Berkshire Local Transport Body, Thursday 20 November 2014 at 4.00pm

Financial Approval 2.01 Newbury: Kings Road Link Road

Approved Committee 2 papers

Berkshire Local Transport Body approved this item on Thursday 20 November 2014. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

Resolved – (a) That scheme 2.01 Newbury: Kings Road Link Road be given conditional financial approval in the sum of £2,340,000 over two years (2016/17 and 2017/18) on the terms of the funding agreement set out at paragraph 13 step 5 of the report, subject to; (b) Written confirmation from WYG, the Independent Assessor, that all aspects of the DfT’s current requirements for a full business case for a scheme of this size have been met. (Councillor Hill joined the meeting)
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Berkshire Local Transport Body

Purpose of report

1. To consider giving financial approval to scheme 2.01 Newbury: Kings Road Link Road.

2. The scheme proposes a new direct link between the Hambridge Road industrial area and the A339 in Newbury to support housing delivery (both on site and with a new link to the Newbury Racecourse Strategic Development Location) and significantly improve access to a key employment area.

3. The scheme will also provide for the remediation of contaminated land on the former Sterling Cables site.

Recommendation

4. You are recommended to give scheme 2.01 Newbury: Kings Road Link Road full financial approval in the sum of £2,340,000 over two years (2016/17 and 2017/18) on the terms of the funding agreement set out at paragraph 13 step 5 below, subject to

5. Written confirmation from WYG, the Independent Assessor, that all aspects of the DfT’s current requirements for a full business case for a scheme of this size have been met.

Other Implications

Financial

6. Scheme 2.01 Newbury: Kings Road Link Road is one of the named schemes in the Error! Hyperlink reference not valid.i announced on 7 July 2014. It was one of two schemes identified for funding from the “pre-allocated Local Transport Body” funding in 2015/16. However, the timing of the scheme has been re- profiled to start in 2016/17. There is a report elsewhere on the LTB agenda seeking DfT permission to swap the funding status with a scheme from the Local Growth Deal approved list of schemes.

7. This report recommends that West Berkshire Council be authorised to draw down the capital sum £2,340,000 from the Local Transport Body funding for this scheme once WYG have certified that the final conditions have been met.

Item 3 BLTB 20 November 2014 Financial Approval 2.01 Newbury: Kings Road Link Road 8. The funding agreement set out at paragraph 13 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.

Risk management

9. The risk management arrangements already put in place by the Local Transport Body are as follows: • The Assurance Frameworkii has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes • White Young Green (WYG) have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme • The funding agreement set out at paragraph 14, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.

Human Rights Act and Other Legal Implications

10. The scheme promoter is a local authority and they have to act within the law. Slough Borough Council will provide legal support for the BLTB, should any questions arise.

Supporting Information

11. The independent assessment process has identified a number of detailed issues that the scheme promoter has been unable to resolve to the satisfaction of WYG at this point in time. These are set out in detail in Appendix 1 (the WYG report). However, it is the opinion of independent assessor that these technical shortcomings are not sufficiently serious to undermine the overall conclusion that this scheme represents good value for money. The independent assessor has indicated that a conditional approval would be appropriate in this case.

12. The full details of the scheme are available from the West Berkshire Council websiteiii. A summary of the key points is given below:

Date Milestone November 2014 Planning permission February 2016 Detailed design complete March/April 2016 Procurement May 2016 Start on site November 2017 Completion of construction

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2.01 Newbury Kings Road Link Road Appendix 1Appendix 370 KB Download
PDF
Financial Approval 2.01 Newbury: Kings Road Link RoadReport 139 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 13 attended
PB
Councillor Pamela BaleCommittee Member, apologies, sent representative
MB
Cllr Marc Brunel-WalkerCommittee Member, present
GH
Cllr Geoffrey HillCommittee Member, present
SM
Councillor Sohail MunawarCommittee Member, present
TP
Councillor Tony PageCommittee Member, present
JK
Councillor John KaiserCommittee Member, absent
SC
Steve Capel-DaviesCommittee Member, present
CE
Charles EalesCommittee Member, present
IF
Ian FrostCommittee Member, present
PH
Peter HoweCommittee Member, present
GS
Graeme SteerCommittee Member, apologies
MT
Matthew TaylorCommittee Member, present

All 13 on the meeting page

On this subject at Slough

Search all
  1. Financial Approval 2.01 Newbury: Kings Road Link RoadThis decision
  2. Financial Approval: Scheme 2.37 Bracknell A322/A329 Corridor Improvements: Birch Hill Junction UpgradeApproved
  3. Financial Approval 2.47 Bracknell: Town Centre - "The Deck"Approved
  4. Financial approval GBF1 Slough: Langley High Street Widening Phase 3Approved
  5. Financial approval: Scheme 2.45 Langley High Street Widening Phase 2Approved
  6. Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban RealmApproved

More from Slough Berkshire Local Transport Body

All decisions
MeetingDecisionOutcome
9 Nov 2023 Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. Approved Open
9 Nov 2023 Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... Noted Open
9 Nov 2023 One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... Noted Open
9 Nov 2023 Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... Agreed Open
13 Jul 2023 Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies