CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rushmoor Borough Council
Cabinet, Tuesday 3 October 2023 at 7.00pm

FARNBOROUGH LEISURE AND CULTURAL HUB – NEXT STEPS

Approved Executive 5 papers

Cabinet approved this item on Tuesday 3 October 2023. Below is the council's own wording, with the papers it was decided on.

Item28

Resolved

RESOLVED that (i) the scope of the Leisure and Cultural Hub project, as set out in Report No. REG2307, as amended at the meeting, be approved as follows; (a) Leisure and Cultural Hub to include: - Leisure Centre with the revised facilities mix, as set out in paragraph 3.12 of the Report - Shared café/bar with space for performance - Library and associated community space - Cultural space including art gallery, digital lab, collaboration space and studios - Customer access to Council and voluntary sector services - Council Offices - Meeting rooms (b) Mobility Hub (circa 350 spaces) (c) Skate park (d) Play area; (ii) the progression of design development to RIBA Stage 3, planning submission and associated costs of up to £1,050 million, as set out in the Report, as amended at the meeting, be approved; (iii) the decision on the approach to sustainability for the building would be based on return-on-investment modelling and would be considered by the Cabinet at its meeting on 17th October, 2023; (iv) the project timetable, decision getaways and dependencies, as set out in the Report, be noted; (v) the intended land assembly process, as set out in the Confidential Appendix 1 of the Report, be approved; (vi) the estimated project budget and current funding strategy, as set out in the Report, be noted; (vii) the overall operator procurement and appointment approach, as set out in the Report, be approved; (viii) the immediate commencement of the operator procurement process, in accordance with the draft contract specification and conditions ... view the full minutes text for item 28.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

CABINET 3rd October COUNCILLOR MARTIN TENNANT 2023 MAJOR PROJECTS AND PROPERTY

REPORT NO REG2307 KEY DECISION? YES

FARNBOROUGH LEISURE AND CULTURAL HUB – NEXT STEPS

SUMMARY AND RECOMMENDATIONS:

In January 2023 the Government announced that the Council’s bid for £20m Levelling Up funding to support the delivery of a Leisure and Cultural Hub in Farnborough had been successful. In March 2023 Cabinet considered a report (REG2303) which identified the next steps in the project, authorised allocation of funding to enable work to commence and confirmed that Council should enter into a Memorandum of Understanding with Government to enable the drawdown of funding. The report also provided budget to enable the project to procure a Leisure Operator to commence.

This report provides an update on the current position with the Leisure and Cultural Hub project and work undertaken on the design development. It proposes the final project scope, seeks confirmation of the schedule of accommodation to be included in the design and asks for permission to submit the required planning application(s). This report also confirms that officers will commence negotiation regarding the sale of Council owned land and termination of associated leases to enable the construction of a mobility hub.

This report also sets out the approach and timing for the Leisure Operator procurement to ensure that the new operator can input into the final design of the facility.

Finally, this report identifies the budget required to complete the pre-construction phases of the project and sets out the associated funding strategy and risks.

It is recommended that Cabinet:

1) Approves the scope of the project as follows: a. Leisure and Cultural Hub to include: • Leisure Centre with the revised facilities mix as set out in paragraph 3.12 • Shared café/bar • Library and associated community space • Cultural space including art gallery, digital lab, collaboration space and studios • Customer access to council and voluntary sector services • Council Offices • Meeting rooms b. Mobility Hub (circa 350 spaces) c. Skate park d. Play area 2) Agrees to progress design development to RIBA Stage 3, planning submission and associated costs of circa £1,050m. 3) Delegate to the Executive Director in consultation with the Portfolio Holder for Major Projects and Property and the Project Board as required to agree the approach to finalise the sustainability and design based on Return-on- Investment modelling. 4) Notes the project timetable, decision gateways and dependencies as set out in the report. 5) Agrees the intended land assembly process as set out in confidential Appendix 1. 6) Notes the estimated project budget and current funding strategy. 7) Agrees the overall operator procurement and appointment approach as outlined in this report. 8) Confirms the immediate commencement of the operator procurement process in accordance with the draft contract specification and conditions outlined in appendices 2 & 3. 9) Delegates any decision to amend the procurement documentation as required throughout the process to the Executive Head of Operations in consultation with the Portfolio Holder for Operational Services 10) Agrees a further extension of the existing contract with Places Leisure to operate the Aldershot Pools & Lido by up to 12 months, whilst the leisure operator procurement process is undertaken.

1. INTRODUCTION

1.1The purpose of this report is to seek Cabinet approval to progress detailed design (to RIBA Stage 3 and planning submission) for the Leisure & Cultural Hub including Council office accommodation alongside the associated facilities including Mobility Hub, Play Area and Skate Park.

1.2The indicative project cost is £68 million including all elements of the scheme. This is the funding envelope that the project team will seek to achieve during design development.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Operator Procurement Draft SpecificationAppendix 2 1.9 MB Download
PDF
Operator Procurement Contract ConditionsAppendix 3 2.1 MB Download
PDF
Stage 0 and 1 ReportAppendix 4 5.6 MB Download
PDF
RIBA 2 Design Update and SoAAppendix 5 11 MB Download
PDF
FARNBOROUGH LEISURE AND CULTURAL HUB: NEXT STEPSReport 891 KB DownloadRead as text

At this meeting

Whole meeting
27MINUTESOn the agenda
28FARNBOROUGH LEISURE AND CULTURAL HUB – NEXT STEPSThis decision

Who was there

6 of 7 attended
JC
Councillor Jonathan CantyCommittee Member, present
SC
Councillor Sue CarterCommittee Member, present
DC
Councillor David CliffordChairman, present
GL
Councillor Gareth LyonCommittee Member, apologies
MS
Councillor Maurice SheehanVice-Chair, present
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantVice-Chair, present

On this subject at Rushmoor

Search all
  1. FARNBOROUGH LEISURE AND CULTURAL HUB – NEXT STEPSThis decision
  2. Proposed New Farnborough Leisure Centre, Queensmead Car Park, Kingsmead, Farnborough - Application No. 25/00583/FULPPAgreed
  3. Farnborough leisure centre - construction contract awardNoted
  4. Farnborough leisure centre - update and next stepsNoted
  5. Farnborough leisure centre - next stepsApproved
  6. Farnborough regeneration and leisure and cultural hub - next stepsNoted

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open