RESOLVED that (i) the proposed approach to design development pursuing full PassiveHaus accreditation, with the associated capital investment of £8,164,000, as set out in Report No. REG2308, be approved; (ii) the final decision to proceed with the implementation of the resulting design being subject to the overall affordability assessment, to be considered in June, 2024, be approved; and (iii) the additional costs for abortive fees and redesign, estimated at £880,000 (excluding VAT) and the delays to the programme, estimated at 10-12 weeks, should a decision be taken not to proceed with the full PassivHaus design later in the project, be noted.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
CABINET 17th October COUNCILLOR MARTIN TENNANT 2023 MAJOR PROJECTS AND PROPERTY
REPORT NO REG2308 KEY DECISION? YES
FARNBOROUGH LEISURE AND CULTURAL HUB – APPROACH TO SUSTAINABILITY
SUMMARY AND RECOMMENDATIONS:
On the 3rd of October Cabinet approved report REG2307 to progress the delivery of RIBA Stage 3 design and planning submission for the Leisure, Cultural and Council Hub as well as commencement of Leisure Operator procurement. At that meeting it was noted that Cabinet would consider a further report at this meeting to agree the approach to sustainability and investment in PassivHaus based on a detailed piece of work undertaken by the Council’s architects (GT3) and cost consultants (Artelia) to look at the return on investment.
This report provides an overview of the options considered with a detailed report from GT3 attached at Appendix A.
It is RECOMMENDED that Cabinet:
1) Approves the proposed approach to design development pursuing full PassivHaus accreditation with the associated capital investment of £8,164,000. 2) Confirms that the final decision to proceed with the implementation of the resulting design will be subject to the overall affordability assessment to be considered in June 2024. 3) Notes that should a decision be taken not to proceed with the full PassivHaus design later in the project, there will be additional costs for abortive fees and redesign estimated at £880,000 (excl VAT) and delays to the programme estimated at 10-12 weeks.
1. INTRODUCTION AND BACKGROUND
1.1The purpose of this report is to seek a Cabinet decision on the approach to sustainability and design for the Leisure, Cultural and Council Hub scheme.
1.2In June 2019, the Council declared a climate emergency with the motion unanimously passed by Council. This included the target for the Council to be carbon neutral by 2030. In July 2023, the Cabinet agreed an Action Plan which provided targeted actions to reduce the Council’s carbon footprint (ACE2306).
1.3One of the agreed actions in the plan is “to review processes for the Council’s capital programme so that environmental impacts are incorporated into business case development and whole life cycle carbon assessments are undertaken”. The Leisure, Cultural and Council Hub once developed will be part of the Council’s operational carbon footprint and therefore there is a need to ensure that the building is designed with the Council’s climate change objectives in mind.
1.4The Levelling Up bid outlined the Council’s aspiration to deliver a net zero carbon facility and, since confirmation of the successful bid, work has been undertaken to understand what this means in more detail. An allowance for sustainability has always been included in the cost plan throughout the feasibility stages of the project.
1.5An initial sustainability workshop with a cross party group of Members took place on the 18th of July to explore the development of a sustainability framework and aspirations for the project. This resulted in a clear steer from Members that they were keen to pursue a facility that was carbon efficient in operation and construction and were keen to understand more about PassivHaus and costs for delivery.
1.6A follow-up workshop took place on 2nd August to explore PassivHaus principles and benefits in more detail. As a result, Members requested that the project team look at the application of PassivHaus principles during RIBA Stage 2 and undertake detailed work on the Return-on-Investment (RoI) to inform a decision regarding the preferred route.
1.7This work has now been completed and has assessed three possible approaches to delivering a sustainable building and specifically focusing on the reduction in operational carbon over the life of the building. A detailed report which has been used to inform this paper is included at Appendix A.
2. Delivering Net Zero
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.