Thames Valley Berkshire Local Growth Deal 2015/16 to 2010/21

Decided Committee 1 paper

Berkshire Local Transport Body decided this item on Thursday 20 November 2014. Below is the council's own wording, with the papers it was decided on.

Item22

Resolved

Resolved – That the BLTB support the request from TVB LEP to government to sanction changes to the programme to allow: (a) Project starts in 2015-16 for 2.10 Slough: A332 improvements and for 2.17 Slough: A355 route. (b) Project delays to start in 2016-17 for 2.01 Newbury: Kings Road Link Road and 2.06 Reading: Green Park Railway Station.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Berkshire Local Transport Body

Purpose of report

1. To report on the overall progress of the Thames Valley Berkshire Local Growth Deal1, with particular reference to the schemes included in the Transport Packages of the Strategic Economic Plan2. The headline figure for Transport Schemes is £94.60m, of which £11.1m is new approval to spend in 2015-16; £14.5m is previously approved; and £69.00m is indicative approval for five future years 2016/17 – 2020/21.

2. The terms of the TVB Local Growth Deal stipulate that permission must be sought to switch approved schemes between different sections. It has become necessary to seek such permission in order to ensure we achieve maximum spend in 2015-16.

3. Elsewhere on this agenda there are detailed reports from the schemes concerned: that information is not repeated in this report, which concentrates on the financial implications of the proposed switch of scheme categorisation.

Recommendation

4. You are recommended to support the request from the LEP to government to sanction changes to the programme which will allow:

4.1project starts in 2015-16 for 2.10 Slough: A332 improvements and for 2.17 Slough: A355 route 4.2. project delays to start in 2016-17 for 2.01 Newbury: Kings Road Link Road and 2.06 Reading: Green Park Railway Station

Other Implications

Financial

5. Since your last meeting the proposers of two schemes identified as ready to start construction in 2015-16 have indicated that they will not now be ready to start construction until 2016-17. They are:

1 https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/327587/35_Thames_Valley_ Berkshire_Growth_Deal.pdf 2 The TVB Strategic Economic Plan is available from thamesvalleyberkshire.co.uk/Strategic_Economic_Plan

Item 10 BLTB 20 November - Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21 Table 1: Schemes Seeking a Delay of 1 Year

Proposed Original Funding Original Spending Proposed Funding Source profile Spending profile Source 2.01 Newbury 2015-16: £1.34m Indicative 2016-17: £1.00m Pre-allocated Kings Road Link Approval in BLTB funds 2016-17: £1.00m 2017-18: £1.34m Road Future Years 2015-16: £2.285m 2.06 Reading Indicative 2016-17: £3.20m Pre-allocated Green Park 2016-17: £2.625m Approval in BLTB funds 2017-18: £3.20m Railway Station Future Years 2017-18: £1.49m

6. Two schemes in Slough, originally identified in the SEP for 2015-16 starts, were given Local Growth Deal approval, but for starts in 2016-17 or later. These are ready to start construction in 2015-16 and are recommended to you as suitable for bringing forward in 2015-16. The TVB Local Growth Deal identifies funding for these two schemes in the “Indicative Approval in Future Years” block.

Table 2: Schemes Seeking to be Advanced by 1 Year

Proposed Proposed Original Funding Original Spending Funding Spending Source profile Source profile

2.10Slough A332 Indicative Approval 2016-17: Pre-allocated 2015-16: £1.35m Improvements in Future Years £2.70m BLTB funds 2016-17: £1.35m

2.17Slough A355 Indicative Approval 2016-17: Pre-allocated 2015-16: £2.28m Route in Future Years £4.40m BLTB funds 2016-17: £2.12m

7. In order to ensure that the proposed swap has a neutral impact on the overall programme, a balancing transfer of £1.64m of previously unallocated BLTB funds is necessary.

Table 3: Impact of Proposed Changes on Pre-allocated BLTB funds

Before £m After £m 2.01 Newbury: Kings Road Link Road 2.34 2.10 Slough: A332 Improvements 2.70 2.06 Reading: Green Park Railway Station 6.40 2.17 Slough: A355 route 4.40 Transfer of funds from “pre- - - 1.64 allocated” to “post-2016” 2.xx Unallocated 5.76 2.xx Unallocated 5.76 14.50 14.50

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Thames Valley Berkshire Local Growth Deal 2015/16 to 2010/21Report 112 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
PB
Councillor Pamela BaleCommittee Member, apologies, sent representative
MB
Cllr Marc Brunel-WalkerCommittee Member, present
GH
Cllr Geoffrey HillCommittee Member, present
SM
Councillor Sohail MunawarCommittee Member, present
TP
Councillor Tony PageCommittee Member, present
JK
Councillor John KaiserCommittee Member, absent
SC
Steve Capel-DaviesCommittee Member, present
CE
Charles EalesCommittee Member, present
IF
Ian FrostCommittee Member, present
PH
Peter HoweCommittee Member, present
GS
Graeme SteerCommittee Member, apologies
MT
Matthew TaylorCommittee Member, present

All 13 on the meeting page

On this subject at Slough

Search all
  1. Thames Valley Berkshire Local Growth Deal 2015/16 to 2010/21This decision
  2. Section 75 Agreement with the NHS Thames Valley Integrated Care Board to govern the delivery of the Better Care Fund 2026-2027Decided
  3. Thames Valley Spatial Development Strategy (SDS) Development and GovernanceDecided
  4. Thames Valley Devolution - Expression of InterestDecided
  5. Report from the Thames Valley Police and Crime CommissionerNoted
  6. Thames Valley Berkshire Capital Programme UpdateNoted

More from Slough Berkshire Local Transport Body

All decisions
MeetingDecisionOutcome
9 Nov 2023 Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. Approved Open
9 Nov 2023 Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... Noted Open
9 Nov 2023 One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... Noted Open
9 Nov 2023 Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... Agreed Open
13 Jul 2023 Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies