Resolved
Resolved – That scheme 2.17 Slough: A355 route be given full financial approval in the sum of £4,400,000 over two years (2015/16 and 2016/17) on the terms of the funding agreement set out at paragraph 10 step 5 of the report.
Berkshire Local Transport Body approved this item on Thursday 20 November 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – That scheme 2.17 Slough: A355 route be given full financial approval in the sum of £4,400,000 over two years (2015/16 and 2016/17) on the terms of the funding agreement set out at paragraph 10 step 5 of the report.
1. To consider giving financial approval to scheme 2.17 Slough: A355 route.
2. This is a scheme to improve traffic flow on the strategic north-south A355 route between the M4, Slough Trading Estate and the M40 and enhancing access to Slough town centre.
3. You are recommended to give scheme 2.17 Slough: A355 route full financial approval in the sum of £4,400,000 over two years (2015/16 and 2016/17) with the terms of the funding agreement set out at paragraph 10 step 5 below.
Other Implications
Financial
4. 2.17 Slough: A355 route is one of the named schemes that received indicative approval for spending in 2016/17 in the Thames Valley Berkshire Local Growth Deali announced on 7 July 2014. This was despite the original bid being for a 2015/16 start. The scheme promoter has continued to develop the scheme, and an opportunity has arisen to advance the start date following the rescheduling of another scheme in the programme.
5. There is a report elsewhere on the LTB agenda supporting an LEP request for government permission to swap the funding status with a scheme identified for funding from the “pre-allocated Local Transport Body” pot in 2015/16.
6. This report recommends that Slough Borough Council be authorised to draw down the capital sum, £4,400,000 from the “pre-allocated Local Transport Body Funding”.
7. The funding agreement set out at paragraph 10 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.
Item 8 BLTB 20 November 2014 Financial Approval 2.17 Slough: A355 route Risk Management
8. The risk management arrangements already put in place by the Local Transport Body are as follows: • The Assurance Frameworkii has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes • White Young Green (WYG) have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme • The funding agreement set out at paragraph 10, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.
Human Rights Act and Other Legal Implications
9. The scheme promoter is a local authority and they have to act within the law. Slough Borough Council will provide legal support for the BLTB, should any questions arise.
Supporting Information
10. The table below sets out the details of this scheme’s compliance with steps1-5 of paragraph 14 of the full Assurance Frameworkiii.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2.17 Slough A355 route Appendix 1Appendix | 372 KB | Download |
PDF |
Financial Approval 2.17 Slough: A355 routeReport | 128 KB | DownloadRead as text |
Follow Berkshire Local Transport Body at Slough and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2023 | Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. | Approved | Open |
| 9 Nov 2023 | Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... | Noted | Open |
| 9 Nov 2023 | One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... | Noted | Open |
| 9 Nov 2023 | Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... | Agreed | Open |
| 13 Jul 2023 | Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.