First Line Assurance: Children's Direct Payments Update

Noted Finance 1 paper

Audit Committee noted this item on Tuesday 25 February 2020. Below is the council's own wording, with the papers it was decided on.

Item70

Resolved

a) That Committee members note the review that took place on 15th January 2020 in relation to the recommendations made from the audit. b) That Committee Members note the progress that has been made to address the recommendations since the last report to Cabinet.
Word for word from the decision Shropshire published for this meeting. Source: www.shropshire.gov.uk

Follow this further

Built from Shropshire's papers

What the report saysPro

Report to Audit Committee

Summary

1.1As part of the approved internal audit plan for 2018 / 19 Audit Services undertook a review of Direct payments Children. The audit work was undertaken to give assurance on the extent to which management control objectives were being achieved. The final report and its findings were issued in March 2019 and from the findings an audit action plan was devised.

1.2The managers for the Disabled Children Team have continued to address the recommendations that they are responsible for and have previously reported back to Cabinet on progress.

1.3It has been six months since the last review and update report to Cabinet, primarily, due to Steve Ladd Service Manager for the Disabled Children’s Team being long-term sick since September 2019. An interim Service Manager [name removed] has been appointed and has conducted the most recent review alongside the Team Manager and Short Breaks Reviewing Officer which took place on 15th January 2020.

1.4The attached action plan (Appendix 2) demonstrates the progress that has been made. Seven of the nine significant recommendations have been evaluated as having been sufficiently attended to and rated green following the most recent management review. Five of the eight requires attention recommendations have been evaluated as having been sufficiently attended to and rated green. Five actions remain outstanding.

Recommendations

2.1That Committee members note the review that took place on 15th January 2020 in relation to the recommendations made from the audit.

2.2That Committee members note the progress that has been made to address the recommendations since the last report to Cabinet. 25 February 2020 Audit Committee: Children’s Direct Payments Update

REPORT

3. Risk Assessment and Opportunities Appraisal

(NB This will include the following: Impact on Children and Vulnerable Adults, Risk Management, Human Rights, Equalities, Community and other Consultation)

3.1It was noted in the last review report that the appointment of the Short Breaks Reviewing Officer in December 2018 had strengthened system controls. Unfortunately, the position became vacant in January 2020 with the departure of the postholder, however, in recognition of the need for this vital role, recruitment is in progress and interviews for a replacement are scheduled for 14th February 2020.

3.2To ensure that we do not disadvantage children and families by develop a backlog of direct payment requests and short break reviews during this period of recruitment, we have agreement from the Senior Business Support and Finance Manager that she will lead on dealing with the financial aspects of direct payments and have appointed a Social Worker in the Disabled Children’s Team to take responsibility for undertaking short break reviews.

3.3The Team Managers Matrix has now been developed and has been up and running since July 2019. The Matrix provides live data on: -

1. The number of children accessing short breaks 2. The timeliness of short break reviews 3. The timeliness of visits and plans.

3.4Discussions between Children’s Social Care and Adult Social Care stalled in September 2020, however, these have now resumed, and [name removed] is in process of writing a business case to support children’s involvement in the adult and children’s all age payment service.

3.5The strategic board continues to meet bi monthly to oversee the development and implementation of the all age payment service and each sub group is making progress in moving it forward. There has been progress in: -

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
First Line Assurance: Children's Direct Payments UpdateReport 240 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
CP
Ceri PilawskiOfficer, present
PA
Peter AdamsChairman, present
IJ
Ioan JonesCommittee Member, present
CM
Chris MellingsCommittee Member, present
BW
Brian WilliamsVice Chairman, present
MW
Michael WoodCommittee Member, present
KW
Katie WilliamsOfficer, present
RP
Richard PercivalPublic, apologies
MW
Mary WrenPublic, apologies

On this subject at Shropshire

Search all
  1. First Line Assurance: Children's Direct Payments UpdateThis decision
  2. First line assurance: Project Management Office Management UpdateNoted
  3. First line assurance: Adult Social Care Outturn Management UpdateAgreed
  4. First line assurance: Internal Control Management UpdateNoted
  5. First Line Assurance: ASC Outturn Update (Period 13)Noted
  6. First line assurance: The Lantern Management UpdateNoted

More from Shropshire Audit Committee

All decisions
MeetingDecisionOutcome
16 Jul 2025 Minutes of the previous meeting held on the 26 June 2025That the minutes of the meeting held on 26 June 2025 be approved as a true record and signed by the Chairman. Approved Open
16 Jul 2025 Third line assurance: Internal Audit Plan 2025/26That the Committee considered and endorsed, with appropriate comment, the approach taken to create the proposed Inter... Approved Open
16 Jul 2025 Third line assurance: Pension Fund Audit Plan 2024/25That the contents of the report be noted. Noted Open
16 Jul 2025 Third line assurance: Annual review of Internal Audit, Quality Assurance and Improvement Programme (QAIP) 2024/25That the Committee considered and endorsed with appropriate comment, the conclusion that the Council employs an effec... Agreed Open
16 Jul 2025 Second line assurance: Annual Whistleblowing reportThat the contents of the report were considered and approved. Approved Open