A. That the progress that had been made to address the recommendations in the 21st April 2017 Audit Report to ensure that all improvements were effectively implemented and monitored via the action plan for estate management be noted. B. That the desktop review undertaken by internal audit in March, which acknowledged the comprehensive interim response and Project Plan and the extension of the implementation date to the end of September 2018, due to the size and complexity of the project be noted. C. To note that the improvements and implementation of the action plan associated with the audit were being progressed in line with continued implementation of the corporate landlord model and the changes required to reflect the overall change in direction of the Council in respect of its planned future new asset management strategy. D. That an update be provided to the November Audit Committee meeting.
Word for word from the decision Shropshire published for this meeting.Source: www.shropshire.gov.uk
REVIEW OF IMPLEMENTED AUDIT RECOMMENDATIONS – JUNE 2018
Rec Rec Recommendation Rec Rating Management Response Lead Date to be Action Ref. No. Officer Actioned 2.1 1 The filing system in respect Significant Yes The current filing arrangement is not Steve Sept 18 The local filing of leases information and a functioning document Law system has been correspondence should be management system and its reviewed and reviewed to enable inadequacies are acknowledged. improvements documentation and We will therefore be seeking made. correspondence to be guidance on the implementation of a As part of the IT retrieved on a timely basis fully functioning system as part of Digital on request. the IT & Digital Transformation Transformation Programme. Programme we will be adopting Sharepoint as the Council’s preferred document management system.
It should be ensured that In the meantime, a Key Documents Mark July 17 Implemented May the correspondence filed on file/folder is to be set up on the Salt 17 Officer's Microsoft Outlook current filing system and TF archives is saved to the containing the CV report, CV memo, shared network drive on a copy of legal document, Finance timely basis to ensure that it Credit Check Request Form & is readily retrievable. periodic income request form A file note system will also be The filing of correspondence implemented to provide a summary and documentation on the of actions taken.
Page 1 Rec Rec Recommendation Rec Rating Management Response Lead Date to be Action Ref. No. Officer Actioned 'Technology Forge' system Officers will be reminded to save should be progressed as is emails and other practical. correspondence/documents to the filing system.
Please note that TF is not a document management system and routine correspondence will not be filed on it, however, it will contain key documents. 2.2 2 It should be ensured that a Requires Partia A finance credit check is carried out Mark July 2017 Implemented July finance or credit check is Attention lly by the Debt Recovery Team for all Salt/Pau 2017 carried out and evidence is industrial unit lettings and a report is l Hesp retained of the check on all produced containing a summary of prospective tenants before a their findings. A copy of this report is lease is agreed. A formal saved on the filing system but it is process should be accepted that this isn’t always easy introduced in respect of the to find and it will be stored in the key checks carried out by the documents folder in future. Debt Recovery Team which should include a report Credit checks on other lettings are containing an analysis of the usually carried out by the letting information in the credit agent. Where this is done copies of report and a credit checks will be obtained and recommendation to the filed in the filing system. Corporate Landlord Team.
2.33 Consideration should be Requires Yes The Debt Recovery Team use a Mark August Implemented given to establishing a Attention company called Creditsafe to Salt/Pau 2017 July17 checklist or task schedule to undertake commercial credit l Hesp
Page 2 Rec Rec Recommendation Rec Rating Management Response Lead Date to be Action Ref. No. Officer Actioned ensure that appropriate checks. checks are carried out on prospective tenants to In consultation with the Debt assess their credit status. It Recovery Team consideration will is anticipated that the be given to the implementation of a checks would at least formal credit check proforma include obtaining credit rating reports, details of business rates arrears, business plans, references from previous landlords etc.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.