Financial Approval 2.11 and 2.12 Reading South Reading MRT Phases 1 and 2

Agreed Committee 2 papers

Berkshire Local Transport Body agreed this item on Thursday 19 November 2015. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

It was agreed to award the scheme full financial approval, and the written confirmation of the revised BCR from the independent assessors would be sent to the Clerk and placed on record. Resolved – That schemes 2.11 and 2.12 Reading: South Reading MRT Phases 1 and 2 be given full financial approval in the sum of £4,500,000 over two years (2016/17-2017/18) on the terms of the funding agreement set out in paragraph 12 step 5 of the report.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Berkshire Local Transport Body

Purpose of report

1. To consider giving financial approval to schemes 2.11 and 2.12 Reading: South Reading MRT Phases 1 and 2. This is one scheme that was split into two phases in anticipation of there being insufficient funds to approve the whole of the necessary works. In the event both phases 1 and 2 have received funding and the proposal is to manage this as one scheme through to completion.

2. The proposal is for the construction of sections of segregated bus-only highway alongside sections of the A33 in South Reading from M4 junction 11 to the Island Road Junction. This scheme will connect to the Mereoak Park and Ride south of the M4 and utilise the bus priority measures built into the design of junction 11. The scheme is designed to increase the capacity of the A33 to deliver journeys at peak hours by encouraging modal shift from private car to buses and is planned in conjunction with the green travel plans of, Madejski Stadium, Green Park and other major employment sites along the A33 corridor.

Recommendation

3. You are recommended to give schemes 2.11 and 2.12 Reading: South Reading MRT Phases 1 and 2 conditional financial approval in the sum of £4,500,000 over two years (2016/17-2017/18) on the terms of the funding agreement set out at paragraph 12 step 5 below. 4. The condition that will have to be met in order to gain full financial approval is that the BCR methodology be further reviewed and recalculated to the satisfaction of the independent assessor, and produce a BCR of 2.00 or more. Failing this, the scheme will have to be revised and represented to a future meeting of the BLTB.

Other Implications

Financial

5. Schemes 2.11 and 2.12 Reading: South Reading MRT Phases 1 and 2 were named schemes in the Thames Valley Berkshire Local Growth Deali announced on 7 July 2014.

6. This report recommends that Reading Council be authorised to draw down the capital sum £4,500,000 from the Local Transport Body funding for this scheme.

Item 5 BLTB 19 November 2015 Financial Approval 2.11 and 2.12 Reading South Reading MRT Ph 1&2 7. The funding agreement set out at paragraph 12 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.

Risk management

8. The risk management arrangements already put in place by the Local Transport Body are as follows:  The Assurance Frameworkii has been drafted following DfT guidance and has been approved by the DfT for use in allocating capital funds for transport schemes  White Young Green (WYG) have been appointed as Independent Assessors and have provided a full written report (see Appendix 1) on the full business case for the scheme  The funding agreement set out at paragraph 14, step 5 makes clear that the financial risk associated with implementation of the scheme rests with the scheme promoter.

Human Rights Act and Other Legal Implications

9. The scheme promoter is a local authority and they have to act within the law. Slough Borough Council will provide legal support for the BLTB, should any questions arise.

Supporting Information

10. The scheme will be carried out entirely by Reading Borough Council.

11. The full details of the scheme are available from the Reading BC websiteiii. A summary of the key points is given below:

Task Timescale Detailed design update January 2016 Procurement June 2016 Contractor appointed June 2016 Construction July 2016 Open to public November 2017

Activity Funder Cost (approx) Scheme development Reading Borough Council £0.35m Major scheme funding Berkshire Local Transport Body £4.50m Private sector funding s.106 and other sources £1.12m Total £5.97m

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
to Item 5 BLTB 19 November 2015 2.11 and 2.12 South Reading Mass TransitAppendix 1 605 KB Download
PDF
Financial Approval 2.11 and 2.12 Reading South Reading MRT Phases 1 and 2Report 154 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 17 attended
MB
Cllr Marc Brunel-Walker Bracknell Forest CouncilCommittee Member, present
JK
Councillor John Kaiser Wokingham Borough CouncilCommittee Member, apologies, sent representative
SM
Councillor Sohail Munawar Slough Borough CouncilCommittee Member, present
TP
Councillor Tony Page Reading Borough CouncilCommittee Member, present
CR
Councillor Colin RaynerCommittee Member, present
GS
Cllr Garth Simpson West Berkshire CouncilCommittee Member, apologies, sent representative
SC
Steve Capel-Davies Thames Valley Berkshire LEPCommittee Member, present
CE
Charles Eales Thames Valley Berkshire LEPCommittee Member, apologies
IF
Ian Frost Thames Valley Berkshire LEPCommittee Member, present
PH
Peter Howe Thames Valley Berkshire LEPCommittee Member, present
GS
Graeme Steer Thames Valley Berkshire LEPCommittee Member, present
MT
Matthew Taylor Thames Valley Berkshire LEPCommittee Member, present

All 17 on the meeting page

On this subject at Slough

Search all
  1. Financial Approval 2.11 and 2.12 Reading South Reading MRT Phases 1 and 2This decision
  2. Financial Approval: Scheme 2.37 Bracknell A322/A329 Corridor Improvements: Birch Hill Junction UpgradeApproved
  3. Financial Approval 2.47 Bracknell: Town Centre - "The Deck"Approved
  4. Financial approval GBF1 Slough: Langley High Street Widening Phase 3Approved
  5. Financial approval: Scheme 2.45 Langley High Street Widening Phase 2Approved
  6. Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban RealmApproved

More from Slough Berkshire Local Transport Body

All decisions
MeetingDecisionOutcome
9 Nov 2023 Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. Approved Open
9 Nov 2023 Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... Noted Open
9 Nov 2023 One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... Noted Open
9 Nov 2023 Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... Agreed Open
13 Jul 2023 Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies