Berkshire Local Transport Body, Thursday 19 November 2015 at 4.00pm

Financial Approval 2.19 Bracknell Town Centre Regeneration Infrastructure Improvements

Approved Committee 2 papers

Berkshire Local Transport Body approved this item on Thursday 19 November 2015. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

Resolved – (a) That scheme 2.19 Bracknell Town Centre Regeneration Infrastructure Improvements be given conditional financial approval in the sum of £2,000,000 in 2015-16 on the terms of the funding agreement set out at paragraph 14 step 5 in the report. (b) That the condition that would have to be met in order to gain full financial approval was that the independent assessor be satisfied that the following elements of a fully compliant Full Business Case had either been supplied or a properly documented reason for their absence had been supplied: i. Linsig Junction Assessments: an explanation of the application of this technique, the assumptions made, the validation used and the mitigation of any limitations; ii. Future Year Modelling: an explanation of the choice of future years used, the calculations employed and the derivation of future traffic flows; iii. Interpeak Modelling: an explanation of the application of this technique, the assumptions made, the validation used and the mitigation of any limitations; iv. WebTAG Dependent Development Unit: an explanation of the way this unit had been applied to the North section of the town centre redevelopment, the access to the new car park, and the new signalised junction of Millennium Way; v. Health Economic Assessment Tool (HEAT): an explanation of the application of this technique, the assumptions made, the validation used and the mitigation of any limitations; vi. Station Way Signalisation: Information on the surveys and validation of the Linsig at this junction; vii. Low and High Growth scenarios: an explanation of how these have been analysed, the assumptions made, the validation used and the mitigation of any shortcomings; viii. Air quality and noise assessments: an explanation of the evidence presented, the assumptions made, the validation used and the mitigation of any limitations. (c) That the Chair and Vice-Chair be given delegated authority to formally give full financial approval to the scheme, following confirmation from the independent assessors that the conditions in (b) had been resolved.
Word for word from the decision Slough published for this meeting. Source: democracy.slough.gov.uk

Follow this further

Built from Slough's papers

What the report saysPro

Report to Berkshire Local Transport Body

Purpose of report

1. To consider giving financial approval to scheme 2.19 Bracknell Town Centre Regeneration Infrastructure Improvements.

2. The scheme aims to bring forward transport infrastructure improvements linked to the town centre regeneration, and compliment them further with behaviour change initiatives. Crucially, leading stakeholders in the town centre regeneration, which is now under construction, have given a strong indication that securing this funding will reduce the joint financial burden, kick-start the development and deliver at least 3,540 retail and leisure jobs for local people.

Recommendation

3. You are recommended to give scheme 2.19 Bracknell Town Centre Regeneration Infrastructure Improvements conditional financial approval in the sum of £2,000,000 in 2015-16 on the terms of the funding agreement set out at paragraph 14 step 5 below.

4. The condition that will have to be met in order to gain full financial approval is that the independent assessor is satisfied that the following elements of a fully compliant Full Business Case have EITHER been supplied OR a properly documented reason for their absence has been supplied i) Linsig Junction Assessments: an explanation of the application of this technique, the assumptions made, the validation used and the mitigation of any limitations ii) Future Year Modelling: an explanation of the choice of future years used, the calculations employed and the derivation of future traffic flows iii) Interpeak Modelling: an explanation of the application of this technique, the assumptions made, the validation used and the mitigation of any limitations iv) WebTAG Dependent Development Unit: an explanation of the way this unit has been applied to the North section of the town centre redevelopment, the access to the new car park, and the new signalised junction on Millennium Way.

Item 6 BLTB 19 November 2015 Financial Approval 2.19 Bracknell Town Centre Regeneration Infrastructure Improvements v) Health Economic Assessment Tool (HEAT): an explanation of the application of this technique, the assumptions made, the validation used and the mitigation of any limitations vi) Station Way Signalisation: Information on the surveys and validation of the Linsig at this junction. vii) Low and High Growth scenarios: an explanation of how these have been analysed, the assumptions made, the validation used and the mitigation of any shortcomings. viii) Air quality and noise assessments: an explanation of the evidence presented, the assumptions made, the validation used and the mitigation of any limitations.

