CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Slough Borough Council
Berkshire Local Transport Body, Thursday 19 November 2015 at 4.00pm

Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21

Noted Committee 2 papers

Berkshire Local Transport Body noted this item on Thursday 19 November 2015. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

Resolved – The progress made on schemes given programme entry status, as set out in Appendix 1 to the report, be noted.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Berkshire Local Transport Body

Purpose of report

1. To report on the progress of the Thames Valley Berkshire Local Growth Deali, with particular reference to the schemes included in the Transport Packages of the Strategic Economic Planii.

2. The government subsequently announced £10.2 million further support to Thames Valley Berkshireiii. Growth Deal 2 included four new transport schemes worth a total of £7.5m, taking the headline figure for transport schemes to £102.1m. This report provides progress reports on all schemes, whether announced in GD1 or GD2.

3. £13.325m is approved for spending in 2015/16 and of the remainder £12.275m has already been approved for specific years in 2016/19; and £76.50m is indicative approval for five future years 2016/17 to 2020/21 but without a detailed profile.

4. The government has confirmed that TVB LEP has been given further freedoms and flexibilities in the management of the overall capital programme. There is now a Monitoring and Evaluation Plan which sets out responsibilities on the LEP and on individual scheme promoters for assessing the economic impact of the Growth Deal.

Recommendations

5. That you note the progress made on the schemes previously given programme entry status, as set out in Appendix 1

Other Implications

Financial

6. Thames Valley Berkshire LEP has been granted further freedoms and flexibilities in managing the Growth Deal Capital Programme. This means that we will receive an annual allocation of capital within which it will be our responsibility to manage the allocation to individual schemes. This is a positive development for TVB LEP and recognises the confidence that government has in our governance arrangements.

Item 7 BLTB 19 November 2015 Thames Valley Berkshire Local Growth Deal 2015/16-2020/21 7. The government has yet to confirm the allocation of funding to financial years beyond the allocation for 2015/16. An announcement covering the pre-allocated LTB amount, the GD 1 and GD 2 approvals is expected with the Autumn Statement.

Table 1: Available Finance for Transport Schemes in TVB Growth Deal

£m 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Total LTB previously 3.625 3.625 3.625 3.625 - - 14.500 approved Growth Deal 1 9.700 - - - - - 9.700 “Tail” of GD1 - 3.400 - - - - 3.400 schemes Indicative - 67.000 67.000 approval GD1 Indicative - 7.500 7.500 approval GD 2 Total 13.325 88.775 102.100

8. The allocation of the 2015/16 money to individual schemes is set out in Table 2 below.

Table 2: Growth Deal Financial Allocation for 2015/16

“Tail” of funding Allocation for Scheme commitment in 2015/16 £m 2016/17 £m 2.02 Bracknell: Warfield Link Road 3.500 - 2.03 Newbury: London Road Industrial Estate 0.500 1.400 2.07 Bracknell: Coral Reef Roundabout 2.100 - 2.08 Slough: Rapid Transit Phase 1 2.600 3.000 2.10 Slough: A332 Improvements 0.850 1.850 2.17 Slough: A355 route 1.775 2.625 2.19 Bracknell: Town Centre Improvements 2.000 - Total 13.325 8.475

9. Table 3 sets out our provisional allocation of scheme finance to financial years and is subject to alteration following the government’s confirmation of the Growth Deal funding profile.

Table 3 – Growth Deal 1 and 2 SEP Scheme Name Status 15/16 16/17 17/18 18/19 19/20 20/21 £m Ref Newbury: King’s Rd GD Full 2.01 - 1.000 1.340 - - - 2.340 Link Road 1 approval

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 445 KB Download
PDF
Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21Report 121 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 17 attended
MB
Cllr Marc Brunel-Walker Bracknell Forest CouncilCommittee Member, present
JK
Councillor John Kaiser Wokingham Borough CouncilCommittee Member, apologies, sent representative
SM
Councillor Sohail Munawar Slough Borough CouncilCommittee Member, present
TP
Councillor Tony Page Reading Borough CouncilCommittee Member, present
CR
Councillor Colin RaynerCommittee Member, present
GS
Cllr Garth Simpson West Berkshire CouncilCommittee Member, apologies, sent representative
SC
Steve Capel-Davies Thames Valley Berkshire LEPCommittee Member, present
CE
Charles Eales Thames Valley Berkshire LEPCommittee Member, apologies
IF
Ian Frost Thames Valley Berkshire LEPCommittee Member, present
PH
Peter Howe Thames Valley Berkshire LEPCommittee Member, present
GS
Graeme Steer Thames Valley Berkshire LEPCommittee Member, present
MT
Matthew Taylor Thames Valley Berkshire LEPCommittee Member, present

All 17 on the meeting page

On this subject at Slough

Search all
  1. Thames Valley Berkshire Local Growth Deal 2015/16 to 2020/21This decision
  2. Section 75 Agreement with the NHS Thames Valley Integrated Care Board to govern the delivery of the Better Care Fund 2026-2027Decided
  3. Thames Valley Spatial Development Strategy (SDS) Development and GovernanceDecided
  4. Thames Valley Devolution - Expression of InterestDecided
  5. Report from the Thames Valley Police and Crime CommissionerNoted
  6. Thames Valley Berkshire Capital Programme UpdateNoted

More from Slough Berkshire Local Transport Body

All decisions
MeetingDecisionOutcome
9 Nov 2023 Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. Approved Open
9 Nov 2023 Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... Noted Open
9 Nov 2023 One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... Noted Open
9 Nov 2023 Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... Agreed Open
13 Jul 2023 Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies