCommittee Member, present
AN
Councillor Adrian NewellCommittee Member, present
MS
Councillor Maurice SheehanCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantCommittee Member, present

On this subject at Rushmoor

Search all
  1. FARNBOROUGH LEISURE CENTRE - DEMOLITION UPDATE AND BUDGETThis decision
  2. Proposed New Farnborough Leisure Centre, Queensmead Car Park, Kingsmead, Farnborough - Application No. 25/00583/FULPPAgreed
  3. Farnborough leisure centre - construction contract awardNoted
  4. Farnborough leisure centre - update and next stepsNoted
  5. Farnborough leisure centre - next stepsApproved
  6. Farnborough regeneration and leisure and cultural hub - next stepsNoted

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies