Resolved
That the progress that each of the projects within the programme was making and the mitigations that were being put in place to address the issues within each work stream be noted.
Audit Committee noted this item on Thursday 28 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the progress that each of the projects within the programme was making and the mitigations that were being put in place to address the issues within each work stream be noted.
This report will provide updates on the following:
1.1Digital Transformation Programme 1.1.1 Social Care Project 1.1.2 Infrastructure and Architecture Project 1.1.3 Business Transformation Project 1.1.4 Customer Experience Project
2.1The recommendations are that:
2.1.1 The Committee notes the progress that each of the projects within the programme is making and the mitigations that are being put in place to address the issues within each work stream.
3.0Update Summary
3.1Social Care Project -The overall project status remains at red for this period for the following reasons.
3.2The Adults work stream has been re-planned but there are still red risks around data testing and reporting.
3.3The Children’s work stream continues at red overall due to the quantity of forms to be built and other configuration items outstanding. Further pressure has been put on this work stream as the Children’s form designer has left the project at short notice. However, the Children’s implementation manager has started now and is reviewing the current build. We are mitigating the risks with additional resources being assigned to assist with the forms build in particular and recruitment of a replacement resource is underway. Audit Committee, 1st March 2018, IT Update
3.3The Infrastructure and Architecture Project – This continues to underpin both the business as usual activities (BAU) of the ICT function and all other major projects in the overall digital programme.
3.4The Wi-Fi roll out for Shirehall is complete, meaning that we can turn off the old system and start to realise savings. The planned roll out to other sites continues.
3.5The data migration hub is working well. It should be available for the next cut of ERP data in Data Migration 3. (The hub automates the upload of the data and identifies gaps or missing data from the cut)
3.6Business engagement around applications and legacy systems is largely complete. An analysis of findings is underway but the process has already identified opportunities in a number of systems that can be consolidated on to the new platforms or can be decommissioned.
3.7Customer Experience Project – The contact centre software is now being used by a range of Council Services.
3.8The email response system is currently being configured and Web chat facility proof of concept is at final round of testing.
3.9Auto-pause facility on the telephone, which is required for PCI compliance, is in place in the contact centre.
3.10In the CRM the complaints process and account manager functionality are in test and scheduled for go live in Aug/Sept
3.11The work with Hitachi and the Portal software developer is on schedule for My Shropshire Portal to go live in November.
3.12ERP- Communications around the ERP and the impact assessments are going well, with lunch and learn sessions for staff and manager training sessions being held, the management training sessions were fully booked.
3.13The ability to resource the project remains an issue and has made it necessary to delay slightly the planned go live date for ERP until 31st October 2018. This will not impact the go live dates for Social Care.
3.14Bringing in resource remains problematic, to mitigate the issues this creates we are looking at what activities can be stopped temporarily or changed to free resources for the project. We are looking to move resources from other areas to cover. In addition as we have exhausted the agencies as a means bringing in staff we have advertised for university/college students to come and work with us over the summer.
4.0Budget
4.1The projected spend on the programme remains within budget.
2 Audit Committee, 1st March 2018, IT Update
5.0Governance and Audit
5.1The design phase of each of the projects within the programme have been audited
5.1.1 Customer Experience – Reasonable 5.1.2 Social Care – Reasonable 5.1.3 ERP – Good
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
First line assurance: Digital Transformation UpdateReport | 96 KB | DownloadRead as text |
Follow Audit Committee at Shropshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2025 | Minutes of the previous meeting held on the 26 June 2025That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman. | Approved | Open |
| 16 Jul 2025 | Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... | Approved | Open |
| 16 Jul 2025 | Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. | Noted | Open |
| 16 Jul 2025 | Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... | Agreed | Open |
| 16 Jul 2025 | Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.