Other Implications

Financial

5. Scheme 2.19 Bracknell Town Centre Regeneration Infrastructure Improvements is a named scheme in the Thames Valley Berkshire Local Growth Deal 2i announced in January 2015.

6. This report recommends that Bracknell Forest Council be authorised to draw down the capital sum £2,000,000 from the Local Transport Body funding for this scheme.

7. The funding agreement set out at paragraph 14 step 5 sets out the roles and responsibilities, reporting and auditing arrangements, timing and triggers for payments, contributions from other funders, consequences of delay, consequences of failure, claw back, and evaluation requirements at one and five years on.

Risk management

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
to Item 6 BLTB 19 November 2015 2.19 Bracknell Town CentreAppendix 1 579 KB Download
PDF
Financial Approval 2.19 Bracknell Town Centre Regeneration Infrastructure ImprovementsReport 161 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 17 attended
MB
Cllr Marc Brunel-Walker Bracknell Forest CouncilCommittee Member, present
JK
Councillor John Kaiser Wokingham Borough CouncilCommittee Member, apologies, sent representative
SM
Councillor Sohail Munawar Slough Borough CouncilCommittee Member, present
TP
Councillor Tony Page Reading Borough CouncilCommittee Member, present
CR
Councillor Colin RaynerCommittee Member, present
GS
Cllr Garth Simpson West Berkshire CouncilCommittee Member, apologies, sent representative
SC
Steve Capel-Davies Thames Valley Berkshire LEPCommittee Member, present
CE
Charles Eales Thames Valley Berkshire LEPCommittee Member, apologies
IF
Ian Frost Thames Valley Berkshire LEPCommittee Member, present
PH
Peter Howe Thames Valley Berkshire LEPCommittee Member, present
GS
Graeme Steer Thames Valley Berkshire LEPCommittee Member, present
MT
Matthew Taylor Thames Valley Berkshire LEPCommittee Member, present

All 17 on the meeting page

On this subject at Slough

Search all
  1. Financial Approval 2.19 Bracknell Town Centre Regeneration Infrastructure ImprovementsThis decision
  2. Financial Approval: Scheme 2.37 Bracknell A322/A329 Corridor Improvements: Birch Hill Junction UpgradeApproved
  3. Financial Approval 2.47 Bracknell: Town Centre - "The Deck"Approved
  4. Financial approval GBF1 Slough: Langley High Street Widening Phase 3Approved
  5. Financial approval: Scheme 2.45 Langley High Street Widening Phase 2Approved
  6. Financial Approval for 2.29 Winnersh Triangle Park & Ride - Addendum 2 Access, Turning Head and Urban RealmApproved

More from Slough Berkshire Local Transport Body

All decisions
MeetingDecisionOutcome
9 Nov 2023 Minutes of the Meeting held on 13th July 2023Resolved – That the minutes of the meeting held on 13 th July 2023 be approved as a correct record. Approved Open
9 Nov 2023 Thames Valley Berkshire Capital Programme UpdateResolved – (a) That the progress made on schemes previously given programme entry status as set out in the report and... Noted Open
9 Nov 2023 One Year Evaluation ReportResolved – That the one-year impact report for Scheme 2.42 – South Wokingham Distributor Road – Eastern Gateway be no... Noted Open
9 Nov 2023 Approach to developing aspirations for prioritised strategic transport infrastructure schemes across BerkshireResolved – That the proposed approach to develop a list of prioritised strategic transport schemes across Berkshire t... Agreed Open
13 Jul 2023 Introduction to Berkshire Local Transport Body - Its Role and PurposeResolved – That the introduction to BLTB and a vote of thanks to Councillor Page be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies